Claims
- 1. A method of installing a subsurface tubing hanger in a well, including the steps of:
- connecting the subsurface tubing hanger in the string of well tubing;
- connecting a predetermined amount of well tubing above the subsurface tubing hanger;
- setting the subsurface tubing hanger at the subsurface location for supporting the string of well tubing below the subsurface tubing hanger by increasing a controlled pressure in the bore of the well tubing communicated to the pressure setting mechanism of the subsurface tubing hanger;
- isolating the pressure setting mechanism of the subsurface tubing hanger from the pressure in the bore of the well tubing; and
- retrieving the plug catcher and plug from the subsurface tubing hanger through the bore of the well tubing.
- 2. A method of installing a subsurface tubing hanger in a well, including the steps of:
- connecting the subsurface tubing hanger in the string of well tubing;
- connecting a predetermined amount of well tubing above the subsurface tubing hanger;
- setting the subsurface tubing hanger at the subsurface location for supporting the string of well tubing below the subsurface tubing hanger by increasing a controlled pressure in the bore of the well tubing communicated to the pressure setting mechanism of the subsurface tubing hanger;
- isolating the pressure setting mechanism of the subsurface tubing hanger from the pressure in the bore of the well tubing;
- moving a tubing stringer relative to the set subsurface tubing hanger to block communication from the bore of the well tubing through a flow path to the pressure setting mechanism of the subsurface tubing hanger; and
- moving the wellhead hanger into the wellhead.
- 3. A method of installing a subsurface tubing hanger in a well, including the steps of:
- connecting the subsurface tubing hanger in the string of well tubing;
- connecting a predetermined amount of well tubing above the subsurface tubing hanger;
- setting the subsurface tubing hanger at the subsurface location for supporting the string of well tubing below the subsurface tubing hanger by increasing a controlled pressure in the bore of the well tubing communicated to the pressure setting mechanism of the subsurface tubing hanger;
- isolating the pressure setting mechanism of the subsurface tubing hanger from the pressure in the bore of the well tubing;
- connecting a safety joint having a strength equal to the well tubing in the preselected amount of well tubing above the subsurface tubing hanger prior to the step of connecting the wellhead hanger; and
- actuating the safety joint to separate at a strength less than the strength of the well tubing after the step of setting the subsurface tubing hanger to insure parting of the well tubing at the safety joint in the event the wellhead is damaged.
- 4. A method of operably installing a safety joint in a well tubing to insure separation of the well tubing at the safety joint while providing for the safety joint to have substantially the strength of the well tubing during installation of a subsurface tubing hanger, including the steps of:
- connecting the safety joint in a well tubing above the subsurface tubing hanger with the safety joint having a strength against pull apart substantially equal to the strength of the well tubing;
- actuating the safety joint after setting the subsurface tubing hanger to reduce the strength against pull apart to substantially less than the strength of the well tubing to assure pull apart of the well tubing at the safety joint.
- 5. The method as set forth in claim 4, wherein the step of actuating includes the step of:
- setting a tubing holddown means by a relative longitudinal movement; and
- releasing a latch means in the safety joint in response to the relative longitudinal movement to activate the safety joint.
- 6. The method as set forth in claim 5, wherein the step of actuating further includes:
- communicating a fluid pressure signal to the tubing holddown means independently of the bore of the well tubing for setting the tubing holddown means.
- 7. The method as set forth in claim 4, wherein the step of actuating includes the step of:
- releasing a load carrying latch means in the safety joint to reduce the safety joint strength against pull apart.
- 8. A method of operably installing a full opening subsurface safety valve in a well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening subsurface safety valve in the well tubing above the tubing hanger;
- connecting a predetermined amount of well tubing above the subsurface safety valve;
- setting the subsurface tubing hanger at the subsurface location for supporting the string of well tubing below the subsurface tubing hanger by increasing the pressure in the bore of the well tubing;
- isolating the pressure mechanism of the subsurface tubing hanger from the pressure in the bore of the well tubing;
- operating from externally of the well the full opening subsurface safety valve to control the flow through the bore of the well tubing;
- releasing the predetermined amount of well tubing and full opening safety valve from the subsurface tubing hanger when desired; and
- removing the predetermined amount of well tubing and full opening safety valve from the well.
