Variable buoyancy buoy for mooring mobile offshore drilling units

Abstract
In a system for mooring offshore drilling units, a first mooring assembles installed at a first drilling venue, after which the mobile offshore drilling unit is moored by connection to the mooring lines. A second mooring assembly is installed at a second drilling venue while drilling operations are carried out at the first drilling venue. In this manner the mobile offshore drilling unit can be relocated between successive drilling venues with minimum down time. Less than complete mooring assemblies can be used to temporarily secure the mobile offshore drilling unit.
Description




TECHNICAL FIELD




This invention relates generally to mooring systems, and more particularly to recoverable systems for mooring mobile offshore drilling units in deep water.




BACKGROUND AND SUMMARY OF THE INVENTION




As is well known, exploration for and recovery of oil and gas has long since extended into offshore venues. Early offshore drilling operations were concentrated in relatively shallow waters. However, the number of shallow water drilling sites is finite, while the world's appetite for oil and gas is seemingly unlimited. It has therefore become necessary to conduct offshore drilling operations in waters as deep as 10,000 feet or more.




Offshore drilling operations are frequently conducted from floating platforms known as mobile offshore drilling units (MODUs). While the mooring of offshore drilling units in shallow water is relatively straightforward, the successful mooring of MODUs in deeper water can be problematic.




The traditional method of mooring MODUs in deeper water involves the use of drag embedment anchors and mooring lines which are stored on the MODU, and which are deployed from the MODU using anchor handling vessels. Some of the latest generation MODUs can carry adequate lengths of wire and chain on board, and are equipped with combination wire/chain mooring winches to moor at maximum depths of 5,000 feet of water. Large anchor handling vessels are capable of deploying and recovering such mooring legs and anchors. In even deeper water, however, the amount of wire and chain that would have to be carried on the MODU becomes too large, and even large anchor handling vessels would have difficulty deploying and recovering such mooring systems in the traditional manner.




Older generation MODUs typically cannot carry enough mooring line to moor in water deeper than about 2,000 to 3,000 feet. This water depth limit can be extended by inserting sections of wire in each mooring leg, or by pre-installing mooring legs prior to arrival of the MODU at location. Both types of extended water depth mooring legs (insert or preset) typically use modern high holding power drag embedment anchors. Large anchor handling vessels are used to install the wire inserts during mooring leg deployment or to pre-install the preset mooring legs.




One drawback to deep water MODU moorings using drag embedment anchors is that such anchors typically cannot handle uplift (vertical load), which requires both that the mooring leg is very long, and that the anchor is set very far from the MODU. In water depths over 6,000 feet the horizontal distance to the anchors can become a problem, since it could be as large as 12,000 feet or 2 nautical miles, and each mooring leg could be as long as 15,000 feet or 2.5 nautical miles. This requires an anchor spread diameter of about 4 nautical miles.




If an anchor system can be used which can handle substantial uplift or vertical load, the anchor radius and mooring line length can be reduced significantly. Driven anchor piles are capable of handling uplift, but cannot be installed in deep water nor are they recoverable. For this reason, driven anchor piles have never been used for MODU moorings.




Mooring systems employing anchors other than drag embedment anchors and driven piles have been proposed heretofore. For example, U.S. Pat. No. 4,318,641, granted to Hogervorst on Mar. 8, 1982, discloses mooring systems employing suction embedment anchors, which are capable of taking significant uplift or vertical load. However, prior to the present invention, there has not been provided a successful system for installing and recovering suction anchors in very deep water thereby facilitating ultra deep water drilling operations.




The present invention comprises a system for mooring mobile offshore drilling units which overcomes the foregoing and other difficulties long since associated with the prior art. In accordance with the broader aspects of the invention, mobile offshore drilling units are moored using anchors which are recoverable and reusable upon the completion of drilling operations. In accordance with a preferred embodiment of the invention, recoverable suction anchors are employed, and in accordance with another embodiment of the invention vertically loaded anchors are employed. Recoverable drag embedment anchors can also be used in the practice of the invention, if desired.




Regardless of the anchor type employed, the present invention comprises a method of mooring MODUs wherein a first set of recoverable preset mooring legs with suitable anchors are pre-installed at spaced apart locations surrounding an offshore drilling venue. After the recoverable preset mooring legs are installed, a MODU is positioned at the drilling venue, and connected to the preset mooring legs by short lengths of the mooring chain or-wire extending from mooring winches on the MODU.




While drilling operations are being conducted from the MODU, a second set of mooring legs is preset at spaced apart locations around a second drilling venue. When drilling operations have been completed at the first drilling venue, the mobile offshore drilling unit is moved from the first drilling venue to the second drilling venue, and is secured in place at the second drilling venue by connection to the second set of preset mooring legs surrounding the second drilling venue. The mobile offshore drilling unit is then used to conduct drilling operations at the second drilling venue in the usual manner.




While drilling operations are being conducted at the second drilling venue, the first set of mooring legs is recovered from the first drilling venue and is moved to a third drilling venue. The mooring legs from the first drilling venue are then preset at spaced apart locations surrounding the third drilling venue with the installation thereof being completed prior to the movement of the mobile offshore drilling unit from the second drilling venue to the third drilling venue. This process continues until drilling operations have been completed at all of the drilling venues within a particular area, whereupon all of the mooring legs and the MODU are removed to a different area.




The present invention may also be practiced using less than two complete sets of mooring legs. In such instances, a reduced number of mooring legs, for example, one half of a complete set, is installed at a second drilling venue. The MODU is then moored to the second drilling venue and secured in place using the preset mooring legs then in place. Next, the remainder of the mooring legs comprising a complete set are installed, whereby the MODU is fully secured. This procedure is repeated until drilling operations are completed at a particular location.











