1. Field of the Invention
This invention relates to a new type of suction leg which is used as foundation of offshore caissons or platforms.
2. Background of the Invention
Currently, the most common foundations of an offshore fixed structure have following four types.
1. Self-elevating platform leg bearing loads after inserted into seabed, which is widely used and includes steel tube friction leg (rarely used now) and boot leg, and the boot leg rely on its pile shoe to bear loads. The biggest advantage of the self-elevating platform is that it does not need any offshore construction facility such as floating crane during offshore installation and the relocation process besides tugs, that is to say the self-elevating platform can achieve self-installation and self-relocation. However, the disadvantage is the depth of the leg inserted into mud is shallow, usually less than 20 meters, which is due to a large resistance of each pile shoe into mud, and a limited volume of the water ballast tank on the platform deck to offer a smaller weight required for the leg inserted into mud. Therefore, the bearing capacity of the self-elevating platform leg, especially the horizontal bearing capacity is limited. When the self-elevating platform serves as a production platform and is located at a same position without moving and relocation for several or a dozen years, it must be designed as per decades or one hundred years environmental conditions, which is a big challenge to ensure the leg's bearing capacity.
2. Open long pile, which is a two-end-opening steel or reinforced concrete long pipe, so called as open pile. The open long pile, such as a steel pile of a jacket platform, inserted into a pile sleeve of the offshore structure is driven into a seabed by a pile hammer and then fixed to the pile sleeve. Due to the limited capability of the pile hammer, the diameter of the open long pile is usually not more than 2.5 meters, and the length in mud is usually not more than 90 meters. The open long pile relies on the lateral friction force between the pile and the soil and the tip resistance after soil-consolidation to bear the vertical load, so the open long pile is usually called as friction pile. The main disadvantage is piling must use the pile hammer which needs a supporting offshore floating crane, and the open long pile will be difficult to pull out and reuse.
3. Suction pile, which is a bottom-opening and top-closed cylinder usually made of steel structure. During the suction or water injection processes by the special pump(s) installed on the top head of the suction pile, the downward penetration force or the upward uplifting force is produced by the pressure difference between inside and outside the top head, and the penetration force or the uplifting force would press or pull the suction pile into or out from the seabed. During penetration, the said pressure difference is determined by the water depth and difficult to increase so much, meanwhile a large external pressure may cause a buckling problem to the cylinder and its top head. Therefore, the diameter and penetrative depth of the suction pile have to be restricted, the diameter is usually 8 to 10 meters, the penetrative depth is generally not more than 12 meters, and the corresponding penetration force cannot be so large. Suction pile belongs to shallow foundation, which relies on the tip resistance, lateral earth pressure, lateral friction force and internal and external differential pressure to bear loads. The advantage of the suction pile is it can be pulled out and reused, that is to say it has recoverability. Two shortcomings of suction pile are as follows: firstly it need special pump and corresponding offshore operations supporting facilities, secondly it has high requirements on the shallow layers' bearing capacity of the seabed.
4. Gravity type foundation, which is widely used in offshore concrete gravity platforms, for example, a fixed offshore structures can stay on a seabed relied on its massive gravity. At present, offshore caissons used in ports, bridges and artificial islands also usually use gravity type foundations, supplemented by anti-sliding piles. The disadvantage of the gravity foundation is it has high requirements on the bearing capacity of the seabed and the structure is difficult to remove.
Fixed platforms for oil and gas field development in shallow waters mainly include jacket platform and gravity platform, mobile self-elevating platform, their basic structure and advantages/disadvantages are well-known and do not need to repeat. Usually, only the gravity platform has liquid storage function, and the mobile platform and the jacket platform, without storage, need to be compatible with FPSO(s) (floating production storage and offloading vessel(s)) to meet the requirement of oil drilling, oil production, storage and exportation. All of said existing facilities have high EPC investments, operating and decommissioning costs.
