The present invention relates to the technical filed of electric power system and automation, and specifically is unit commitment method considering security region of wind turbine generators with frequency response control.
To achieve low-carbon operation of the power system, renewable energy sources such as wind power and photovoltaics have developed rapidly. However, in traditional control modes, renewable energy sources, such as wind power and photovoltaics are all non-synchronous energy sources. High-penetration non-synchronous energy sources bring major challenges to system frequency security. The low inertia power system is easy to be interfered, which will cause the system frequency drop rapidly after a failure, and seriously threaten the system frequency stability. To ensure the system frequency stability, maintaining a certain amount of synchronous generator is necessary. But it will limit the penetration rate of non-synchronous energy sources, and may lead to the consumption problem of renewable energy sources. Therefore, renewable energy sources are required to undertake the task of providing frequency response. Among renewable energy sources, wind turbine generator is considered as an ideal frequency response provider due to the rotational kinetic energy stored on the rotors. The frequency response control of wind turbine generators can simulate frequency response characteristics of synchronous generator, such as inertial response and primary frequency response. When determining the scheme of unit commitment, the frequency responses of wind turbine generators are expected to reduce the burden of synchronous generator to provide frequency response. However, the ability of wind turbine generators to provide frequency response is restricted by its safe operation requirement. In the frequency-constrained unit commitment model, the safety of wind turbine generators is usually ignored, leading to the overestimation of the frequency response capability of wind turbine generators. Therefore, the unit commitment model considering the safety of wind turbine generators needs further study.
The purpose of the present invention is to solve the problem in the prior art.
The technical solution adopted to achieve the purpose of the present invention is as follows. Unit commitment method considering security region of wind turbine generator with frequency response control, mainly comprises the following steps.
1) Determining the security region of the wind turbine generators when provides frequency response, and the main steps are as follows.
1.1) Establishing an output model of wind turbine generators when provides frequency response, namely:
In the above formulas, ΔPwPFR and ΔPwIR respectively represent the primary frequency response and virtual inertia response provided by the wind turbine generators. Frequency response coefficient Kw=1/Kdroop-w. Kdroop-w is the droop control parameter of the wind turbine generators in primary frequency response control. Jw is the virtual inertia control parameter of the wind turbine generators. Δf is the system frequency deviation, and t refers to time.
1.2) Establishing constraint condition of the rotor rotational speed ωr, namely:
ωmin≤ωr≤ωmax (3)
In the above formulas, ωmin and ωmax respectively are the lowest speed and highest speed of the rotor rotational speed of the wind turbine generators.
1.3) Establishing constraint conditions of wind power stability, the main steps are as follows.
1.3.1) Determining the synchronization characteristics of the wind turbine generators, namely:
In the above formulas, PE is the active output of the wind turbine generators. KDL is the de-load factor of the wind turbine generators. When the wind turbine generators are working at maximum power tracking mode, the coefficient KDL is the maximum power tracking coefficient, and KDLωr3 is the output of the wind turbine generators when there is no virtual inertia response. p is the air density. R is the diameter of the rotor of the wind turbine generators. v is the wind speed. Cp is the power coefficient of the wind turbine generators. PM is the mechanical power of the wind turbine generators. β is the pitch angle of the wind turbine generators.
Wherein, the tip speed ratio λ is shown as follows.
1.3.2) Determining the limit operating rotational speed ωrc of the wind turbine generators. The limit operating rotational speed ωrc of the wind turbine generators meets the following formula.
1.3.3) Substituting the limit operating rotational speed ωrc of the wind turbine generators into formula (5), calculating to obtain the limit operating point of the wind turbine generators
1.3.4) Connecting the extreme operating points at each wind speed to form the stability boundary of the wind turbine generators, and substituting formula (6) into formula (7) to calculate the limit tip speed ratio A. The limit tip speed ratio A meets the following formula.