BRIEF DESCRIPTION OF THE DRAWINGS




A more complete understanding of the present invention may be had by reference to the following Detailed Description when taken in connection with the accompanying Drawings wherein:





FIG. 1

is a diagrammatic illustration of the method of mooring mobile offshore drilling units comprising the present invention;





FIG. 2

is an illustration of a preset taut mooring leg with a recoverable anchor in its pre-installed configuration useful in the practice of the invention.





FIG. 3

is a view similar to

FIG. 2

showing the mooring leg attached to a mobile offshore drilling platform;





FIG. 4

is a side view of a suction anchor useful in the practice of the invention;





FIG. 5

is an illustration similar to

FIG. 4

wherein the suction anchor is rotated 90 degrees;





FIG. 6

is a top view of the suction anchor of

FIG. 4

;





FIG. 7

is an enlargement of the pad eye of the suction anchor of

FIG. 4

;





FIG. 8

is a sectional view of the pad eye of FIG.


7


:





FIG. 9

is a top view of a submerged buoy useful in the practice of the invention;





FIG. 10

is a longitudinal sectional view of the buoy of

FIG. 9

;





FIG. 11

is a bottom view of the buoy of

FIG. 9

;





FIG. 12

is a top view of an installation vessel useful in the practice of the invention;





FIG. 13

is a side view of the vessel of

FIG. 12

;





FIG. 14

is an illustration of an early stage in the installation of a suction anchor in accordance with the present invention;





FIG. 15

is an illustration of a somewhat later stage in the installation of the suction anchor;





FIG. 16

is an illustration of a still later stage in the installation of the suction anchor;





FIG. 17

is an illustration of a still later stage in is the installation of the suction anchor;





FIG. 18

is an illustration of a still later stage in the installation of the suction anchor;





FIG. 19

is an illustration of a still later stage in the installation of the suction anchor;





FIG. 20

is an illustration of a still later stage in the installation of the suction anchor;





FIG. 21

is an illustration of a still later stage in the installation of the suction anchor;





FIG. 22

is a top view of a pumpskid useful in the practice of the invention;





FIG. 23

is a side view of the pumpskid of

FIG. 22

;





FIG. 24

is an end view of the pumpskid of

FIG. 22

;





FIG. 25

is an illustration of the final stages in the installation of the suction anchor;





FIG. 26

is an illustration of an early stage in the removal of the suction anchor in accordance with the present invention;





FIG. 27

is an illustration of a later stage in the removal of the suction anchor;





FIG. 28

is an illustration of a still later stage in the removal of the suction anchor;





FIG. 29

is an illustration of a recoverable system for mooring offshore drilling units comprising a second embodiment of the invention;





FIG. 30

is an illustration of a recoverable system for mooring mobile offshore drilling units comprising a third embodiment of the invention;





FIG. 31

is an illustration of a recoverable system for mooring offshore drilling units comprising a fourth embodiment of the invention;





FIG. 32

is an illustration of a recoverable system for mooring mobile offshore drilling units comprising a fifth embodiment of the invention;





FIG. 33

is an illustration of a recoverable system for mooring mobile offshore drilling units comprising a sixth embodiment of the invention;





FIG. 34

is an illustration of a first type of vertically loaded anchor useful in the practice of the invention;





FIG. 35

is an illustration of a second type of vertically loaded anchor useful in the practice of the invention; and





FIG. 36

is an illustration of the vertically loaded anchor of

FIG. 35

showing the anchor in the installed configuration.











DETAILED DESCRIPTION




Referring now to the Drawings, and particularly to

FIG. 1

thereof, there is shown an area


30


comprising a portion of the ocean or other water body suitable for underwater drilling operations. Area


30


includes at least three drilling venues,


32


,


34


, and


36


. Venue


32


comprises a previously drilled location at which drilling operations have been completed. Venue


34


comprises a current drilling location wherein drilling operations are currently underway. Venue


36


comprises a yet-to-be drilled location at which drilling operations have not yet begun.




In accordance with the present invention, a mobile offshore drilling unit


38


(MODU) is employed to conduct drilling operations at venues


32


,


34


, and


36


. During the time that drilling operations were in progress at venue


32


, the mobile offshore drilling platform


38


was secured in place at venue


32


by a first mooring assembly


40


comprising a plurality of mooring legs


42


each including a mooring line


44


connected to the mobile offshore drilling unit


38


. Although the mooring assembly


40


is illustrated as comprising eight mooring legs


42


, it will be understood that the invention is not limited to any particular number of mooring legs, with the actual number employed being dependent upon the requirements of particular applications of the invention, and that in some cases


9


,


10


, or more mooring legs will be required in order to properly moor a particular MODU.




After drilling operations are completed at drilling venue


32


, the mobile offshore drilling unit


38


is disengaged from the first mooring assembly


40


and is towed or otherwise repositioned at drilling venue


34


. Prior to the repositioning of the mobile offshore drilling unit


38


from venue


32


to venue


34


, a second mooring assembly


46


also comprising mooring legs


42


including mooring lines


44


extending therefrom is preset at venue


34


. The use of multiple mooring assemblies and the installation thereof at drilling venues prior to the positioning of the mobile offshore drilling unit at the drilling venue comprises an important feature of the invention in that it allows the mobile offshore drilling unit to be secured in place and ready for operation very rapidly.




After the mobile offshore drilling unit


38


has been disengaged therefrom, the first mooring assembly


40


is recovered from drilling venue


32


and is transported to drilling venue


36


. The mooring legs


42


and the mooring lines


44


associated therewith comprising the first taut-leg mooring assembly


40


are preset at drilling venue


36


while drilling operations are progressing at drilling venue


34


. Later, after drilling operations are completed at drilling venue


34


, the mobile offshore drilling unit


38


is disconnected from the mooring assembly


46


and is towed or otherwise repositioned at drilling venue


36


. The mobile offshore drilling unit


38


is then secured in place at drilling venue


36


utilizing the first mooring assembly


40


. The foregoing steps are repeated until drilling at all of the venues comprising a particular one has been completed, whereupon the mooring assemblies and the MODU are moved to a different area.





