Turbine installation method

Information

  • Patent Grant
  • 8784005
  • Patent Number
    8,784,005
  • Date Filed
    Thursday, April 16, 2009
    15 years ago
  • Date Issued
    Tuesday, July 22, 2014
    10 years ago
Abstract
The present invention provides a method of installing a hydroelectric turbine onto the seabed or the like while ensuring that a pre-laid electrical cable connected to the turbine prior to lowering to the seabed is not damaged during installation of the turbine, the method involving lowering the turbine towards the seabed while simultaneously displacing the turbine in order to maintain tension in the electrical cable.
Description
FIELD OF THE INVENTION

The present invention is concerned with an improved method of installing a hydroelectric turbine onto the seabed or the like; and in particular a method which improves the handling of the electrical cable connected between the hydroelectric turbine and an onshore power station to which electricity generated by the turbine is supplied.


BACKGROUND OF THE INVENTION

Due to the environmental damage which has been inflicted on the planet as a result of the burning of fossil fuels, renewable energy has finally begun to be given significant attention, with many projects being developed around solar energy, wind energy, and tidal power. Of these alternative forms of energy, tidal power is arguably the most attractive, given that tidal flows are entirely predictable and constant, unlike wind or solar energy which are relatively intermittent and therefore less dependable.


However, harnessing tidal energy does provide its own challenges, in particular with respect to the installation and maintenance of tidal power generators, for example hydro-electric turbines, which by the very nature of the operation of same must be located in relatively fast flowing tidal currents, and more than likely located on the seabed. In addition, in order to be economically viable these turbines must be built on a large scale. Essentially however these turbines must deliver power back to shore for eventual supply into the grid. The level of electricity generated by the turbines renders working on the electrical systems a hazardous operation, and this is magnified by the location of the turbines under water on the seabed, and in regions of fast flowing tides. These regions of fast flowing tides are often found in isolated locations making getting to and from the site a time consuming, dangerous, and therefore expensive undertaking. In addition, the process of installing and removing such turbines generally requires the use of multiple vessels and associated heavy machinery, in addition to experience divers. Furthermore, these turbines will generally need to be deployed in multiples in the form of a tidal turbine farm in order to be economically viable. Thus the installation process is multiplied by the number of turbines to be installed. The availability of such equipment and divers is relative scare, and thus it is extremely desirable to reduce the time and equipment necessary to perform the installation and removal of tidal turbines.


Due to both the relatively large electric currents generated by hydroelectric turbines, and the extremely harsh conditions under which the turbines and associated electrical cables are exposed, the electrical cable extending onshore from each turbine must be relatively large and robust. As a result of the diameter of the cable, which may be in the region of 300-500 mm, and given the length of cable involved, the weight of the cable is significant. The handling of the cable is therefore both a difficult and time-consuming operation, made even more difficult by the tidal conditions present at the sites where hydroelectric turbines are deployed. The cabling is also relatively inflexible and so the mishandling of same can quickly and easily result in kinking/knotting of the cable, thus rendering same permanently damaged and therefore requiring replacement.


It is therefore an object of the present invention to provide a method of installing a hydroelectric turbine, which method avoids damage to the cable during the installation process.


SUMMARY OF THE INVENTION

The present invention therefore provides a method of installing a hydroelectric turbine system at a tidal site comprising the steps of:


connecting a pre-laid power cable to the system;


lowering the system towards a deployment site while simultaneously displacing the system in line with the direction of tidal flow such as to maintain tension in the cable.


Preferably, the method comprises positioning the system substantially above the deployment site prior to connecting the cable.


Preferably, the method comprises lowering the system from a deployment vessel and simultaneously displacing the deployment vessel such as to maintain tension in the cable.


Preferably, the deployment vessel comprises a source of propulsion.


Preferably, the method comprises the step of positioning an anchor to be upstream of the system during the lowering step; directly or indirectly connecting the system to the anchor; and using the anchor to achieve the displacement of the system during the lowering thereof.