1.3.5) Establishing the expression formula of the relationship between wind speed and rotor rotational speed on the stability boundary of the wind turbine generators, namely:
1.3.6) Substituting formula (9) into formula (5), and calculating to obtain the expression formula of the stability boundary of the wind turbine generators, namely:
1.3.7) Based on formula (10), updating the limit operating point of the wind turbine generators to (ωrc, Kcωr3).
1.3.8) Establishing the stability constraints of the wind turbine generators when provides frequency response, and it is divided into the following three situations.
I) When the wind turbine generators are operating at the lowest speed, the wind turbine generators do not provide frequency response. The frequency response of the wind turbine generators is as follows.
In the above formulas, ωr0 is the rotor rotational speed in the initial operating state of the wind turbine generators.
II) When the limit operating rotational speed ωrc is less than the lowest speed ωmin, the stability constraints of the wind turbine generators when provides frequency response are as follows.
In the above formulas, fM(ωmin) is the mechanical power of the wind turbine generators at the lowest rotational speed comm.
III) When ωrc≥ωmin, the stability constraints of the wind turbine generators when provides frequency response are as follows.
1.4) Establishing the output constraints of the wind turbine generators when provides frequency response, and the main steps are as follows.
1.4.1) Updating the active output PE* of the wind turbine generators, namely:
In the above formulas, Pw is the available power of the wind turbine generators. dw is the reserve coefficient of the wind turbine generators, and (1−dw)Pw, is the actual output of the wind turbine generators when does not provide frequency response output.
1.4.2) Establishing the output constraints of the wind turbine generators when provides frequency response, namely:
In the above formulas, Pwmaxis the maximum output of wind turbine generators.
1.5) Combining formula (10), formula (12), formula (13) and formula (15), the security region of the wind turbine generators meets formula (16) to formula (19), namely:
2) Based on the security region of the wind turbine generators when provides frequency response, establishing a unit commitment model considering the security region of the wind turbine generators. The main steps are as follows.
2.1) With the goal of minimizing the operating cost of the traditional synchronous generator, establishing the objective function, namely:
In the above formulas, cis a set of traditional synchronous generators. cg is the marginal cost. cgnl is the no-load cost. cgsu is the start-up cost. Pg,i is the active power of the traditional synchronous generator. Ng,ion is an online synchronous generator. Ng,isu is the synchronous generator turned on at step i. T is the total optimization time scale. Δt is the unit time interval. Variables with the subscript i represent the variables of the i-th step. Variables with subscript g represent variables related to traditional synchronous generator g. Variables with subscripts g,i represent the related variables of the traditional synchronous generator g at the i-th step.
2) Establishing constraints of traditional unit commitment, which include power flow constraints, synchronous generator constraints, system frequency stability constraints, frequency change rate constraints, frequency lowest point constraints, and wind turbine generators security region constraints.
2.2.1) Power flow constraints are as follows.
In the above formulas, W is a set of wind turbine generators. Li is the total load of the system. The wind turbine generators parameters are all aggregate parameters. Variables with subscript w represent variables related to wind turbine generators w. Variables with subscripts w,i represent related variables of wind turbine generators w at step i.
2.2.2) Synchronous generator constraints are shown in formula (22) to formula (28).
In the above formulas, Pgmin and Pgmax are the minimum value and maximum value of the synchronous generator output, respectively. ΔPgmax is the maximum value of the output change of the synchronous generator. ΔPgsu max and ΔPgsd max are the maximum upward and downward climbing power of the synchronous generator, respectively. Ng,isd is the number of synchronous generators shut down in the step i. Ng,ioff is the number of synchronous generators offline at step i. Δtgup and Δtgdw are the minimum start and stop time of the unit. i∈T. g∈ζ
2.2.3) The system frequency stability constraints are as follows.
Wherein, Di is the load damping coefficient. Hi is the system inertia time constant. Ki is the frequency response coefficient.
Wherein, the system inertia time constant Hi is shown as follows.