FIG. 1

further illustrates two alternative procedures for mooring MODUs in accordance with the present invention. The first alternative procedure involves the use of a single mooring assembly, for example, the mooring assembly


40


. The mobile offshore drilling unit


38


is initially secured at the first drilling venue


32


utilizing the mooring assembly


40


, including all of the mooring legs


42


thereof.




After drilling operations are completed at the first drilling venue


32


, half of the mooring legs


42


comprising the mooring assembly


40


are disengaged and are repositioned at the second drilling venue


34


. The mobile offshore drilling unit


38


is then repositioned to the second drilling venue


34


and is secured in place utilizing the drilling legs


42


comprising part of the mooring assembly


40


which have been preset at the second drilling venue


34


. Thereafter, the remainder of the drilling legs


42


comprising the mooring assembly


40


are installed at the second drilling venue


36


, whereupon the mobile offshore drilling unit


38


is fully secured. This procedure is repeated until all of the drilling venues in a particular area have been drilled, after which the mooring legs


42


comprising the mooring assembly


40


are recovered and the mooring assembly


40


and the mobile offshore drilling unit


38


are removed to a new drilling area.




The second alternative procedure involves the use of one complete mooring assembly


40


and a second mooring assembly


46


comprising, for example, one half of the number of mooring legs utilized in the complete mooring assembly


40


. The mobile offshore drilling unit


38


is initially secured in place at the first drilling venue


32


utilizing the complete mooring assembly


40


. While drilling operations are in progress at the first drilling venue


32


, the partial mooring assembly


46


is preset at the second drilling venue


34


.




Upon completion of drilling operations at the first drilling venue, the mobile offshore drilling unit


38


is relocated to the second drilling venue


34


and is secured in place utilizing the mooring legs


42


comprising the partial mooring assembly


46


. Thereafter, half of the mooring legs


42


from the complete mooring assembly


40


are installed at the second drilling venue


34


, whereupon the mooring assembly


46


becomes a complete mooring assembly and the mooring assembly


40


becomes a partial mooring assembly. During the time that drilling operations are in progress at the second drilling venue


36


, the partial drilling assembly


40


is preset at the third drilling venue


36


.




After drilling operations are completed at the second drilling venue


34


, the mobile offshore drilling unit


38


is repositioned to the third drilling venue


36


and is secured in place by the drilling legs


42


comprising the partial drilling assembly


40


. Thereafter, half of the mooring legs comprising the taut-leg mooring assembly


46


are installed at the third drilling venue


36


. This procedure is repeated until all of the drilling venues at a particular drilling location have been drilled, whereupon all of the drilling legs comprising the drilling assemblies


40


and


46


are recovered and are moved to a new drilling area along with the mobile offshore drilling unit


38


.




Referring now to

FIG. 2

, the mooring legs


42


and the is mooring lines


44


associated therewith comprising the mooring assemblies


40


and


46


are illustrated in greater detail. The mooring legs


42


preferably comprise taut-leg mooring legs which include suction anchors


43


constructed either from steel or from concrete. For example, a steel suction anchor comprising a cylindrical tube 12 feet in diameter, 60 feet in length, and having a wall thickness of 1 and ½ inches may be utilized in the practice of the invention. Special drag embedment anchors designed for high vertical loading, also known as Vertically Loaded Anchors (VLAs) may also be utilized in the practice of the invention, if desired.




In the case of a drilling venue having a water depth of 7,500 feet, the mooring line


44


of each mooring leg


42


comprises a 5,500-foot long, 3.88-inch diameter first segment of riser line


50


attached to and extending from the anchor


43


. A 4 and ½-inch diameter connecting link


51


of the type manufactured by Kenter, Baldt, Bruce, or Ramnäs is attached to the distal end of the riser line


50


. A 5,500-foot second segment of riser line


52


is attached at its proximal end to the connecting link


51


. A 3.38-inch diameter, 15-feet long, buoy pigtail chain


53


is attached to the distal end of riser line segment


52


. A plurality of submerged buoys


54


having a 145-kip total net buoyancy are attached to the distal end of the buoy pendent wire


53


.




Below each buoy


54


there is a 15-foot×3.38-inch chain section


53


, and there is a 100-foot×3.88-inch wire rope pendant


58


between the buoys


54


. A 3.88-inch diameter, 50-foot length of wire


60


extends from the upper buoy


54


to a connector


62


. A 15-foot 2.5-inch diameter wire


63


extends from the connector


62


to a submerged buoy


64


having a buoyancy of between about 3 and about 5 kips. A buoyant line


65


formed from synthetic material, for example Samson® ultrablue 3.5-inch diameter line extends to a floating marker buoy


66


.




In

FIG. 3

there is illustrated the connection of the mooring line


44


to the mobile offshore drilling unit


38


. A 3.88-inch diameter wire


68


of about 800 feet length deployed by the MODU from its mooring winch, and secured to a 150-foot long×3.38-inch diam. K


4


chain


69


, which is inserted by the hook-up vessel between the preset mooring line and the MODU's mooring wire. The line


63


, the submerged buoy


64


, the line


65


, and the floating marker buoy


66


are removed when the MODU


38


is connected to the taut-leg mooring leg


42


.




It will be understood that the foregoing indications of length, diameter, and type of the component parts of the mooring line


44


are representative only, and that the actual dimensions of the component parts of the mooring line


44


will depend at least on three factors: first, the depth of the water in which the mooring line is used; second, the particular material selected for use in the fabrication of each component part of the mooring line


44


; third, the size of the MODU. It will be further understood that the use of one or more submerged buoys


54


as a component part of each mooring line


44


comprises an important feature of the invention in that it allows the mobile offshore drilling unit


38


to be secured rapidly in place by a taut-leg mooring system. In addition, the use of the buoys


54


significantly improves the performance of the taut-leg mooring system and reduces the vertical loads imposed on the MODU by the mooring legs.




