The present invention relates to a tire management apparatus, a tire management method, and a tire management program.
A technique is known that estimates the amount of abrasion of aircraft tires (Patent Literature 1). The method disclosed in Patent Literature 1 acquires plural kinds of abrasion energy corresponding to plural running states (such as a touching-down state, a deceleration state after touching down, and a taxiing state) classified depending on the conditions of use, and estimates the amount of abrasion of the respective aircraft tires based on the acquired abrasion energy.
Patent Literature 1: Japanese Unexamined Patent Application Publication No. 2013-113724
The aircraft tires are replaced when the amount of abrasion reaches a predetermined value. A delay in replacing operation or an insufficiency of the number of the aircraft tires in the stock may be caused if a certain number of tires or greater are replaced simultaneously at the same replacement time. To deal with such a problem, appropriate planning is required for the replacing operation by recognizing the replacement time. The problem described above is not limited to be applied to the aircraft tires, and is also applied to any tires attached to vehicles such as automobiles, trucks, and buses.
To solve the conventional problems described above, the present invention provides a tire management apparatus, a tire management method, and a tire management program contributing to planning for replacing operation by recognizing a replacement time of tires.
A tire management apparatus (10) according to the present invention includes a remaining tread amount acquisition unit (12) configured to acquire a remaining tread amount of tires, a traveling information acquisition unit (13) configured to acquire traveling information of moving objects to which the tires are attached, a replacement time calculation unit (14) configured to calculate a replacement time of the tires in accordance with the remaining tread amount and the traveling information, and a notification unit (15) configured to notify a particular notification target of information on the number of the tires to be replaced at the replacement time when the number exceeds a threshold.
The present invention can contribute to the planning for the operation of replacing tires that is commonly a non-planning operation.
Hereinafter, some embodiments according to the present invention are described with reference to the drawings. The same elements illustrated in the drawings are denoted by the same reference numerals, and overlapping explanations are not made below.
1. Configuration Example of Tire Management System
An example of a configuration of a tire management system 1 is described below with reference to
The tire management apparatus 10 is a general-purpose computer, for example, which includes a processor including a CPU and a memory including a read-only memory (ROM) and a random-access memory (RAM). The CPU reads out a program stored in the ROM to the RAM and executes the program. The tire management apparatus 10 may be either a built-in terminal device or a mobile terminal device easy to carry (such as a smartphone). The tire management apparatus 10 may also be a server. The tire management apparatus 10 manages tires attached to a plurality of moving objects. As illustrated in
The present embodiment is illustrated below with a case in which the tires managed by the tire management system 1 are aircraft tires 31 attached to a plurality of aircrafts, but the tires managed by the tire management system 1 are not limited to the aircraft tires 31. In other words, the moving objects to which the tires managed by the tire management system 1 are attached are not limited to aircrafts. The moving objects to which the tires managed by the tire management system 1 may be any of automobiles, trucks (including off-road dump trucks), and buses, for example. The term “aircraft” can be simply referred to below as a “plane”.
The communication unit 11 is an interface connected to a network 20 to communicate with the airline 30 so as to send/receive data therebetween. The communication unit 11 acquires various kinds of pieces of information from the airline 30 via the network 20. The remaining tread amount acquisition unit 12 acquires the remaining tread amount of the aircraft tires 31 by use of the information acquired from the airline 30. The traveling information acquisition unit 13 acquires traveling information of an aircraft to which the aircraft tires 31 are attached from the airline 30. The traveling information of the aircraft includes a flight schedule of the aircraft. The replacement time calculation unit 14 calculates a replacement time of the aircraft tires 31 in accordance with the remaining tread amount acquired by the remaining tread amount acquisition unit 12 and the traveling information acquired by the traveling information acquisition unit 13. The notification unit 15 notifies a particular notification target of information on the number of the aircraft tires 31 to be replaced at the replacement time calculated by the replacement time calculation unit 14 when the number exceeds a threshold. The particular notification target in the present embodiment is illustrated with the airline 30, but is not limited to this case. For example, the particular notification target may be a company that provides maintenance repair overhaul (MRO) service. The company provides the MRO service including repair, inspection, and maintenance of aircraft tires and wheels. The particular notification target may include the airline 30 and the company that provides the MRO service. When the particular notification target includes the airline 30 and the company that provides the MRO service, the tire management apparatus 10, the airline 30, and the company that provides the MRO service are connected to each other via the network 20.