In the above formulas, Hg is the inertia time coefficient of synchronous generator. The optimized variables in formula (30) are the virtual inertia control parameters Jw,i of the online synchronous generator Ng,ion and the wind turbine generators at i-th step. f0 is the reference frequency of the power system.
Frequency response coefficient Ki is shown as follows.
In the above formulas, Kg=1/Kdroop-g. Kdroop-g is the droop control parameter of the synchronous generator. The optimized variables in formula (31) are the frequency response parameter Kw,i of the online synchronous generator Ng,ion and the wind turbine generators at the i-th step.
System frequency deviation Δf is shown as follows.
Frequency change rate dΔf/dt is shown as follows.
2.2.4) Frequency change rate constraints are shown as follows.
2.2.5) Frequency lowest point constraints are shown as follows.
2.2.6) Based on formula (1), formula (2), formula (32) to formula (35), establishing the equation of frequency response provided by the wind turbine generators, namely:
2.2.7) Substituting formula (36) into formula (17) to formula (19) to establish the security region constraints of the wind turbine generators, which are shown as formula (37) to formula (43) respectively.
3) Calculating the unit commitment model considering the security region of the wind turbine generators by using mixed-integer linear programming method, to obtain the operation result of the unit commitment considering the wind turbine generators security region with frequency response control.
It is worth noting that the present invention considers the synchronization stability of the wind turbine generators, derives the stability constraints of the wind turbine generators, and provides a calculable quantitative expression. Combining the rotational speed constraints and output constraints of the wind turbine generators, jointly characterize the security region of the wind turbine generators when provides frequency response. Then, according to the characteristics of the wind turbine generators when provides frequency response (inertia response and primary frequency response), combined with the system frequency constraints, linearize the security region of the wind turbine generators when provides frequency response, and introduce the linearized security region into the unit commitment model considering frequency constraints. Thus, it can be ensured that the unit commitment model proposed by the present invention can simultaneously meet the system frequency constraints and the security region constraints of the wind turbine generators. The frequency response of the wind turbine generators obtained based on the present invention can guide the setting of the frequency response control parameter of the wind turbine generators.
The technical effect of the present invention is beyond doubt. The present invention has the following effects.
1) The security region of the wind turbine generators when provides frequency response proposed by the present invention, can effectively guide the setting of the frequency response control parameters of the wind turbine generators, ensure the safe and stable operation of the wind turbine generators when provides frequency response, and take into account the stability of the system frequency and the safety of the wind turbine generators.
2) The present invention considers both the system frequency stability constraints and the wind turbine generator's own safety constraints in the unit commitment model. When performing unit dispatch, based on the safe and stable operation of the wind turbine generators can be ensured, the wind turbine generators can provide frequency response for the system, support system frequency stability, reduce the burden of synchronous generator to support frequency stability, and save system operating costs.
The present invention can be widely used in the setting of frequency response parameters of wind turbine generators dispatched in the prior art and the start-stop and output plans of synchronous generator.
The present invention will be further described below in conjunction with embodiments, but it should not be understood that the scope of the above subject matter of the present invention is limited to the following embodiments. Without departing from the above-mentioned technical idea of the present invention, various substitutions and changes based on common technical knowledge and conventional means in the field shall be included in the protection scope of the present invention.
Refer to
1) Determining the security region of the wind turbine generators when provides frequency response, and the main steps are as follows.
1.1) Establishing an output model of wind turbine generators when provides frequency response, namely:
In the above formulas, ΔPwPFR and ΔPwIR respectively represent the primary frequency response and virtual inertia response provided by the wind turbine generators. Frequency response coefficient Kw=1/Kdroop-w. Kdroop-w is the droop control parameter of the wind turbine generators in primary frequency response control. Jw is the virtual inertia control parameter of the wind turbine generators. Δf is the system frequency deviation, and t refers to time.