Preferably, the method comprises positioning the anchor on the seabed.


Preferably, the method comprises the steps of towing the deployment vessel behind a towing vessel; and utilising the towing vessel to achieve the displacement of the deployment vessel.


Preferably, the method comprises the step of winching the deployment vessel towards the towing vessel during lowering of the system in order to achieve the displacement of the deployment vessel.


Preferably, the method comprises the step of securing the towing vessel to the anchor and pulling the towing vessel towards the anchor to at least partially achieve the displacement of the deployment vessel.


Preferably, the deployment vessel or the towing vessel comprises a dynamic positioning vessel.


Preferably, the method comprises the step of marking the location of the pre-laid cable with a floatation device.


Preferably, the method comprises lowering the system during a running tide.


Preferably, the method comprises the step of laterally displacing the system prior to or as part of final positioning of the system at the deployment site.


As used herein, the term “hydroelectric turbine system” is intended to mean either a hydroelectric turbine mounted on a base, which can be lowered together onto the seabed; the base in isolation from the turbine, which may be lowered to the seabed and the turbine subsequently lowered into position onto the base; or the turbine in isolation from the base, to be lowered onto the previously located base.





BRIEF DESCRIPTION OF THE DRAWINGS


FIG. 1 illustrates a schematic side elevation of a hydroelectric turbine system in the early stages of installation and according to the method of the present invention; and



FIG. 2 illustrates a schematic illustration of the method of deployment shown in FIG. 1, with the hydroelectric turbine system partially lowered toward the seabed.





DETAILED DESCRIPTION OF THE DRAWINGS

Referring now to the accompanying drawings, there is illustrated a method of installing a hydroelectric turbine 10 onto the seabed B at a tidal site according to a preferred embodiment of the invention. While the following description refers to installing the turbine 10 on the seabed B it will be appreciated that the method of the invention may be employed at any other suitable or desired location, for example installing the turbine 10 onto a river bed or the like.


Referring now in particular to FIG. 1, the method of the present invention involves transporting the turbine 10 into a position substantially above a tidal deployment site S on the seabed B where the turbine 10 is to be located during use. Prior to transporting the turbine 10 into position above the tidal deployment site S an electrical cable C is pre-laid on the seabed B. The processes involved in laying the cable C from an onshore location, or from some other location, to the deployment site S are well known and will not be described in any detail hereinafter. The final stretch of the cable C leading to the deployment site S, for example the last 100 meters, is laid substantially in line with the direction of the prevailing tide T. In order to allow the location and retrieval of the free end of the cable C it is preferable that a flotation device in the form of a buoy (not shown) or the like is tethered at or adjacent the free end of the cable C and therefore locatable on the surface of the water W once the turbine 10 is brought into position above the tidal deployment site S. It is also envisaged that it may be more practical to attach an umbilical or extension (not shown) onto the end of the cable C, and that the umbilical/extension would then be the portion that gets raised and lowered from the seabed B. The cable C may be used to take power directly ashore, or for daisy chaining the turbine 10 to one or more additional turbines (not shown).


With the cable C pre-laid to the deployment site S the turbine 10 is, as mentioned above, brought into position substantially above the deployment site S. In the preferred embodiment illustrated the turbine 10 is carried by a deployment vessel 12 which may be of any suitable form and, in the embodiment illustrated, is in the form of a non-powered barge 12. The deployment vessel 12 may however comprise a source of propulsion. A towing vessel in the form of a tug 14 is used in order to tow the turbine 10 and barge 12 into position, and in the embodiment illustrated, against the running tide T. In this embodiment a simple tow line 16 is connected between the tug 14 and the barge 12, and may be adjusted in length in order to make small corrections to the position of the turbine 10 and barge 12. The tug 14 could however be replaced with a dynamic positioning vessel (not shown) which could then utilise GPS in order to accurately maintain a desired position during the installation process. The turbine 10 may be releasably connected to the barge 12 by any number of suitable arrangements, and the details of the connection are not material to the method of the invention, and so will not be described in detail hereinafter.