Turning now to

FIGS. 4 through 8

, therein is shown a steel suction anchor


70


useful in the practice of the invention. The suction anchor


70


is a right circular cylinder 12 feet in diameter and 60 feet in length, having a wall thickness of 1.5 inches. Skids


71


, which may comprise lengths of angle iron or lengths of pipe cut in half longitudinally are welded to the cylinder comprising the anchor


70


to prevent it from rolling on the deck of the installation vessel.




The suction anchor


70


is open on the lower end


72


and closed at the upper end


74


by a plate


76


. A pad eye


78


, for receiving mooring line


44


, is attached on an exterior side of suction anchor


70


approximately 40 feet from the top. The top closure plate


76


on the upper end


74


of suction anchor


70


includes ports


82


which allow water to flow through the closure plate


76


as the anchor


70


heaves up and down during lowering to and retrieval from the sea floor. The ports


82


are opened and closed by worm gear actuators


83


which are in turn operated by a manipulator extending from a remote operation vehicle (ROV)


300


which is located relative to the skid


80


by docking posts


84


.




Alignment of the anchor


70


is determined using a camera on the ROV


300


which observes a bullseye level


85


. The ROV


300


also adjusts the horizontal alignment of the suction anchor


70


by checking the suction anchor's heading with a gyrocompass on board the ROV. If the horizontal alignment is out of tolerance, the ROV


300


rotates the suction anchor


70


by activating thrusters on the ROV. The placement of the ROV


300


on the outer edge of the closure plate


80


ensures that the ROV's thrusters can apply adequate torque to rotate the suction anchor


70


about its axis.




Pad eyes


86


are used to connect the anchor to a recovery bridle. An alternate pad eye


87


may be used with a single recovery pendant or with double recovery sling. A suction port


88


having a clamp down hub is engaged by the ROV


300


to effect pumping of water into or out of the anchor


70


.




The submerged buoys


58


utilized in the mooring lines


44


are further illustrated in

FIGS. 9

,


10


, and


11


. Each buoy


54


comprises a frame


90


including a hollow central shaft


92


and a bottom plate


94


secured thereto. A pad eye


96


is secured at the bottom of the shaft


92


for use in securing the buoy


54


in the mooring line


44


. A top plate


98


is mounted at the upper end of the shaft


92


and is secured in place by a bolt


100


. The upper end of the shaft


92


is provided with a pad eye


102


for use in securing the buoy


58


in. the mooring line


44


.




The buoy


58


further comprises a primary buoyancy member


104


and a plurality of auxiliary members


106


which are added to or removed from the buoy


54


depending on the amount of buoyancy required by the water depth and the particular applications of the invention. All of the buoyancy members


104


and


106


comprise syntactic foam. An outer protective layer of glass reinforced polyester may be provided around the buoyancy members


104


and


106


, if desired. It will be understood that the top plate


98


is secured in place on the buoy


54


by extending the bolt


100


through selected holes


108


formed in the shaft


92


depending upon the number of auxiliary buoyancy members


106


that are utilized in a particular application of the invention.




Referring now to

FIG. 12

, therein is illustrated a top view of the deck


110


of an installation vessel


112


. The deck


110


of the vessel


112


supports suction anchors


70


during transportation to a drilling venue.

FIG. 13

is a side view of the transportation vessel


100


and the anchors


70


.




Referring now to

FIG. 14

therein is illustrated the initial deployment stage of the suction anchor


70


. The installation vessel


110


is positioned at the drilling venue with its bow into the prevailing seas. Recovery pendent line


142


and a recovery buoy


146


are rigged to the top of the suction anchor


70


by connection to the pad eyes


87


.




It is also possible to install and recover the suction anchor


70


without using the recovery buoy


146


. In such instances there is provided a doubled sling secured to the top of the suction anchor


70


which is laid down across the suction anchor and onto the sea floor. For recovery of the suction anchor, the ROV


300


connects a special hook to the doubled sling. This option comprises an important feature of the invention since recovery buoys suitable for use in very deep water are expensive to purchase and maintain.




The recovery buoy


146


, if used, is secured to a nylon stretcher


139


which is in turn secured to a multi-strand lowering wire


140


spooled off an auxiliary vessel


200


. The nylon stretcher


139


allows the stern of the auxiliary vessel


200


to heave in the seas without overloading the lowering wire


140


. An upper drum work wire


150


is rigged over an A-frame gantry


158


and connected to the suction anchor


70


. A lower drum work wire


152


is also connected to the suction anchor for use as a hold back line.




Turning now to

FIGS. 15 through 19

, the auxiliary vessel


200


moves away from the installation vessel


100


paying out approximately 100 feet of the lowering wire


140


. The auxiliary vessel


200


stops paying out lowering wire


140


and increases tension in the lowering wire. Slowly the lower drum work wire


152


allows the auxiliary vessel


200


to pull the suction anchor


70


out into the water. The A-frame gantry


158


is moved slowly aft, as required, payingout the riser wire


50


. The upper drum work wire


150


lifts the lower end of the suction anchor


70


and the lower drum work wire


152


is disengaged. As shown in

FIG. 19

, the riser wire


50


is payed out while the auxiliary vessel


200


moves closer to the installation vessel


110


. The upper drum work wire


150


is disengaged, the suction anchor


70


swings down under the stern of the auxiliary vessel


200


and the weight of the suction anchor


70


is transferred to the lowering wire


140


.




Turning now to

FIG. 20

, a remote operation vehicle (ROV)


300


is deployed from the auxiliary vessel


200


. ROV


300


may comprise a Raycal SEA Lion MK II heavy work class ROV having


100


horsepower; however, any of the various commercially available ROV's having 75 h.p. or more can be used in the practice of the invention. The lowering wire


140


and riser wire


50


are paid out until the suction anchor reaches the ocean floor. Meanwhile the auxiliary vessel also pays out the ROV's umbilical wire


302


, so that the ROV can observe the suction anchor during its descent.