1.2) Establishing constraint condition of the rotor rotational speed ωr, namely:
ωmin≤ωr≤ωmax (3)
In the above formulas, ωmin and ωmax respectively are the lowest speed and highest speed of the rotor rotational speed of the wind turbine generators.
1.3) Establishing constraint conditions of wind power stability, the main steps are as follows.
1.3.1) Determining the synchronization characteristics of the wind turbine generators, namely:
In the above formulas, PE is the active output of the wind turbine generators. KDL is the de-load factor of the wind turbine generators. When the wind turbine generators are working at maximum power tracking mode, the coefficient KDL is the maximum power tracking coefficient, and KDLωr3 is the output of the wind turbine generators when there is no virtual inertia response. p is the air density. R is the diameter of the rotor of the wind turbine generators. v is the wind speed. Cp is the power coefficient of the wind turbine generators. PM is the mechanical power of the wind turbine generators. β is the pitch angle of the wind turbine generators.
Wherein, the tip speed ratio λ is shown as follows.
1.3.2) At a certain wind speed, the stability condition of the wind turbine generator is that the curve of formula (4) and the curve of formula (5) have at least one intersection, otherwise the wind turbine generators may lose its balance point and cause instability. Therefore, the stability limit of the wind turbine generators is that the curve of formula (4) and the curve of formula (5) have one and only one intersection point, which is the tangent point of the curve of formula (4) and the curve of formula (5). Therefore, the limit operating speed ωrc of the wind turbine generators is calculated by deriving formula (4) and formula (5).
1.3.3) Substituting the limit operating rotational speed ωrc of the wind turbine generators into formula (5), calculating to obtain the limit operating point of the wind turbine generators
Connecting the extreme operating points at each wind speed to form the stability boundary of the wind turbine generators, and substituting formula (6) into formula (7) to calculate the limit tip speed ratio λc. The limit tip speed ratio λc meets the following formula.
1.3.5) Establishing the expression formula of the relationship between wind speed and rotor rotational speed on the stability boundary of the wind turbine generators, namely:
1.3.6) Substituting formula (9) into formula (5), and calculating to obtain the expression formula of the stability boundary of the wind turbine generators, namely:
1.3.7) Based on formula (10), updating the limit operating point of the wind turbine generators to (ωrc, Kcωr3).
1.3.8) Establishing the stability constraints of the wind turbine generators when provides frequency response, and it is divided into the following three situations.
I) When the wind turbine generator is operating at the lowest speed, the wind turbine generator does not provide frequency response. The frequency response of the wind turbine generator is as follows.
In the above formulas, ωr0 is the rotor rotational speed in the initial operating state of the wind turbine generators.
II) When the limit operating rotational speed ωrc is less than the lowest speed ωmin, the stability constraints of the wind turbine generators when provides frequency response are as follows.
In the above formulas, FM(ωmin) is the mechanical power of the wind turbine generators at the lowest rotational speed ωmin.
III) When ωrc≥ωmin, the stability constraints of the wind turbine generators when provides frequency response are as follows.
1.4) Establishing the output constraints of the wind turbine generators when provides frequency response, and the main steps are as follows.
1.4.1) Updating the active output PE* of the wind turbine generators, namely:
In the above formulas, Pw is the available power of the wind turbine generators. dw is the reserve coefficient of the wind turbine generators, and (1−dw)Pw is the actual output of the wind turbine generators when does not provide frequency response output.
1.4.2) Establishing the output constraints of the wind turbine generators when provides frequency response, namely:
In the above formulas, Pwmax is the maximum output of wind turbine generators.
1.5) Combining formula (10), formula (12), formula (13) and formula (15), the security region of the wind turbine generators meets formula (16) to formula (19), namely:
2) Based on the security region of the wind turbine generators when provides frequency response, establishing a unit commitment model considering the security region of the wind turbine generators. The main steps are as follows.