The notification unit 15 also has a proposal function that proposes, to the particular notification target, a change of the replacement time of the aircraft tires 31 when the number exceeds the threshold.
The network 20 is a communications network capable of sending/receiving various kinds of information. For example, the network 20 is implemented by various types of communication lines installed by telecommunications carriers, such as dedicated lines, public switched telephone networks, satellite communication lines, and mobile communication lines.
The communication unit 11, the remaining tread amount acquisition unit 12, the traveling information acquisition unit 13, the replacement time calculation unit 14, and the notification unit 15 each can be fabricated by single or plural processing circuits. The respective processing circuits include a programmed processing device, such as a processing device including an electric circuit. The respective processing circuits also include an application-specific integrated circuit (ASIC) configured to execute the functions described herein and a device including circuit components.
An example of a method of calculating the replacement time of the aircraft tires is described below with reference to
As shown in
As shown in
Since the abrasion energy per flight has been confirmed, the remaining number of usage of the respective aircraft tires (can be referred to below as a “remaining number of flights”) can be calculated. The traveling information acquisition unit 13 acquires the flight schedule of the plane AAA from the airline 30. The traveling information acquisition unit 13 uses the flight schedule, so as to calculate the number of days by which the remaining tread amount of the respective aircraft tires reaches a predetermined value or smaller (can be simply referred to below as a “remaining number of days”).
The aircraft tires are replaced when the remaining tread amount reaches the predetermined value or smaller. As described above, the tire management apparatus 10 can calculate the remaining number of days. The tire management apparatus 10 thus can calculate the date on which the aircraft tires are replaced (can be referred to below as a “replacement date”).
Next, a notification of the replacement time (the replacement date) and a proposal for a change of the replacement time of the aircraft tires are described below with reference to
As shown in
A delay in replacing operation may be caused if a predetermined number of aircraft tires or greater needs to be replaced simultaneously at the same replacement time. A case is presumed below in which the number of the aircraft tires (threshold) determined to be replaced smoothly is 20. In such a case, a delay in the replacing operation could be caused on January 4 (35 aircraft tires), on January 5 (29 aircraft tires), and on January 11 (27 aircraft tires). There is sufficient time enough to execute the replacing operation on the other days since the number of the aircraft tires to be replaced is the threshold (20 aircraft tires) or less.
The notification unit 15 in the present embodiment, when the number of the aircraft tires to be replaced at a specific replacement time exceeds the threshold, notifies the airline 30 of this information. This enables the planning for the operation of replacing the aircraft tires that is commonly a non-planning operation. This operation further enables a preparation of new aircraft tires for the replacement during the flight of the corresponding aircraft, for example, so as to allot resources including operators and equipment to appropriate locations.
While the notification unit 15 in the present embodiment notifies the airline 30 of the replacement time per aircraft tire regardless of whether the number of the aircraft tires to be replaced exceeds the threshold, together with alert particularly regarding at least either (may be both of) the specific replacement time when exceeding the threshold or (and) the aircraft tires required to be replaced at the specific replacement time when exceeding the threshold, but the present embodiment is not limited to this case. For example, the notification unit 15 may only notify the airline 30 of at least either (or both of) the specific replacement time when exceeding the threshold or (and) the aircraft tires required to be replaced at the specific replacement time when exceeding the threshold.
The notification unit 15 in the present embodiment may propose the change of the replacement time of the aircraft tires to the airline 30. For example, the notification unit 15 can propose the acceleration of the replacement time of the aircraft tires to the airline 30. A case is presumed below in which the number of the aircraft tires exceeding the threshold on January 4 is 15, and the number of the aircraft tires exceeding the threshold on January 5 is 9. As shown in
Next, an example of operation of the tire management apparatus 10 is described below with reference to
In step S101, the tire management apparatus 10 acquires the abrasion energy of the aircraft tires, and predicts the abrasion amount of the aircraft tires based on the abrasion energy. The tire management apparatus 10 acquires the remaining tread amount of the aircraft tires by use of the predicted abrasion amount.
The process proceeds to step S102, and the tire management apparatus 10 acquires the flight schedule of the aircraft from the airline 30. The process proceeds to step S103, and the tire management apparatus 10 calculates the replacement time of the aircraft tires in accordance with the abrasion amount and the flight schedule. The process proceeds to step S104, and the tire management apparatus 10 notifies, when the number of the aircraft tires to be replaced at the replacement time exceeds the threshold, the particular notification target of the specific replacement time when exceeding the threshold and/or the aircraft tires required to be replaced at the specific replacement time. The tire management apparatus 10 notifies, regardless of whether the number of the aircraft tires to be replaced exceeds the threshold, the particular notification target of the information particularly together with the alert regarding the specific replacement time when exceeding the threshold and/or the aircraft tires required to be replaced at the specific replacement time when exceeding the threshold.