As shown in

FIG. 21

, the suction anchor


70


is slowly lowered into the seafloor under its own weight. Meanwhile the ROV


300


observes the bullseye level


85


on the top of the suction anchor


70


to assure that the suction anchor remains vertical within established tolerances. Under its own weight, the suction anchor


70


will penetrate about 40%-50% of its length into the seafloor (typical in the-Gulf of Mexico). The ROV


300


next checks the amount of self penetration by reading the penetration marks at the mudline, while the lowering line


140


is slacked off. During the lowering process the evacuation ports


82


and suction port


88


remain open, allowing water displaced by the ocean floor inside the suction anchor to flow outwardly through these ports.




As shown in

FIGS. 22

,


23


, and


24


, the ROV


300


is fitted with a pumpskid


160


which is mounted beneath the ROV. The pumpskid


160


includes a pump


162


, pump manifold valve actuators


164


and


165


, and latching actuators


166


, all powered and controlled by the hydraulic system of the ROV


300


. The pumpskid further includes a male connector


168


for the suction port


88


.




Next, the ROV


300


docks and latches onto the suction anchor and its suction port


88


by engagement of the male connector


168


and by engaging the latching actuators onto the clamp down hub of the suction port


88


. Next, the ROV closes the ports


82


. The pump


162


of the pumpskid


160


is started and pumps water out of the interior of the suction anchor


70


, reducing the water pressure inside relative to the outside pressure. This is accomplished by means of actuator


164


which opens valve


170


and closes valve


172


and actuator


165


which opens valve


174


and closes valve


176


, thereby causing water to flow through suction port


88


, valve


174


, pump


162


, and valve


170


, and then out-through opening


178


.




The differential pressure under the action of pump


162


acts as a downwards force on the top of the suction anchor


70


pushing the suction anchor further into the seafloor to the desired penetration depth. When the desired penetration has been reached, as determined from the ROV's depth monitoring system, the ROV disconnects from the top of the suction anchor


70


. Next the ROV checks the suction anchor penetration by reading the penetration marks at the mudline. When the suction anchor


70


penetration is found to be within tolerance, the ROV


300


closes the suction port


88


so that all openings in the top of the suction anchor are closed. As is shown in

FIG. 25

, the ROV


300


now disconnects lowering line


140


from the recovery buoy


146


. Next the ROV is retrieved by the auxiliary vessel


200


.




Turning now to

FIG. 26

,


27


, and


28


, therein is illustrated a recovery procedure that may be employed to recover the suction anchor


70


after drilling operations at a particular drilling venue are completed. The installation vessel


112


is attached by the riser wire


50


to the suction anchor


20


. The auxiliary vessel


200


lowers the ROV


300


with the pumpskid


160


on the umbilical wire


302


, while at the same time the recovery wire


240


is lowered to the seafloor. The recovery wire


240


is equipped with a special hook, and a submerged buoy


242


some distance above the hook. The submerged buoy


242


isolates the hook from much of the auxiliary vessel's heave motions. The ROV


300


attaches the hook to the doubled sling on the recovery buoy, or to the doubled sling laying across the suction anchor. The auxiliary vessel takes up tension on the recovery line


240


, and the ROV


300


docks onto the suction anchor top and latches onto the suction port


88


. The ROV


300


pumps water into the interior of the suction anchor by means of the pump


162


. This is accomplished by operating the actuators


164


and


165


to open valve


176


, open valve


172


, close valve


174


, and close valve


170


, thereby causing water to flow through opening


178


, valve


172


, pump


162


, valve


176


and port


88


into anchor


70


.




Due to the pump


162


, the water pressure inside becomes greater than the outside water pressure, and the differential pressure results in an upwards force on the suction anchor top. The upwards force, and the pull on the recovery line pulls the suction anchor out of the seafloor. If too much pump pressure is required to pull the suction anchor


70


out of the seafloor, due to too much consolidation of the soil around and inside the suction anchor, the water flow direction of the pump


162


can be reversed instantaneously by changing the positions of valve actuators


164


and


165


. By rapidly changing the water flow direction from pumping in to pumping out, the suction anchor


70


will be alternately pulled out and pushed in. When this is done over time, the soil in contact with the suction anchor cylinder will liquefy, making it easier to pump and pull the suction anchor out off the soil. The suction anchor


70


is raised to the surface by recovery line


240


and is loaded on installation vessel


112


using the riser line


50


.




Referring now to

FIG. 29

, there is shown a catenary mooring leg


342


which may be used in the practice of the invention in lieu of the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described hereinabove in conjunction therewith. The mooring leg


342


may employ a suction anchor of the type illustrated in

FIGS. 4

,


5


,


6


,


7


, and described hereinabove in conjunction therewith. Alternatively, the mooring leg


342


may employ a vertically loaded anchor. Referring momentarily to

FIGS. 34

,


35


, and


36


, the vertically loaded anchor may comprise a vertically loaded anchor


346


of the type sold by Vryhof under the trademark “STEVMANTA”. Alternatively, the vertically loaded anchor may comprise a vertically loaded anchor


348


of the type sold by Bruce under the trademark “DENIA”. Vertically loaded anchors are particularly adapted to the practice of the present invention for two reasons. First, vertically loaded anchors are designed and adapted to accommodate and withstand relatively high vertical loads and are therefore particularly adapted for use in conjunction with taut-leg mooring legs. Second, vertically loaded anchors are designed and adapted to be recovered after the project for which they are installed has been completed.