PCT/CN2013/070808 disclosed a type of sealing steel pile comprising a tubular pipe and a top head connected tightly to form a cylindrical integral structure with a sealing top and an opening bottom, and a release valve, an air intake valve and a water intake valve installed on the top head. As the foundation of offshore facilities, the sealing steel pile could be pressed into seabed by the weight of the facilities with ballast water, or/and by pump suctioning; and also, it could be pulled out from the seabed by the buoyancy of the facilities de-ballasted water, or/and by the method to inject water or gas into the sealing pile. PCT/CN2013/070808 gave detailed descriptions about the sealing pile pressed into or pulled out from seabed, as well as the offshore installation of the facility with sealing steel piles, and also disclosed limited information about the connection structure between the sealing steel piles and the offshore facility.
One of the purposes of this application is to provide a type of suction leg which has advantages of simple structure, large penetrative depth, high bearing capacity, small loads of penetration or pile pull-out, and easy to control.
Another of the purposes of this application is to provide a type of offshore caisson founded with the said suction legs.
Another of the purposes of this application is to provide a type of removable sit-on-bottom offshore platform founded with the said suction legs.
In order to achieve above purposes, this application discloses a suction leg, comprising a sealing long pile and a long pole. The sealing long pile comprises a tubular pipe and a top head connected tightly to form a cylindrical integral structure with a sealing top and an opening bottom. The top head has at least one opening hole to be able to open or close. The long pole is fixed in the center of the top head of the sealing ling pile and it has a common central axis with the sealing long pipe. The sealing long pile can be pressed into a seabed by gravity penetration method or/and suction pile penetration method, and be pulled out from the seabed by buoyancy uplift method or/and suction uplift method.
This application also discloses an offshore caisson, it comprises a watertight tank made of steel or reinforced concrete, at least two pile sleeves arranged symmetrically around the bottom of the said tank, and legs, i.e., the said suction legs, inserted into these pile sleeves. The watertight tank has at least one ballast compartment for adding solid ballast to increase the weight of the caisson, or for injecting/ejecting seawater to change the weight of the caisson. The watertight tank and the pile sleeves are permanently connected together to form an integral structure, each suction leg can be detachably connected to the pile sleeve.
This application also discloses a sit-on-bottom offshore platform, which includes the following components.
Storage tank(s) sit on the seabed, which is used to store the platform's output liquid(s) or receive input liquid(s). A transparent moon pool may or may not set in the tank. There are at least two pile sleeves which arranged symmetrically around the bottom parameter of the said tank to form an integral structure.
Suction legs as described above, which number is equal to the number of the pile sleeves. Each leg can have a long pole or not. The sealing long pile of each suction leg is inserted into the pile sleeve, and the long pile can slide up/down along and be fixed to the pile sleeve.
Topsides located in the top of storage tank and above water, it is connected to storage tank by deck legs or suction legs.
The sealing long piles of the suction legs are inserted downwards into the seabed to become a foundation of the sit-on-bottom offshore platform. By gravity penetration or/and suction pile penetration, or buoyancy uplift or/and suction uplift, the sit-on-bottom offshore platform can be sit on and fixed to the seabed, or re-floated and removed.
This application further discloses a suction leg including a sealing long pile with or without a long pole. The sealing long pile comprises a tubular pipe and a top head connected tightly to the tubular pipe to form a cylindrical integral structure with a sealing top and an opening bottom. The top head has at least one opening to be opened or closed. The long pole is a cylindrical or a triangle truss structure being fixed on a center of the top head of the sealing long pile and has a common axis with the sealing long pile. A diameter of the long pile is smaller than a diameter of the tubular pipe. The the sealing long pile is penetrated into a seabed by a gravity penetration method or a suction pile penetration method, or pulled out from the seabed by a buoyancy uplift method or a suction pile uplift method.
This application further discloses an offshore caisson including a watertight tank made of steel or reinforced concrete structure, the watertight tank having at least one ballast compartment used for injecting or ejecting ballast seawater and a solid ballast to change the weight of the offshore caisson, at least two pile sleeves arranged symmetrically around a bottom of the watertight tank, and a suction leg in the pile sleeves. The watertight tank and the pile sleeves are connected together to form an integral structure. The suction leg comprises a sealing long pile having a tubular pipe and a top head connected tightly to the tubular pipe to form a cylindrical integral structure with a sealing top and an opening bottom. The sealing long pile of the suction leg slips up-and-down along or is fixed with the pile sleeve. The sealing long pile serves as a foundation of the offshore caisson.