Prior to towing the turbine 10 into position above the deployment S at least one anchor 18 is installed, in the embodiment illustrated, at a location on the seabed B upstream of the tidal deployment site S with respect to the direction in which the tide T is flowing during the installation. The anchor 18 may be of any suitable form, and in the embodiment illustrated is in the form of a simple rock-type anchor 18. However, the type and/or size of anchor 18 may vary depending on the conditions on the seabed B. Again in order to mark the position above the water W of the anchor 18 it is preferable that a tethered buoy (not shown) or similar marker is secured to the anchor 18, and for reasons described hereinafter.


Once the tug 14 has positioned the turbine 10 and barge 12 above the deployment site S the tug 14 is connected to the anchor 18 via an anchor line 20. This is achieved simply by retrieving the buoy (not shown) connected to the anchor 18 onto the tug 14 and then suitably securing the anchor line 20 to the tug 14. The anchor 18 now allows the tug 14, and therefore the turbine 10 and barge 12, to hold position against the running tide T. It should however be noted at this point, and as will become clear from the following description of the method of installation of the present invention, that the tug 14 may be dispensed with, and in such a scenario the vessel 12 would be connected directly to the anchor 18. This is a possibility regardless of whether the vessel 12 has a source of propulsion or not.


Once the turbine 10 and vessel 12 are secured against the running tide T by the anchor 18, the free end of the cable C (or umbilical) is recovered to the surface and electrically connected to the turbine 10 in known manner. The cable C may be recovered using a conventional winch arrangement provided on the barge 12, or may be achieved by a separate support vessel (not shown). At this point the turbine 10 is prepared for lowering to the seabed B. In the embodiment illustrated the turbine 10 is pre-mounted on a base 22 which will support the turbine 10 on the seabed B during use. Thus in the embodiment illustrated it is the base 22 which is used to secure the turbine 10 to the barge 12. The turbine 10 and base 22 together define a hydroelectric turbine system. It is envisaged that the cable C could be connected to the base 22, with a suitable connection then being provided between the base 22 and the turbine 10.


Referring then to FIG. 2 the turbine 10 and base 22 are now lowered towards the seabed B. This may be achieved by any suitable means, and in the embodiment illustrated a number of support lines 24 are connected between the barge 12 and the base 22. The barge 12 is therefore provided with a corresponding number of winches (not shown) which are operable to raise and lower the support lines 24, and therefore raise and lower the base 22 and turbine 10 towards or away from the seabed B. In the embodiment illustrated the turbine 10 and base 22 are connected in an under slung arrangement to the barge 12 in order to allow the turbine 10 and base 22 to be quickly and easily lowered away from the barge 12 towards the seabed B. Any other suitable arrangement may however be employed.


While the turbine 10 is being lowered towards the seabed B it is simultaneously displaced in line with the direction of tidal flow, and in the embodiment illustrated forwardly against the running tide T and towards the anchor 18, such as to maintain tension in the cable C. This is achieved by either pulling the tug 14 forwardly on the anchor 18, or by shortening the tow line 16 between the tug 14 and the barge 12, or a combination of the above-mentioned procedures. However as mentioned above, the tug 14 may be omitted and the barge 12 connected directly to the anchor 18. In this case the line (not shown) connecting the barge 12 to the anchor 18 would be used to pull the barge 12 forward against the tide T. In either scenario, the turbine 10 will be lowered towards the seabed B along an arced path with the cable C remaining in line with the direction of tidal flow. This path ensures that tension is maintained in the electrical cable C connected to the turbine 10 or base 22. This tension ensures that no kinking or knotting of the cable C can occur during the lowering of the turbine 10. Once the turbine 10 is positioned on the seabed B each of the support lines 24 can be disconnected therefrom and winched back up onto the barge 12. At this point the turbine 10 may begin operation and feeding power onshore via the cable C, or to any other desired location. At this point, the cable C should be in a straight line with respect to the direction of tidal flow T, and under tension in order to prevent any undue movement thereof during operation.