Referring again to

FIG. 29

, the mooring leg


342


employs a drag embedment anchor


349


. A 3-inch diameter, 3,300-foot long ORQ ground chain


350


is connected to and extends from the anchor


349


. A 3¼-inch diameter, 9,000-foot long IWRC−EIPS+20% catenary wire


352


is connected to the distal end of the chain


350


and extends upwardly therefrom. A 3-inch diameter, 15-foot long ORQ+20% buoy chain pendant


354


is connected to the distal end of the catenary wire


352


. The 64-foot kip fixed buoyancy submerged buoy


356


is connected to the buoy pendant chain


354


. The buoy


356


is similar to the buoy


54


illustrated in

FIGS. 9

,


10


, and


11


, and described hereinabove in conjunction therewith except that the buoy


356


comprises a single block of syntactic foam similar to the block


104


of the buoy


54


and does not include removable syntactic foam sections such as the foam sections


106


of the buoy


54


.




The buoy


356


is utilized in conjunction with a 57-kip adjustable buoyancy submerged buoy


358


which is identical in construction and function to the buoy


54


illustrated in

FIGS. 9

,


10


, and


11


.




A 3¼-inch diameter, 200-foot long IWRC−EIPS+20% intermediate connection pendant


360


is connected to the upper end of the buoy


356


. A 3-inch diameter, 15-foot long ORQ+20% buoy chain pendant


362


is connected to the distal end of the connection pendant


360


. A 3¼-inch diameter, 400-foot long IWRC−EIPS+20% upper connection pendant


364


is connected to the upper end of the buoy


358


. The upper connection pendant


364


is connected to a 3-inch diameter, 700-foot long ORQ rig chain which extends from the MODU


38


. As will be appreciated by those skilled in the art, the taut-leg mooring leg


342


is typically not employed singly but rather in combination with other, similar taut-leg mooring legs in order to properly stabilize the MODU at a drilling venue.




Referring now to

FIG. 30

, there is shown a catenary mooring leg


372


which may be utilized in the practice of the invention in lieu of the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described hereinabove in conjunction therewith. The mooring leg


372


may employ a suction anchor of the type illustrated in

FIGS. 4

,


5


,


6


,


7


, and


8


and described hereinabove in conjunction therewith. Alternatively, the mooring leg


372


may employ a vertically loaded anchor comprising one of the two types of vertically loaded anchors illustrated in

FIGS. 34

,


35


, and


36


and described hereinabove in conjunction therewith. As shown, the mooring leg


372


uses a drag embedment anchor


374


.




A 3-inch diameter, 3,300-foot long ORQ ground chain


376


is connected to the vertically loaded anchor


374


and extends therefrom. A 3¼-inch, 6,000-foot long IWRC-EIPS+20% catenary wire


378


extends from the distal end of the ground chain


376


. A 3-inch diameter, 15-foot long ORQ+20% buoy chain pendant


380


is connected between the distal end of the catenary wire


378


and a 64-kip fixed buoyancy submerged buoy


382


. The buoy


382


is identical in construction and function to the buoy


360


illustrated in FIG.


29


and described hereinabove in conjunction therewith.




A 3¼-inch diameter, 200-foot long IWRC−EIPS+20% intermediate connection pendant


384


is connected to the upper end of the buoy


382


. A 3-inch diameter, 15-foot long ORQ+20% buoy pendant chain


386


is connected between the distal end of the intermediate connection pendant


384


and a 17-kip adjustable buoyancy submerged buoy


388


. A 3¼-inch diameter, 400-foot long IWRC−EIPS+20% upper connection pendant


390


is connected to the upper end of the buoy


388


. The pendant


390


is in turn connected to a 3-inch diameter, 647-foot long ORQ rig chain


392


extending to and connecting from the MODU


38


. Those skilled in the art will appreciate the fact that the mooring leg


372


is typically not employed singly, but rather is employed in conjunction with other, similar mooring legs in order to properly stabilize the MODU at a drilling venue.




Referring now to

FIG. 31

, there is shown a taut-leg mooring leg


402


which may be utilized in the practice of the invention in lieu of the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described hereinabove in conjunction therewith. The taut-leg mooring leg


402


employs a suction anchor


404


which may be of the type illustrated in

FIGS. 4

,


5


,


6


,


7


, and


8


and described hereinabove in conjunction therewith. Alternatively, the taut-leg mooring leg


402


may employ a vertically loaded anchor of the type illustrated in

FIGS. 34

,


35


, and


36


and described hereinabove in conjunction therewith. A 3-inch diameter, 1,500-foot long K


4


ground chain


406


is connected to the suction anchor


404


and extends upwardly therefrom. A 3½-inch diameter, 8,500-foot long IWRC+20% catenary wire


408


is connected to the distal end of the ground chain


406


and extends upwardly therefrom. A 3-inch diameter, 15-foot long K


4


buoy chain pendant


410


is connected between the distal end of the catenary wire


408


and a 82-kip fixed buoyancy submerged buoy


412


. The buoy


412


is identical in construction and function to the buoy


356


illustrated in FIG.


9


and described hereinabove in conjunction therewith.




A 3½-inch diameter, 200-foot long IWRC−EIPS+20% intermediate connection pendant


414


is connected to the upper end of the buoy


412


. A 3-inch diameter, 15-foot long K


4


buoy chain pendant


416


extends between the distal end of the intermediate connection pendant


414


and a 57-kip adjustable buoyancy submerged buoy


418


. The buoy


418


is identical in construction and function to the buoy


54


illustrated in

FIGS. 9

,


10


, and


11


and described hereinabove in conjunction therewith.




A 3½-inch diameter, 400-foot long IWRC−EIPS+20% upper connection pendant


420


is connected to the upper end of the buoy


418


. The distal end of the upper connection pendant


420


is in turn connected to a 3-inch diameter, 500-foot long K


4


rig chain


422


extending from the MODU


38


. Those skilled in the are will appreciate the fact that the taut-leg mooring leg


402


is typically not used singly, but rather is employed in conjunction with other, similar taut-leg mooring legs to properly stabilize the MODU at a drilling venue.