This application additionally disclose a sit-on-bottom offshore platform including a storage tank sit on a seabed for storing platform-produced liquid or receiving input liquid and with or without a transparent moon pool, at least two pile sleeves being arranged symmetrically around the bottom of the storage tank, the pile sleeves being connected to the storage tank to form an integral structure, suction legs comprise sealing long piles with or without long poles, the sealing long pile having a tubular pipe and a top head connected tightly to the tubular pipe to form a cylindrical integral structure with a sealing top and an opening bottom, the top head having an opening, a number of the suction legs being equal to a number of the pile sleeves, the sealing long piles of the suction legs being inserted into the pile sleeves, and slide up and down or are fixed to the pile sleeves, a topsides located in a top of storage tank, which is connected to the storage tank by deck legs or the long poles of the suction legs. Each suction leg is raised up at its upper position, the bottom of each sealing long pile and the storage tank are at a same horizontal plane. The opening on the top heads of the sealing long pile is closed during construction and towing. The bottom opening of each sealing long pile is submerged underwater to form a closed air inside the sealing long pile to increase the buoyancy and the GM of the sit-on-bottom platform during wet towing. The sealing long piles of the suction legs are pressed down into the seabed and become a foundation of the sit-on-bottom platform. The sit-on-bottom platform sits on seabed, or is re-floated or removed through a gravity penetration method or a suction pile penetration method, or a buoyancy uplift method or a suction pile uplift method.
Compared with existing technology, the present application has the following characteristics and advantages:
1. Compared with the existing self-elevating platform leg, the suction leg in this application has advantages of simple structure, large penetrative depth, high bearing capacity, small loads of penetration or pile pull-out, and easy to control.
2. Compared with the existing open long pile and suction pile being used as foundation of fixed offshore structures, the suction leg in this application has the advantages of both open long pile and suction pile at the same time. The offshore structures and facilities using this sealing long pile as foundation, such as offshore caissons and removable fixed offshore platforms, assisting by the gravity type foundation if necessary, can be flexibly installed on the seabed with different engineering geological conditions to save foundation cost.
3. Compared with the existing fixed offshore platform and FPSO, the removable fixed offshore platform in this application unites two of jacket and FPSO in one, with functions of drilling, oil and gas production, storage and transportation, oily water treatment, natural gas liquefaction and then gasification; it has series of advantages, such as eco-friendly, safe and reliable. Besides, all the construction and pre-commissioning work of the entire platform can be completed in a shipyard, and the platform can achieve self-installation and self-relocation and reuse, as well as significant savings in facilities construction, production operation and decommissioning.
These drawings described herein are only used for the purpose of interpretation and do not intend to limit the scope of the present invention in any way. Further, in the graph shape and scale size of each component are only schematic to help understanding this invention, not specifically defined each component's shape and proportional size. Technical staff in this field under the guidance of this invention can according to specific situation choose possible options of shape and proportional size to implement this invention.
Description of appended drawing reference numbers is as follow:
1. Water Surface, 2. Seebed, 10. Suction Leg, 11. Sealing Long Pile, 111. Tubular Pipe of Sealing Long Pile, 112. Top Head of Sealing Long Pile, 113. Valve, 12. Long Pole, 20. Offshore Caisson , 21. Caisson Pile Sleeve, 22. Tank Of Caisson, 221. Ballast Compartment, 23. Caisson Skirt Plate, 30. Removable Sit-On-Bottom Offshore Platform, 30a. Removable Sit-On-Bottom Offshore Platform and the Storage Tank with Above-Water Top, 30b. Removable Sit-On-Bottom Offshore Platform and the Storage Tank with Underwater Top, 31. Storage Tank Sit on Seabed (Sit-On-Bottom Storage Tank), 311. Tank Unit, 312. Top Connecting Structure, 3121. Hole for Long Pole, 313. Bottom Connecting Structure, 314. Platform Pile Sleeve, 315. Moon Pool, 32. Topsides, 321. Open Deck Structure of Topsides, 322. Box Watertight Deck Structure, 323. Deck Leg, 33. Tank Unit with Steel Plate and Concrete Composite Structure, 331. Outer Concrete Tank, 3311. Outer Tank Shell, 3312. Outer Tank Head, 3313. Ring Corbel, 332. Inner Steel Tank, 3321. Inner Tank Shell, 3322. Inner Tank Head, 3323. Cylinder Epitaxial Structure of Inner Tank, 3324. LNG Compartment Wall, 3325. Thermal Insulation, 3326. Inner Tank's Outer Steel Wall, 333. Isolation Layer, 334. Spare Compartment.