2.1) With the goal of minimizing the operating cost of the traditional synchronous generator, establishing the objective function, namely:
In the above formulas, ζ is a set of traditional synchronous generators. cg is the marginal cost. cgnl is the no-load cost. cgsu is the start-up cost. Pg,i is the active power of the traditional synchronous generator. Ng,ion is an online synchronous generator. Ng,isu is the synchronous generator turned on at step i. T is the total optimization time scale. Δt is the unit time interval. Variables with the subscript i represent the variables of the i-th step. Variables with subscript g represent variables related to traditional synchronous generator g. Variables with subscripts g,i represent the related variables of the traditional synchronous generator g at the i-th step.
2) Establishing constraints of traditional unit commitment, which include power flow constraints, synchronous generator constraints, system frequency stability constraints, frequency change rate constraints, frequency lowest point constraints, and wind turbine generators security region constraints.
2.2.1) Power flow constraints are as follows.
In the above formulas, W is a set of wind turbine generators. Li is the total load of the system. The wind turbine generators parameters are all aggregate parameters. Variables with subscript w represent variables related to wind turbine generators w. Variables with subscripts w,i represent related variables of wind turbine generators w at step i.
2.2.2) Synchronous generator constraints are shown in formula (22) to formula (28).
In the above formulas, Pgmin and Pgmax are the minimum value and maximum value of the synchronous generator output, respectively. ΔPgmax is the maximum value of the output change of the synchronous generator. ΔPgsu max and ΔPgsd max are the maximum upward and downward climbing power of the synchronous generator, respectively. Ng, isd is the number of synchronous generators shut down in step i. Ng,ioff is the number of synchronous generators offline at step i. Δtgup and Δtgdw are the minimum start and stop time of the unit. i∈T. g∈ζ.
2.2.3) The system frequency stability constraints are as follows.
Wherein, Di is the load damping coefficient. Hi is the system inertia time constant. Ki is the frequency response coefficient.
Wherein, the system inertia time constant Hi is shown as follows.
In the above formulas, Hg is the inertia time coefficient of synchronous generator. The optimized variables in formula (30) are the virtual inertia control parameters Jw,i of the online synchronous generator Ng, ion and the wind turbine generators at i-th step. f0 is the reference frequency of the power system.
The frequency response coefficient Ki controlled by the P-f of the synchronous generator and wind turbine generators is shown as follows.
In the above formulas, Kg=1/Kdroop-g. Kdroop-g is the droop control parameter of the synchronous generator. The optimized variables in formula (31) are the frequency response parameter Kw,i of the online synchronous generator Ng, ion and the wind turbine generators at the i-th step.
System frequency deviation Δf is shown as follows.
Frequency change rate dΔf/dt is shown as follows.
2.2.4) Frequency change rate constraints are shown as follows.
2.2.5) Frequency lowest point constraints are shown as follows.
2.2.6) Based on formula (1), formula (2), formula (32) to formula (35), establishing the equation of frequency response provided by the wind turbine generators, namely:
2.2.7) Substituting formula (36) into formula (17) to formula (19) to establish the security region constraints of the wind turbine generators, which are shown as formula (37) to formula (43) respectively.
3) Calculating the unit commitment model considering the wind turbine generators security region by using mixed-integer linear programming method, to obtain the operation result of the unit commitment considering the wind turbine generators security region with frequency response control.
An experiment to verify the unit commitment method considering the wind turbine generators security region with frequency response control, mainly comprises the following steps.
1) Taking the UK 2030 power system (GB 2030 power system) as test system. Information of the synchronous generator is shown in Table 1.
The maximum and minimum load requirements of the system are 30 GW and 60 GW. The capacity of a single wind turbine generators is 1.5 MW, and the total wind power capacity of the system changes according to demand. In each case, the total wind power output accounts for about 35% of the load. The load damping parameter is set to D=0.5%/Hz. Considering the typical N−1 failure scenario, the maximum power fluctuation of the system is the push operation of the synchronous unit with the largest capacity ΔLmax=1800 MW. The limit value of the frequency drop rate is (dΔf/dt)max=0.5 Hz/s, and the lowest point of the frequency is Δfnadir=0.5 Hz/s. The unit commitment is solved by gurobi.