Referring now to

FIG. 32

, there is shown a taut-leg mooring leg


432


which may be used in the practice of the invention in lieu of the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described hereinabove in conjunction therewith. The taut-leg mooring leg


432


employs a suction anchor


434


which may be of the type illustrated in

FIGS. 4

,


5


,


6


,


7


, and


8


and described hereinabove in conjunction therewith. Alternatively, the taut-leg mooring leg


432


may employ a vertically loaded anchor which may be either of the type illustrated in

FIG. 34

or of the type illustrated in

FIGS. 35 and 36

and described hereinabove in conjunction therewith.




A 3-inch diameter, 1,500-foot K


4


ground chain


436


is connected to the anchor


434


and extends upwardly therefrom. A 3½-inch diameter, 6,000-foot long IWRC−EIPS+20% catenary wire


438


is connected to the distal end of the chain


436


and extends upwardly therefrom. A 3-inch diameter, 15-foot long K


4


buoy chain pendant


440


is connected between the distal end of the catenary wire


438


and an 82-kip fixed buoyancy submerged buoy


442


. The buoy


442


is identical in construction and function to the buoy


356


illustrated in FIG.


29


and described hereinabove in conjunction therewith.




A 3½-inch diameter, 200-foot long IWRC−EIPS+20% intermediate connection pendant


444


is connected to the upper end of the buoy


442


. A 3-inch diameter, 15-foot long K


4


buoy chain pendant


446


is connected between the distal end of the intermediate connection pendant


444


and a 17-kip adjustable buoyancy submerged buoy


448


. The buoy


448


is identical in construction and function to the buoy


54


illustrated in

FIGS. 9

,


10


, and


11


and described hereinabove in conjunction therewith.




A 3½-inch diameter, 400-foot long IWRC−EIPS+20% upper connection pendant


450


is connected to the upper end of the buoy


448


. The upper connection pendant


450


is in turn connected to a 3-inch diameter, 500-foot long K


4


rig chain


452


extending from the MODU


38


. Those skilled in the art will appreciate the fact that the taut-leg mooring leg


432


is typically not employed singly, but rather is employed in conjunction with other, similar taut-leg mooring legs to properly stabilize the MODU


38


at a drilling venue.




Referring now to

FIG. 33

, there is shown a taut-leg mooring leg


462


which may be utilized in the practice of the invention in lieu of the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described hereinabove in conjunction therewith. The taut-leg mooring leg


462


employs a suction anchor


464


which may be of the type illustrated in

FIGS. 4

,


5


,


6


,


7


, and


8


and described herein in conjunction therewith. Alternatively, the taut-leg mooring leg


462


may employ a vertically loaded anchor, such as the vertically loaded anchor


346


illustrated in

FIG. 34

or the vertically loaded anchor


348


illustrated in

FIGS. 35 and 36

and described hereinabove in conjunction therewith.




A 3½-inch diameter, 4,000-foot long IWRC−EIPS+20% ground wire


466


is connected to the suction anchor


464


and extends upwardly therefrom. A 3-inch diameter, 5-foot long K


4


chain


468


is connected to the distal end of the ground wire


466


and is in turn connected to a 6½-inch diameter, 2,400-foot long catenary segment


470


preferably comprising the polyester rope available from Marlow Ropes of the United Kingdom under the trademark “PolySuper.” A 3-inch diameter, 5-foot long K


4


chain


472


is connected between the “PolySuper” catenary segment


470


and a 6½-inch diameter, 2,440-foot long catenary segment


474


also comprising the “PolySuper” material. A 3-inch diameter, 5-foot long K


4


chain


476


is connected between the “PolySuper” catenary segment


474


and a 6½-inch diameter, 2,400-foot long “PolySuper” catenary segment


478


. A 3½-inch diameter, 5-foot long K


4


chain


480


is connected between the “PolySuper” catenary segment


478


and a 6½-inch diameter, 2,400-foot long “PolySuper” catenary segment


482


. A 3-inch diameter, 20-foot long K


4


chain


484


is connected between the “PolySuper” catenary segment


482


and a 3½-inch diameter, 400-foot long IWRC−EIPS+20% wire for


486


. The wire


486


is in turn connected to a 3-inch diameter, 500-foot long K


4


rig chain


488


which extends from and is connected to the MODU


38


.




Those skilled in the art will appreciate the fact the taut-leg mooring leg


462


differs considerably from the taut-leg mooring leg


42


illustrated in

FIGS. 2 and 3

and described herein in conjunction therewith and from the taut-leg drilling legs


342


,


372


,


402


, and


432


illustrated in

FIGS. 29

,


30


,


31


, and


32


, respectively, and described hereinabove in conjunction therewith. This is because the taut-leg mooring leg


462


comprises segments


470


,


474


,


478


, and


482


all of which are formed from “PolySuper”, which has a submerged negative buoyancy about 13% that of steel rope of the same strength. The use of more buoyant materials in forming the connection between the anchor


464


and the rig chain


488


extending from and connected to the MODU unit eliminates the necessity of employing discrete submerged buoys within the taut-leg mooring leg


462


, for example, the buoys


54


employed in the taut-leg mooring leg


42


of

FIGS. 2 and 3

, the buoys


356


and


358


of the taut-leg drilling leg


352


illustrated in

FIG. 29

, etc. Those skilled in the art will further appreciate the fact that the taut-leg mooring leg


462


is typically not employed singly, but rather is employed in combination with other, similar taut-leg mooring legs in order to properly stabilize the MODU


38


at a drilling venue in the manner illustrated in FIG.


1


and described hereinabove in conjunction therewith.




Although preferred and alternative embodiments of the invention have been illustrated in the accompanying Drawings and described in the foregoing Detailed Description, it will be understood that the invention is not limited to the embodiments disclosed, but is capable of numerous rearrangements and substitutions of parts and elements without departing from the spirit of the invention.