Drawings and descriptions of embodiments can make the invention details clearer. However, those described embodiments are only used to explain the purpose of the invention, could not be interpreted as limiting the invention in any way. Technical staff in this field under the guidance of this invention could conceive any possible deformation based on this invention, these should be considered as belong to the scope of this invention.
As shown in
The sealing long pile 11 can slide up-and-down or be fixed in pile sleeve 21 (see
The sealing long pile of the suction leg in this embodiment has both advantages of the open long pile and the suction pile at the same time and does not have their disadvantages.
When the opening hole on top head 112 of suction leg 10 is opened, the sealing long pile 11 becomes an open long pile, which can be penetrated into the seabed or pulled out from the seabed rely on the weight-in-water or the buoyancy of the offshore structure. The said two methods referred to as “gravity penetration method” and “buoyancy uplift method” respectively. The existing open long pile is driven into the seabed by a pile hammer. The diameter of the open long pile is rather small. However, compared with the open long pipe, the diameter of sealing long pile 11 in this embodiment is larger and its length is longer than existing suction pile provided the weight-in-water of the offshore structure is large enough. For example, the diameter of this suction leg 10 can be more than 10 meters, and its penetrative depth is between the depths of the open long pile and the suction pile and usually 20˜30 meters to meet the bearing capacity requirement. Besides, as long as the offshore structure's buoyancy is large enough after its wet weight reduced, the sealing long pile 11 can be pulled out from the seabed by the buoyancy. Method to increase/decrease the weight of the offshore structure is to inject/eject ballast seawater into/out from the ballast compartment.
When the opening hole on the top head 112 of the suction leg 10 is closed, the sealing long pile 11 becomes a suction pile, which has the following characteristics: 1) This suction leg 10, similar to existing suction pile, can be penetrated into or pulled out from the seabed by the difference of the internal and external pressures at the top head 112 during offshore installation. The pressure difference is produced by suction or injection operations of the special pump(s) installed on the top head. The said two methods referred to as “suction pile penetration method” and “section pile uplift method”. 2) In in-place condition, this suction leg 10 reach the required penetrative depth as shown in
The sealing long pile 11 can be penetrated into the seabed using the two methods of gravity penetration and suction pile penetration at the same time, and be pulled out from the seabed using the two methods of buoyancy uplift and suction pile uplift at the same time. When two methods used at the same time, the opening hole on the head 112 must be closed.
The sealing long pile 11 of the suction leg 10 in this embodiment is steel structure or reinforced concrete structure, and the long pole 12 is steel structure.
The sealing long pile 11 of the suction leg 10 in this embodiment has the following advantages: good adaptability to the seabed, safety and reliability, flexible construction scheme, more convenient to installation due to the long pole 12 matched with the sealing long pile 11, project investment saving and recyclable, that creates necessary conditions for self-installation and self-removal of the offshore structure with suction legs 10.