2) Determining the influence of wind turbine generators security region on unit commitment.
It can be seen from
Therefore, the period of effective constraint distribution is as follows.
It can be seen from Table 2 and Table 3 that in the high wind speed section, the security region constraints are mainly determined by the output constraints. In the medium wind speed section, the security region constraints are mainly determined by the stability constraints. In the low wind speed section, the security region constraints are mainly determined by the rotor rotational speed constraints. The security region of the wind turbine generators when provides inertia response changes with the changes of wind speed. Therefore, the inertia response parameter of the wind turbine generators should not be set to a fixed value, but should be optimized in real time with changes of wind speed and system status.
The system frequency indexes are shown in
It can be seen from
3) The influence of wind turbine generators reserve capacity on frequency response output.
When considering the reserve capacity of wind turbine generators, its frequency response output is shown in
According to the analysis in the previous section, the main effective constraints of this embodiment are the output constraints of the wind turbine generators. Therefore, when the wind power has a certain amount of reserve capacity, it can effectively expand the security region of the wind turbine generators, thereby improving the ability of the wind turbine generators to provide frequency response.
To ensure the stability of the system frequency, when the wind turbine generators inertia response is insufficient, more synchronous generators need to be launched. Since the synchronous generators are restricted by minimum output and climbing constraints, the launch of a large number of synchronous generators will compress the penetration rate of wind turbine generators and cause a large amount of wind curtailment.
In this embodiment, the wind power utilization rate is shown in Table 4, and the wind power utilization rate unlisted dispatching points is 100%. At the dispatch points of 0-2 and 23, due to the influence of thermal power climbing constraints, it is impossible to fully balance the fluctuations of the wind turbine generators output, which results in partial wind power curtailment. During this time period, the curtailed wind can be fully utilized as a reserve. Other dispatching points need to sacrifice part of the wind power output as reserve capacity. It can be seen from Table 4 that after considering the reserve of wind turbine generators, although part of the wind power output is reduced, the security region of wind power is expanded, and the inertia response capability of wind turbine generators is enhanced, which reduces the pressure of synchronous generators to provide frequency response, thereby reducing the number of online synchronous power generator, and increasing the utilization rate of wind power output.
The method provided by the present invention can effectively optimize the wind power reserve capacity and fully guarantee the wind power utilization rate.
From the experimental results, it can be seen that the unit commitment method considering the security region of wind turbine generators with frequency response control proposed by the present invention can ensure the safe operation of the wind turbine generators while meeting the needs of system frequency stability, and can make full use of the reserve capacity of the wind turbine generators to improve the ability of providing frequency response by the wind turbine generators, improve wind power utilization and reduce the wind curtailment.
In summary, the present invention proposes a unit commitment method considering both frequency stability and safe operation of wind turbine generators. Comprehensively considering the stability constraints, rotational speed constraints and output constraints of wind turbine generators, and the security region of wind turbine generators when provides frequency response is deduced. With the goal of minimizing the operating cost of synchronous generator, the system frequency stability constraints and wind turbine generators security region constraints are added to the traditional unit commitment model to achieve economic, stable and safe operation of the entire system. The study of the embodiment shows that the method provided by the present invention can effectively guarantee the stability of the system frequency and the safe operation of wind turbine generators. It can make full use of wind power resources by optimizing the reserve capacity of wind turbine generators, and can provide guidance to the set of frequency response parameters of wind turbine generators and the unit commitment considering high-penetration wind turbine generators.
Number | Date | Country | Kind |
---|---|---|---|
201911225185.5 | Dec 2019 | CN | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/CN2020/101932 | 7/14/2020 | WO |