Claims
  • 1. For use in a mooring line extending from the sea floor to the sea surface, a variable buoyancy buoy comprising:a frame having first and second ends; a first buoyancy member mounted on the frame; a second buoyancy member removably mountable on the frame to selectively change the buoyancy of the buoy when being used onsite; means for securing the second buoyancy member on the frame; and means located at the first and second ends of the frame for securing the buoy in the mooring line.
  • 2. The variable buoyancy buoy according to claim 1 further characterized by a plurality of second buoyancy members each removably mountable on the frame to selectively change the buoyancy of the buoy, and the means for securing the second buoyancy members in engagement with the frame.
  • 3. The variable buoyancy buoy according to claim 2 wherein the first buoyancy member and the second buoyancy members are formed from syntactic foam.
  • 4. The variable buoyancy buoy according to claim 3 wherein the frame includes a shaft extending through the first buoyancy member, a fixed plate comprising one end of the frame and secured to the shaft in engagement with the first buoyancy member, and a second plate comprising the opposite end of the frame and selectively engageable with the shaft for securing a selected number of the buoyancy members in engagement therewith.
  • 5. The variable buoyancy buoy according to claim 4 wherein the securing means comprises a fastener extending through the second plate and the shaft for securing the second plate and the variable buoyancy members in engagement with the shaft.
  • 6. A variable buoyancy buoy comprising:a frame having first and second ends; a first plate securably mounted to the first end of the frame; a second plate selectively positionable along the frame between the first and second ends of the frame; a first buoyancy member mounted on the frame adjacent to the first plate; and a second buoyancy member removably mountable on the frame between the first buoyancy member and the second plate, whereby the second plate is selectively positioned along the frame proximate the second buoyancy member when being used in operation to change the buoyancy of the buoy.
  • 7. The variable buoyancy buoy according to claim 6 further comprises a third buoyancy member removably mountable on the frame between the second buoyancy member and the first buoyancy member.
  • 8. The variable buoyancy buoy according to claim 7 further comprises a fourth buoyancy member removably mountable on the frame between the second buoyancy member and the first buoyancy member.
  • 9. The variable buoyancy buoy according to claim 8 further comprises a fifth buoyancy member removably mountable on the frame between the second buoyancy member and the first buoyancy member.
  • 10. The variable buoyancy buoy according to claim 6 wherein the first buoyancy member and the second buoyancy member are formed from syntactic foam.
  • 11. The variable buoyancy buoy according to claim 6 further comprises first and second pad eyes respectively positioned on the first and second ends of the shaft.
  • 12. A variable buoyancy buoy comprising:a frame having first and second ends; a first plate securably mounted to the first end of the frame; a second plate selectively positionable along the frame between the first and second ends of the frame; a first buoyancy member mounted on the frame adjacent to the first plate; and a second buoyancy member removably mountable on the frame between the first buoyancy member ad the second plate, whereby the second plate is positioned along the frame proximate the second buoyancy member, wherein the frame further comprises a shaft including a plurality of spaced apart holes along at least a portion of a length of the shaft that receive a fastener extending through the second plate such that the second plate may be positioned in a plurality of locations along the shaft.
Parent Case Info

This application is a division of pending application No. 08/948,227 filed Oct. 9, 1997, U.S. Pat. No. 6,009,825.

US Referenced Citations (38)
Number Name Date Kind
421686 Fagan et al. Feb 1890
1295008 Corley Feb 1919
1320604 Dame Nov 1919
3295489 Bossa Jan 1967
3411473 Mott et al. Nov 1968
3431879 Westling Mar 1969
3540396 Horton Nov 1970
3602174 Gorman Aug 1971
3703151 Clement Nov 1972
4024718 Roche et al. May 1977
4075862 Ames Feb 1978
4086866 Nixon May 1978
4107933 Lamy Aug 1978
4155673 Yashima May 1979
4164195 Frigeni Aug 1979
4222591 Haley Sep 1980
4257721 Haynes Mar 1981
4318641 Hogervorst Mar 1982
4347012 Glidden Aug 1982
4432671 Westra et al. Feb 1984
4439068 Poklandnik Mar 1984
4572304 Mahar et al. Feb 1986
4575282 Pardue, Sr. et al. Mar 1986
4601608 Ahlstone Jul 1986
4635728 Harrington Jan 1987
4669989 Havlick Jun 1987
4721415 Shatto Jan 1988
4733993 Andréasson Mar 1988
4830541 Shatto May 1989
4940362 Paulshus et al. Jul 1990
5041038 Poldervaart et al. Aug 1991
5097788 Castel Mar 1992
5159891 Lohr et al. Nov 1992
5190107 Langner et al. Mar 1993
5364297 Rohardt Nov 1994
5480521 Snyder, Jr. et al. Jan 1996
5704307 Treu et al. Jan 1998
5893334 Poranski, Sr. Apr 1999
Foreign Referenced Citations (4)
Number Date Country
B-5336379 Nov 1979 AU
0 011 894 Apr 1984 EP
610714 May 1978 SU
797955 Jan 1981 SU
Non-Patent Literature Citations (5)
Entry
Telefax memo from Aker Omega Marine, Inc. to Shell Offshore, Inc. dated May 7, 1991.
Telefax memo from Aker Omega Marine, Inc. to Shell Offshore, Inc. dated Jun. 17, 1991.
Pre-set Moorings Provide Less Costly Alternative to DP in Ultra-Deepwater, Peter G.S. Dove & Thomas M. Fulton, Aker Marine Contractors, Offshore, May 1997 pp 76-80.
Why Mobile Drilling Units Will be Able to Moore in 10,000 ft. Depths, Peter G.S. Dove & Thomas M. Fulton, Aker Marine Contactors, Offshore, Apr. 1997, pp 32-34.
Mooring Descent Deeper, Peter Dove & Thomas Fulton, Aker Marine Contractors, Offshore Engineer, Mar. 1997, pp 47-48.