Offshore Caisson
As an application of the suction leg 10 in the present application, as shown in
Similar to the existing offshore caisson, the offshore caisson in present embodiment can be built in a dry dock and transported to site by wet towing (float towing in water). The sealing long piles 11 are inserted into the pile sleeves 21, the bottoms of the sealing long piles 11 and the storage tank 22 are at the same horizontal plane and they can fixed temporarily as an integrated structure for wet towing. Gravity foundation or long pile foundation, or both two are usually used for the existing offshore caissons. The foundation of this offshore caisson 20 is the sealing long piles 11. Gravity penetration method can be used for the sealing long piles 11, that is to say, when the valves 113 of the sealing long piles 11 opened, injecting ballast seawater or adding solid ballast to the ballast compartment 221 of the offshore caisson 20 to increase the underwater weight for penetration. When the valves 113 of the sealing long piles 11 closed, the sealing long piles 11 can be penetrated into seabed and the caisson 20 sitting on the seabed (see
The caisson 20 in this embodiment use sealing long pile 11 as foundation, at the same time, it can also use its weight as an auxiliary gravity foundation. For example, when the pile penetration is done, more solid ballast can be added into the caisson 20. Besides, there is a skirt guard plate 23 around the bottom parameter of the caisson 20 to increase the capacity of anti-sliding and anti-scour, and this skirt guard plate 23 can be penetrated into or pulled out from the seabed by the gravity or buoyancy of the caisson. The offshore caisson 20 in this embodiment can realize self-installation and entire installation procedure does not require large offshore construction facilities, which follows the steps of transporting the offshore caisson 20 with sealing long pile 11 to site by wet towing under help of the buoyancy, putting down sealing long pile 11, using “gravity penetration method” or/and “suction pile penetration method” to penetrate the sealing long pile 11 into the seabed and making offshore caisson 20 sit on the seabed. The steps to remove or relocate the caisson 20 without large offshore construction facilities are as follows: using the “buoyancy uplift method” or/and the “suction pile uplift method” to pull out pile from seabed and making the caisson refloated and removed.
Sit-On-Bottom Offshore Platform
As shown in
The removable sit-on-bottom offshore platform 30a and 30b all have a storage tank 31, suction legs 10 and a topsides 32, as described below.
The storage tank 31 sit on the seabed 2, which is used to store platform-produced liquid or receive input liquid. A transparent moon pool 315 may be or not set in the storage tank. There are at least two pile sleeves 314 around the bottom parameter of storage tank 31 and they are connected and fixed together to form an integral structure.
The suction legs 10 as described above, the number of suction legs is equal to the number of the pile sleeves 314. Each suction leg 10 can have a long pole 12 or not. Each sealing long pile 11 of the suction leg 10 inserted into a pile sleeve 314 can slide up and down and be fixed to the pile sleeve 314.
The topsides 32 located in the top of storage tank 31 and above water 1, which comprises one or two or more kinds of facilities required for drilling, oil and gas production, storage and transportation, utilities and living, as well as open deck structures 321 (as shown in
As shown in
As shown in
The storage tank 31 in this embodiment is steel structure or concrete structure or composite structure of both. Concrete structure including reinforced concrete structure, bi-steel concrete structure, fiber concrete structure and other existing concrete structures.
The long poles 12 and the deck legs 323 are cylindrical or triangle truss structure (not shown in
During the process of construction in a dry dock and wet towing, each sealing long pile 11 of the suction leg 10 are raised and inserted in a pile sleeve 314, the bottoms of sealing long pile 11 and storage tank 31 are at the same horizontal plane (in other words, the suction legs 10 at the lifting position) and then fixed temporarily (as shown in
The sealing long pile 11 is used for the removable sit-on-bottom offshore platform 30 as a foundation in this embodiment, at the same time, the weight of the platform also could be used as an auxiliary gravity foundation. Similar to the existing self-elevating platform, the suction legs 10 of this platform can be inserted into or pulled out from the seabed to make its storage tank 31 be sit on bottom and fixed to the seabed, or re-floated and removed.
The main process of offshore installation (inserting pile) of this platform 30a in present invention is as follows:
a. Towing the platform 30a to sea site.
b. Dropping anchor, adjusting and tensioning the anchor cables for positioning.
c. Opening all the openings on the heads of the sealing long piles for air releasing and water coming in.
d. Relieving the temporary fixing connections between the suction legs 10 and the platform storage tank 31.
e. Putting the suction legs 10 down relied on self-weight, inserting the sealing long piles 11 into mud.
f. Using the “gravity penetration method” or/and the “suction pile penetration method” (all head openings of the sealing long piles 11 have to be closed when using suction pile penetration method) to penetrate the sealing long pile 11 into the seabed and make the platform sit on the seabed.
g. If a one-time pile penetrating cannot reach the design depth, it has to remove the fixing connections, discharge ballast water, make the storage tank 31 re-floating from the seabed, and then use the “gravity penetration method” or/and the “suction pile penetration method” again, until it reaches the design depth.
h. Closing all head openings of the sealing long piles 11, then the offshore installation is finished.