It will be appreciated that the above described method of installation could be achieved in the absence of the anchor 18, although with greater difficulty. The tug 14, or preferably dynamic positioning vessel (not shown) could be used to initially hold the position of the turbine 10 and barge 12 against the tide T while the cable C is connected to the turbine 10. Once lowering of the turbine 10 is commenced the tug 14 could then pull the barge 12 forwardly in order to achieve the above mention arced path of the turbine 10.


If it is desired to relocate the turbine 10 for whatever reason, this can be achieved before the support lines 24 are disconnected from the base 22. Relocation may be required for example due to an undesirable attitude of the base 22 following initial installation on the seabed B. Due to the configuration of the cable C, where for example the last 100 meters or the like is in a straight line, the base 22 can be raised slightly off the seabed B and the tug 14 used to reposition the barge 12 laterally of the original position.


In order to remove the turbine 10 from the seabed B, for example for maintenance or replacement, the above procedure is simply reversed.


It is also envisaged that the method of the present invention could be implemented with the tide flowing in the opposite direction to that described and shown with respect to FIGS. 1 and 2. In this situation, the towing vessel 14, and anchor 18 if employed, would need to be on the other side of the barge 12 to that shown in FIGS. 1 and 2, in order to be able to hold the barge 12 in a substantially fixed position over the deployment site S. When lowering the turbine 10 towards the seabed B the tide could be used to effect displacement of the turbine such as to maintain tension in the cable C. This could be achieved for example by feeding out and therefore lengthening the towing line 16 and/or anchor line 20, and simply allowing the tide to carry the barge 12, and therefore the turbine 10, with the tide in order to maintain tension in the cable C. Again this arrangement could be effected without the use of the anchor 18.