2. Operational Effects
The operational effects of the tire management apparatus 10 are described below.
The tire management apparatus 10 notifies the particular notification target (such as the airline 30) of the information on the number of the aircraft tires to be replaced at the replacement time when the number exceeds the threshold. This enables the planning for the operation of replacing the aircraft tires that is commonly a non-planning operation. This operation further enables the preparation of the new aircraft tires for replacement during the flight of the corresponding aircraft, for example, so as to allot the resources including operators and equipment to appropriate locations.
The threshold is the information on the remaining number of the aircraft tires in the stock at the replacement time, for example. Setting such a threshold can allow the planning for the operation of replacing the aircraft tires.
The tire management apparatus 10 may propose, to the particular notification target, the change of the replacement time of the aircraft tires when exceeding the threshold. As shown in
The tire management apparatus 10 may propose the acceleration of the replacement time of the aircraft tires upon the change of the replacement time. This can avoid the concentration of the aircraft tires to be replaced on a specific replacement time, so as to execute the replacement operation smoothly.
The tire management apparatus 10 calculates the remaining tread amount of the aircraft tires according to the remaining tread amount of new aircraft tires and the predicted abrasion amount. The tire management apparatus 10 calculates the replacement time in accordance with the remaining tread amount calculated as described above and the traveling information. This improves the accuracy of calculating the replacement time accordingly.
The tire management apparatus 10 also calculates the remaining number of flights that the corresponding aircraft can take in accordance with the remaining tread amount. The tire management apparatus 10 acquires the flight schedule of the corresponding aircraft from the airline 30. The tire management apparatus 10 calculates the replacement time of the aircraft tires in accordance with the remaining number of flights and the flight schedule. This improves the accuracy of calculating the replacement time accordingly.
While the present embodiment has been illustrated above with the case in which the traveling information of the aircraft includes the flight schedule, the flight schedule may be either a future flight schedule or a past flight schedule. The tire management apparatus 10, if cannot acquire the future flight schedule, may predict the future flight schedule based on the past flight schedule.
The present embodiment has been illustrated above with the case in which the replacement time is one day, but is not limited to this case. The replacement time may include several days. When an average number of the aircraft tires to be replaced for three days exceeds a threshold, for example, the tire management apparatus 10 may propose the change of the replacement time. In particular, the average number of the aircraft tires to be replaced for three days from January 3 to January 5 (27 aircraft tires) exceeds the threshold (20 aircraft tires), as shown in
The present embodiment has been illustrated above with the case in which the tire management apparatus 10 predicts the remaining tread amount by use of the predicted abrasion amount, but is not limited to this case. The remaining tread amount may be obtained by measurement.
While the present invention has been described above by reference to the embodiment, it should be understood that the present invention is not intended to be limited to the descriptions and the drawings composing part of this disclosure. Various alternative embodiments, examples, and technical applications will be apparent to those skilled in the art according to this disclosure.
For example, the tire management apparatus 10 has been illustrated with the case of acquiring the information of the aircraft from the airline 30, but is not limited to this case. The tire management apparatus 10 may acquire the information of the aircraft from any other source instead of the airline 30.
This example has been illustrated above with the case of calculating the number of the aircraft tires to be replaced at the replacement time for each size of the aircraft tires (the size is one type in the example shown in
This example has been illustrated above with the case in which the notification unit 15 proposes the change of the replacement time of all of the aircraft tires that exceed the threshold, as shown in
The wheels can be replaced simultaneously together with the aircraft tires. The threshold thus may be set in view of the number of wheels to be replaced. When the number of the aircraft tires and the wheels to be replaced exceeds a threshold, the notification unit 15 may notify the particular notification target of this information. This enables the planning for the operation of replacing the aircraft tires and the wheels that is a non-planning operation.
This application is based upon and claims the benefit of priority from Japanese Patent Application No. 2019-170316, filed on Sep. 19, 2019, the entire contents of which are incorporated herein by reference.
Number | Date | Country | Kind |
---|---|---|---|
2019-170316 | Sep 2019 | JP | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/JP2020/030124 | 8/6/2020 | WO |