Each sealing long pile 11 bears loads as a suction pile does. Large offshore construction facilities are not required during the entire process which means “self-installation”.
The main process of offshore installation (inserting pile) of this platform 30b in present embodiment is as follows.
a. Putting the topsides down to make the box watertight deck structure 322 sit on the top of the storage tank 31 before the platform towing.
b. Towing the platform 30b to sea site.
c. Dropping anchor, adjusting and tensioning the anchor cable to fixed position.
d. Opening all the openings at the heads of the sealing long piles 11 to make air releasing and water coming in.
e. Relieving the temporary fixing connections between the suction leg 10 and the deck 322 and between the suction leg 10 and the platform storage tank 31 at the same time.
f. Putting the suction leg 10 down relied on self-weight to a setting depth (determined by the depth needed for the sealing long pile 11).
g. Fixing the sealing long piles 11 to the storage tank 31 again.
h. Ballasting water into the storage tank 31 until the watertight deck 322 in floating condition.
i. Continuously ballasting water into the storage tank 31 to its highest level to make the sealing long piles 11 inserted into seabed 2 as deep as possible.
j. Lifting watertight the deck 322 to a setting height, fixing the long pole 12 or fixing the deck leg 323 to the deck 322 again.
k. Ballasting water into the top seawater ballast compartment of the deck 322, using the “gravity penetration method” or/and the “suction pile penetration method” (the openings of the sealing long piles have to be closed when using suction pile penetration method) to penetrate the pile into seabed and make the storage tank sit on the seabed.
1. Closing all head openings of the sealing long piles 11, then the offshore installation is finished.
Each sealing long pile 11 bears loads as a suction pile does. Large offshore construction facilities are not required during the entire process which means “self-installation.”
When the platform need to be relocated, the pile extracting is the inverse process of the pile inserting, using the “buoyancy uplift method” or/and the “suction pile uplift method” to complete the pile extracting and make the storage tank re-floated again and then remove platform. The said process, which does not require large offshore construction facilities and means “self-removal”, is the inverse one of pile inserting mentioned above and no need to be repeated here.
Various forms and structures of the storage tank 31 of the removable sit-on-bottom offshore platform are provided in the present application, including but not limited to single-cylinder form, multi-cylinder form and rectangular box form made of steel structure or concrete structure. The functions of the storage tank are as: being support for the topsides 32, providing storage for liquids produced by the platform or received outside, providing gravity for pile inserting, and providing buoyancy for construction, towing and pile extracting. The storage tank 31 comprises at least one liquid storage compartment and one seawater ballast compartment for displacement between the stored liquid and the ballast seawater in equal or unequal mass flow-rate, or only one liquid storage compartment without seawater ballast compartment. The storage tank 31 can has a moon pool to accommodate wellhead conductors and risers.
As shown in
The said tank units 311 can be used for storing one or many different liquids. As shown in
The tank unit 311 of the storage tank has different structural forms as per its-stored liquid, which comprises four types: 1) tank unit with single-wall made of reinforced concrete or steel as oily water compartment, which is used to deal with oily water by thermochemical settlement or bacterial biochemical treatment, 2) tank unit with steel plate and concrete composite structure 33 provided by this application, which is used to store various kinds of industrial liquid products, 3) vertical cylindrical multi-tank, which is addressed in this inventor's U.S. patent document U.S. Pat. No. 8,292,546B, which is incorporated herein by reference, 4) vertical tank unit with steel plate and concrete composite structure, which is addressed in this inventor's application of PCT/CN2013/070808 dated Jan. 22, 2013, which also incorporated herein by reference. The structural forms of tank units 311 of the storage tank could be only one or more of the said four types at the same time as per the function of the platform 30.
As shown in
The spare compartment 314 of the tank unit with steel plate and concrete composite structure 33 to be used as seawater ballast compartment can be made of concrete. The pressure inside the tank unit with steel plate and concrete composite structure 33 should not be so high, usually just above atmospheric pressure 1-2 bar.