Claims
  • 1. A method of installing a hydroelectric turbine system at a tidal site comprising the steps of: connecting a pre-laid power cable to the system;lowering the system towards a deployment site during a running tide while simultaneously displacing the system in line with the direction of tidal flow such that the cable is laid substantially in line with the direction of the prevailing tide and as to maintain tension in the cable.
  • 2. The method of claim 1 comprising positioning the system substantially above the deployment site prior to connecting the cable.
  • 3. The method of claim 1 comprising lowering the system from a deployment vessel and simultaneously displacing the deployment vessel such as to maintain tension in the cable.
  • 4. The method of claim 3 in which the deployment vessel comprises a source of propulsion.
  • 5. The method of claim 3 comprising the steps of towing the deployment vessel behind a towing vessel; and utilising the towing vessel to achieve the displacement of the deployment vessel.
  • 6. The method of claim 5 comprising the step of winching the deployment vessel towards the towing vessel during lowering of the system in order to achieve the displacement of the deployment vessel.
  • 7. The method of claim 5 comprising the steps of positioning an anchor to be upstream of the system during the lowering step; securing the towing vessel to the anchor; and pulling the towing vessel towards the anchor to at least partially achieve the displacement of the deployment vessel.
  • 8. The method of claim 5 in which the deployment vessel or the towing vessel comprises a dynamic positioning vessel.
  • 9. The method of claim 1 comprising the step of positioning an anchor to be upstream of the system during the lowering step; directly or indirectly connecting the system to the anchor; and using the anchor to achieve the displacement of the system during the lowering thereof.
  • 10. The method of claim 9 comprising positioning the anchor on the seabed.
  • 11. The method of claim 1 comprising the step of marking the location of the pre-laid cable with a floatation device.
  • 12. The method of claim 1 comprising laterally displacing the system prior to or as part of final positioning of the system at the deployment site.
  • 13. A method of installing a hydroelectric turbine system at a tidal site comprising the steps of: connecting a pre-laid power cable to the system;lowering the system towards a deployment site while simultaneously displacing the system in line with the direction of tidal flow such as to maintain tension in the cable; andpositioning an anchor to be upstream of the system during the lowering step; directly or indirectly connecting the system to the anchor; and using the anchor to achieve the displacement of the system during the lowering thereof.
  • 14. A method of installing a hydroelectric turbine system at a tidal site comprising the steps of: connecting a pre-laid power cable to the system;lowering the system towards a deployment site while simultaneously displacing the system in line with the direction of tidal flow such as to maintain tension in the cable;lowering the system from a deployment vessel and simultaneously displacing the deployment vessel such as to maintain tension in the cable;towing the deployment vessel behind a towing vessel; and utilising the towing vessel to achieve the displacement of the deployment vessel; andwinching the deployment vessel towards the towing vessel during lowering of the system in order to achieve the displacement of the deployment vessel.
Priority Claims (1)
Number Date Country Kind
