The following invention relates to a tool and an associated method of making operations in subsea wells possible, without the use of a cable or coiled tubing connected topside to a rig, ship or platform. In particular, the present invention addresses the requirement to maintain two independent well barrier envelopes—without the use of cut and seal functions. This creates an opportunity to use lighter and more efficient equipment for installing, testing, well maintenance, wellhead stacks and associated operations. This will make it possible to move traditional operations from heavy drilling rigs to lighter vessels, such as boats and ships. However, the invention also makes possible use of traditional work-over systems as an alternative contingency, as alternative, independent operation, should this new technology not complete the operation as intended.
The background for the invention is the petroleum industry's demand for cost reducing subsea operations with corresponding or higher security levels, compared to today's practice. It is well known that a substantial capital investment, in both equipment and operational costs, is required in order to develop and operate a subsea oil and gas field that typically consists of several subsea wells and subsea Xmas trees. A large part of such a subsea field development cost relates to the drilling-, completion-, production- and maintenance operations of wells. Traditionally the industry has used larger drilling rigs with its own drill systems to drill and penetrate reservoirs, followed by installation of subsea wellhead and internal casings. After such installation, a subsea Xmas tree is connected to the subsea wellhead to control production after startup. It has been common to install also the Xmas tree from the drilling rig. The start of production from the well normally takes place with so-called workover systems (service system), which is connected to the Xmas tree and which gives a mechanical access from the drilling rig to the subsea well and reservoir. This access allows the possibility of internally running tools on a wire (wireline operation) or a smaller work pipe (coiled tubing—typically 2″ pipe) down into the well, by means of a workover system, for pulling plugs and to open towards reservoir for production. Such a workover system may also be used towards maintenance work inside the well for controlling or optimizing production throughout the lifetime of the well. Common to these operations and systems is that they result in high cost to manufacture, operate and maintain.
Consequently, there is a need for solutions that are useful for installation and testing of subsea Xmas trees, as well as maintenance of wells, without the use of a drilling rig. This technology or equipment shall therefore make it possible to move such operations to a lighter vessel or ship, which is not necessarily rated to handle hydrocarbons on the deck of the vessels. It would also be beneficial to let the drilling rig be used for its intended purpose—namely to drill the well and to install casing and production tubing. Further optimization of the drilling rig is achieved, as there is no need to change between the different types of risers in use. The logistics on the drilling rig will also become easier as the subsea Xmas tree is not lifted onboard, as this requires additional space and handling of heavy loads, typically around 30-50 metric tons. The heavy load and size of a work-over system is also substantial, as such a system requires several containers on the deck, as well as large reels with umbilicals.
It will be desirable to introduce new technology that both reduces operational costs, has less weight and size, and which does not expose personnel to equipment carrying well pressure. This will reduce the requirements for lifting and handling system on the vessel, as well as improve health, safety and environment (HSE). One main reason for the large weight for drilling and work-over systems is the requirement to cut and seal the working string that penetrates the barrier envelopes as needed. An example of this would be a loss of well control, so that main safety valves must be activated and shut in or isolate the well from the environment. These safety valves are known as elements of a Blow Out Preventer (BOP) or a Lower Riser Package (LRP). The weight of a BOP may be around 200-500 tons, while an LRP normally weighs around 30-50 tons. The present invention is intended not to penetrate the barrier envelopes, in order to avoid the cutting functionality requirement. This will result in substantially lighter equipment for maintaining well control. Another desired function is to avoid opening of the well, or it being elevated to the vessel. It will, on the other hand, be appropriate to include the possibility of allowing for traditional systems to take over the operation as a back-up solution, should the new technology not complete the operation as planned.
Alternative systems have been proposed, and the nearest prior art is disclosed in the publications U.S. Pat. Nos. 6,719,059 B2, 3,638,722, 7,063,157 B2, US2011/0315392 A1, US2012/0037374 A1, WO2004/003338 A1 and WO2012/115891 A2. None of these publications describes a tool that does not require cutting functions and which simultaneously has the possibility of intervening the well with an independent, alternative operation (back-up).
The object of the invention is to enable a closed well operation. A closed operation refers to activities in a subsea well without the use of cable or a riser extending to surface, penetrating a well barrier. The invention comprises a hoist arrangement, a sealing element and an upper connection point for alternative operation. The placement, setup and the method of use of these are essential for the invention. When conducting a closed well operation it is imperative to have a secondary method to pull out the well tool, should the primary method fail. By placing the hoist arrangement on the side of the main bore and the seal element above in the main bore, one achieves a safe alternative operation of the well tool. A primary method is to use the shown tool (3) to perform mechanical operation in a well, such as pulling a plug that sits in the well after installation of the Xmas tree the wellhead. If this operation should fail, the tool will still maintain the well isolated from its surroundings, while succeeding secondary operation may be performed by connecting a traditional workover system on top of the illustrated tool (3). Well access is possible by opening, preferably, a valve that sits in the top of the tool, which is used in the primary operation. The plug may thus be pulled with a traditional wire line operation, which is an independent and recognized method.
The basis of the invention is illustrated in
The invention placed in a larger system as shown in
Operational Procedure
The method of closed well operation with the invention is illustrated in
Number | Date | Country | Kind |
---|---|---|---|
20150229 | Feb 2015 | NO | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/NO2016/000007 | 2/17/2016 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2016/133401 | 8/25/2016 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
3602300 | Jaffe | Aug 1971 | A |
3638722 | Talley, Jr. | Feb 1972 | A |
6719059 | Dezen et al. | Apr 2004 | B2 |
7063157 | Bartlett | Jun 2006 | B2 |
20080264630 | Lavrut et al. | Oct 2008 | A1 |
20110315392 | Edwards | Dec 2011 | A1 |
20120037374 | Schuurman et al. | Feb 2012 | A1 |
20120181038 | Edwards | Jul 2012 | A1 |
Number | Date | Country |
---|---|---|
1 696 101 | Aug 2006 | EP |
1.536.233 | Apr 1967 | FR |
2 152 979 | Aug 1985 | GB |
2 284 257 | May 1995 | GB |
2 454 915 | May 2009 | GB |
WO 9214029 | Aug 1992 | WO |
WO 2004003338 | Jan 2004 | WO |
WO 2004065757 | Aug 2004 | WO |
WO 2009016353 | Feb 2009 | WO |
WO 2010050827 | May 2010 | WO |
WO-2010050827 | May 2010 | WO |
WO 2012115891 | Aug 2012 | WO |
WO 2013036145 | Mar 2013 | WO |
Number | Date | Country | |
---|---|---|---|
20180038185 A1 | Feb 2018 | US |