As shown in
During the storage and transportation process, crude oil, liquid at normal pressure and temperature and LPG could be displaced with ballast seawater in an equal or unequal mass flow rate. If the equal mass flow rate selected, the technologies of “displacement system between stored liquid and ballast seawater in an equal mass flow rate” and “sit-on-bottom with small underwater weight” as described in U.S. Pat. No. 8,292,546 B2, and “displacement system between LPG and ballast seawater in an equal mass flow rate” as described in d U.S. Pat. No. 8,678,711 B2 are recommended. U.S. Pat. Nos. 8,292,546 B2 and 8,678,711 B2 are herein incorporated by reference.
As shown in
The removable sit-on-bottom offshore platform in the present application has a wide range of uses, and based on the storage tank selected, it can form different platforms with different functions.
The removable sit-on-bottom offshore platform 30a, which has a storage tank 31 with above-water top, is used for oil and gas field development (see
The removable sit-on-bottom offshore platform 30b, which has a storage tank 31 with underwater top, is used for oil and gas field development (see
As an application of the platform 30a, this embodiment provides a LNG receiving and regasification terminal which is located in shore waters. The storage tank of this terminal could preferably be one or multiple multilayer cylindrical-tank groups with above-water top and the multiple tank groups with a space to each other, and the tank units within each tank group are arranged in forms of a regular hexagon or a long hexagon as LNG storage tank 31 without moon pool. All the tank units within the said storage tank are steel plate and concrete composite structure 33 suitable to store LNG. The cylindrical-tank group arranged in a regular hexagon of the terminal is as shown in
The processes of storage and transportation of the platforms 30a & b and the terminal preferably adopt a displacement system between the stored liquids and ballast seawater in equal mass flow rate. The technology of “displacement system between stored liquid and ballast seawater in equal mass flow rate” as described in U.S. Pat. No. 8,292,546 B2 is recommended for crude oil and liquids with normal temperature. The technology of “displacement system between LPG/LNG and ballast seawater in equal mass flow rate” as described in U.S. Pat. No. 8,678,711 B2 is recommended for LPG and LNG For the platform 30a with foundations of the sealing long piles than gravity, the technology of “sit-on-bottom with small underwater weight” as described in U.S. Pat. No. 8,292,546 B2 is also recommended.
As an application of the platform 30a, this embodiment provides an oily water treatment and reinjection platform as shown in
The removable sit-on-bottom offshore platform in the present application provides a new type of surface facilities with multifunction in one, and a new mode to develop offshore oil and gas fields with a water depth within 200 meters. The multi functions include drilling, oil and gas production, storage and transportation, oily water treatment, natural gas liquefaction and re-gasification. The platform in this application also has series of advantages, such as eco-friendly, safe and reliable. All the construction and commissioning work of the entire platform can be completed in a shipyard to achieve self-installation and self-relocation and reuse, significant savings of construction costs, production operations costs and decommissioning costs.
The specific embodiments described in this invention are only used to explain the purpose of the invention to provide a better understanding, and could not be interpreted as limitations to the invention in any way. In particular, various features in different embodiments described herein could be combined mutually and arbitrarily combination to form other implementation methods; unless there was a clear contrast description, these features should be understood as can be applied to any one embodiment, not limited to the embodiments described herein.
Number | Date | Country | Kind |
---|---|---|---|
PCT/CN2013/070808 | Jan 2013 | CN | national |
This application is a continuation of International Application Serial No. PCT/CN2014/071120 entitled “Suction-Type Pile Leg, Offshore Caisson, and Seabed-Fixed Offshore Platform,” filed on Jan. 22, 2014, which claims priority from International Application Serial No. PCT/CN2013/070808 entitled “Unitary Barrel of Steel Plate and Concrete Composite Structure, Unitary Group Barrel, and Offshore Platform,” filed on Jan. 22, 2013. All of the above-identified applications are incorporated herein by reference in their entirety.
Number | Date | Country | |
---|---|---|---|
Parent | PCT/CN2014/071120 | Jan 2014 | US |
Child | 14805357 | US |