08007477 Apr 2008 EP regional
PCT Information
Filing Document Filing Date Country Kind 371c Date
PCT/EP2009/002793 4/16/2009 WO 00 12/16/2010
Publishing Document Publishing Date Country Kind
WO2009/127415 10/22/2009 WO A
US Referenced Citations (126)
Number Name Date Kind
228467 Maclay Jun 1880 A
928536 Pino Jul 1909 A
1710103 Nelson Apr 1929 A
2054142 Sharp Sep 1936 A
2470797 Thomas May 1949 A
2501696 Souczek Mar 1950 A
2563279 Rushing Aug 1951 A
2658453 Walters Nov 1953 A
2782321 Fischer Feb 1957 A
2792505 Baudry May 1957 A
2874547 Fiore Feb 1959 A
3078680 Wapsala Feb 1963 A
3209156 Struble, Jr. Sep 1965 A
3292023 Korber Dec 1966 A
3342444 Nelson Sep 1967 A
3355998 Roemisch Dec 1967 A
3384787 Schwartz May 1968 A
3422275 Braikevitch et al. Jan 1969 A
3433024 Diamond et al. Mar 1969 A
3477236 Burrus Nov 1969 A
3487805 Satterthwaite et al. Jan 1970 A
3708251 Pierro Jan 1973 A
3986787 Mouton, Jr. et al. Oct 1976 A
3987638 Burkhardt et al. Oct 1976 A
4095918 Mouton et al. Jun 1978 A
4163904 Skendrovic Aug 1979 A
4219303 Mouton, Jr. et al. Aug 1980 A
4274009 Parker, Sr. Jun 1981 A
4367413 Nair Jan 1983 A
4421990 Heuss et al. Dec 1983 A
4427897 Migliori Jan 1984 A
4523878 Richart et al. Jun 1985 A
4541367 Lindberg Sep 1985 A
4613762 Soderholm Sep 1986 A
4720640 Anderson et al. Jan 1988 A
4740711 Sato et al. Apr 1988 A
4744697 Coppens May 1988 A
4744698 Dallimer et al. May 1988 A
4810135 Davenport et al. Mar 1989 A
4867605 Myers et al. Sep 1989 A
4868408 Hesh Sep 1989 A
4868970 Schultz et al. Sep 1989 A
4990810 Newhouse Feb 1991 A
5592816 Williams Jan 1997 A
5606791 Fougere et al. Mar 1997 A
5609441 Khachaturian Mar 1997 A
5656880 Clark Aug 1997 A
5662434 Khachaturian Sep 1997 A
5715590 Fougere et al. Feb 1998 A
5800093 Khachaturian Sep 1998 A
5998905 Fougere et al. Dec 1999 A
6039506 Khachaturian Mar 2000 A
6109863 Milliken Aug 2000 A
6113314 Campbell Sep 2000 A
6166472 Pinkerton Dec 2000 A
6168373 Vauthier Jan 2001 B1
6232681 Johnston et al. May 2001 B1
6242840 Denk et al. Jun 2001 B1
6293734 Thomas et al. Sep 2001 B1
6300689 Smalser Oct 2001 B1
6367399 Khachaturian Apr 2002 B1
6406251 Vauthier Jun 2002 B1
6409466 Lamont Jun 2002 B1
6445099 Roseman Sep 2002 B1
6476709 Wuidart et al. Nov 2002 B1
6612781 Jackson Sep 2003 B1
6648589 Williams Nov 2003 B2
RE38336 Williams Dec 2003 E
6729840 Williams May 2004 B2
6770987 Sogard et al. Aug 2004 B1
6777851 Maslov Aug 2004 B2
6806586 Wobben Oct 2004 B2
6840713 Schia et al. Jan 2005 B1
6843191 Makotinsky Jan 2005 B1
6857821 Steenhuis et al. Feb 2005 B2
6957947 Williams Oct 2005 B2
6995479 Tharp Feb 2006 B2
6998730 Tharp Feb 2006 B2
7190087 Williams Mar 2007 B2
D543495 Williams May 2007 S
7275891 Owen et al. Oct 2007 B2
7352078 Gehring Apr 2008 B2
7378750 Williams May 2008 B2
7425772 Novo Vidal Sep 2008 B2
7471009 Davis et al. Dec 2008 B2
7527006 Khachaturian May 2009 B2
7611307 Owen et al. Nov 2009 B2
7845296 Khachaturian Dec 2010 B1
7874788 Stothers et al. Jan 2011 B2
7976245 Finnigan Jul 2011 B2
20020034437 Williams Mar 2002 A1
20030044272 Addie et al. Mar 2003 A1
20030137149 Northrup et al. Jul 2003 A1
20030168864 Heronemus et al. Sep 2003 A1
20030193198 Wobben Oct 2003 A1
20030218338 O'Sullivan et al. Nov 2003 A1
20040021437 Maslov et al. Feb 2004 A1
20040201299 Naritomi et al. Oct 2004 A1
20040227500 O'Meara Nov 2004 A1
20040262926 Hansen Dec 2004 A1
20050005592 Fielder Jan 2005 A1
20050031442 Williams Feb 2005 A1
20060261597 Gehring Nov 2006 A1
20070018459 Williams Jan 2007 A1
20070063448 Kowalczyk Mar 2007 A1
20070231072 Jennings et al. Oct 2007 A1
20070291426 Kasunich et al. Dec 2007 A1
20080012538 Stewart et al. Jan 2008 A1
20080236159 Tierney Oct 2008 A1
20090162144 Ayre Jun 2009 A1
20090243298 Jean et al. Oct 2009 A1
20090278357 Williams Nov 2009 A1
20100025998 Williams Feb 2010 A1
20100026002 Spooner Feb 2010 A1
20100068037 Ives Mar 2010 A1
20100172698 Ives et al. Jul 2010 A1
20100196100 Soe-Jensen Aug 2010 A1
20100201129 Holstein et al. Aug 2010 A1
20100232885 Ives et al. Sep 2010 A1
20100295388 Ives et al. Nov 2010 A1
20110018274 Ives et al. Jan 2011 A1
20110110770 Spooner et al. May 2011 A1
20110305518 Pearce et al. Dec 2011 A1
20120027522 Ives et al. Feb 2012 A1
20120187680 Spooner et al. Jul 2012 A1
20120235412 Dunne et al. Sep 2012 A1
Foreign Referenced Citations (96)
Number Date Country
2388513 Aug 2000 CA
2352673 Jan 2003 CA
260699 Apr 1947 CH
146935 Aug 1983 CH
31 16 740 Nov 1982 DE
3116740 Nov 1982 DE
3638129 May 1988 DE
3718954 Dec 1988 DE
19948198 Apr 2001 DE
10101405 Jul 2002 DE
20308901 Sep 2003 DE
10244038 Apr 2004 DE
102007016380 Oct 2008 DE
1318299 Dec 2003 EP
1564455 Jan 2005 EP
1691377 Feb 2006 EP
1876350 Jan 2008 EP
1878912 Jan 2008 EP
1878913 Jan 2008 EP
1879280 Jan 2008 EP
1878911 Sep 2008 EP
1992741 Nov 2008 EP
1885047 Dec 2008 EP
1980670 Jul 2009 EP
2088311 Aug 2009 EP
2110910 Oct 2009 EP
2112370 Oct 2009 EP
1980746 Jun 2010 EP
2199199 Jun 2010 EP
2199598 Jun 2010 EP
2199599 Jun 2010 EP
2199601 Jun 2010 EP
2199602 Jun 2010 EP
2199603 Jun 2010 EP
2200170 Jun 2010 EP
2071709 Sep 2010 EP
2209175 Sep 2010 EP
2241749 Oct 2010 EP
2302204 Mar 2011 EP
2302755 Mar 2011 EP
2302766 Mar 2011 EP
2823177 Oct 2002 FR
2 859 495 Mar 2005 FR
204505 Oct 1923 GB
924347 Apr 1963 GB
980575 Jan 1965 GB
1131352 Oct 1968 GB
1413835 Nov 1975 GB
2 316 461 Feb 1998 GB
2344843 Jun 2000 GB
2408294 May 2005 GB
2431628 May 2007 GB
2434413 Jul 2007 GB
2447514 Sep 2008 GB
59203881 Nov 1984 JP
63055370 Mar 1988 JP
01043908 Feb 1989 JP
2000341818 Dec 2000 JP
2005069025 Mar 2005 JP
2005248822 Sep 2005 JP
2006094645 Apr 2006 JP
2007255614 Oct 2007 JP
2007291882 Nov 2007 JP
WO 9844372 Oct 1998 WO
9852819 Nov 1998 WO
9966623 Dec 1999 WO
0077393 Dec 2000 WO
0134973 May 2001 WO
0134977 May 2001 WO
02099950 Dec 2002 WO
03014561 Feb 2003 WO
03025385 Mar 2003 WO
03046375 Jun 2003 WO
2004015264 Feb 2004 WO
2004027257 Apr 2004 WO
2004107549 Dec 2004 WO
2004113717 Dec 2004 WO
2005045243 May 2005 WO
2005061887 Jul 2005 WO
2005078233 Aug 2005 WO
2005080789 Sep 2005 WO
2005116443 Dec 2005 WO
2006029496 Mar 2006 WO
2007043894 Apr 2007 WO
2007055585 May 2007 WO
2007083105 Jul 2007 WO
2007086814 Aug 2007 WO
2007125349 Nov 2007 WO
2008004877 Jan 2008 WO
2008006614 Jan 2008 WO
2008050149 May 2008 WO
2008081187 Jul 2008 WO
WO2010118766 Oct 2010 WO
WO2011039249 Apr 2011 WO
WO2011039255 Apr 2011 WO
WO2011039267 Apr 2011 WO
Non-Patent Literature Citations (9)
Entry
International Search Report completed May 26, 2009, mailed Jun. 4, 2009, from corresponding International Application No. PCT/EP2009/002793.
PCT Written Opinion of International Searching Authority, Jun. 4, 2009.
Notification of Transmittal, mailed Jun. 4, 2009.
U.S. Appl. No. 13/133,235, filed Jun. 7, 2011, including the specification, claims and drawings.
U.S. Appl. No. 13/133,805, filed Jun. 9, 2011, including the specification, claims and drawings.
U.S. Appl. No. 13/133,504, filed Jun. 8, 2011, including the specification, claims and drawings.
U.S. Appl. No. 13/133,507, filed Jun. 8, 2011, including the specification, claims and drawings.
U.S. Appl. No. 13/133,832, filed Jun. 9, 2011, including the specification, claims and drawings.
U.S. Appl. No. 13/264,667, filed Oct. 14, 2011, including specification, claims and drawings.
Related Publications (1)
Number Date Country
20110088253 A1 Apr 2011 US