- 9. The method of claim 8, further including the steps of:
- installing a replacement full opening subsurface safety valve and the predetermined amount of well tubing into the well; and
- engaging the subsurface tubing hanger for effecting a seal to direct flow of well fluids through the replacement full opening subsurface safety valve.
- 10. The method as set forth in claim 9, including the step of:
- operating from externally of the well replacement full opening subsurface safety valve to control the flow through the bore of the well tubing.
- 11. A method of operably installing a well safety system having a full opening remote controlled subsurface safety valve in the well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening remote controlled subsurface safety valve in the well tubing above the subsurface tubing hanger;
- setting the subsurface tubing hanger in the well for supporting the string of well tubing below the subsurface tubing hanger by increasing a controlled setting pressure in the bore of the well tubing communicated to the setting mechanism of the subsurface tubing hanger; and
- isolating the setting mechanism from the pressure in the bore of the well tubing.
- 12. The method as set forth in claim 11, including the step of:
- operating the full opening subsurface safety valve to control the flow through the bore of the well tubing in response to a remote control signal communicated to the valve independently of the well tubing.
- 13. The method as set forth in claim 11, including the step of:
- disconnecting from the set subsurface tubing hanger to enable retrieval of the full opening subsurface safety valve from the well without disturbing the well tubing supported by the subsurface tubing hanger.
- 14. A method of operably installing a well safety system having a full opening remote controlled subsurface safety valve in the well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening remote controlled subsurface safety valve in the well tubing above the subsurface tubing hanger;
- connecting a full-strength safety joint in the well tubing above the full opening remote controlled subsurface safety valve;
- setting the subsurface tubing hanger in the well for supporting the string of well tubing below the subsurface tubing hanger;
- activating the safety joint to reduce the strength of the safety joint in response to a controlled fluid pressure; and
- communicating an increased fluid pressure to the safety joint independently of the well tubing for activating the safety joint.
- 15. A method of operably installing a well safety system having a full opening remote controlled subsurface safety valve in the well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening remote controlled subsurface safety valve in the well tubing above the subsurface tubing hanger;
- connecting a tubing holddown in the well tubing above the full opening remote controlled subsurface safety valve;
- setting the subsurface tubing hanger in the well for supporting the string of well tubing below the subsurface tubing hanger; and
- setting the holddown to secure the well tubing above the set subsurface tubing hanger in the well in response to a controlled fluid pressure.
- 16. The method as set forth in claim 15, including the step of:
- communicating an increased fluid pressure to the holddown independently of the well tubing for setting the holddown.
- 17. The method as set forth in claim 15, including the step of:
- expanding a plurality of slips radially outwardly into engagement with the well casing for setting the holddown.
- 18. A method of operably installing in a single trip a well safety system having a full opening remote controlled subsurface safety valve disposed above a subsurface tubing hanger in the well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening remote controlled subsurface safety valve in the well tubing above the subsurface tubing hanger;
- connecting a holddown above the full opening remote controlled subsurface safety valve for receiving the portion of the well tubing above the subsurface safety valve in the well when set;
- mounting a full-strength safety joint in the well tubing above the full opening remote controlled subsurface safety valve for supporting the well tubing during the single trip;
- setting the subsurface tubing hanger in the well for supporting the string of well tubing below the subsurface tubing hanger; and
- activating the safety joint to reduce the strength of the safety joint in response to a controlled fluid pressure while setting the holddown for securing the well tubing in the well to insure separation of the well tubing at the safety joint in the event of damage to the wellhead.
- 19. A method of operably installing in a single trip a well safety system having a full opening remote controlled subsurface safety valve disposed above a subsurface tubing hanger in the well, including the steps of:
- connecting a subsurface tubing hanger in a string of well tubing;
- connecting the full opening remote controlled subsurface safety valve in the well tubing above the subsurface tubing hanger;
- connecting a holddown above the full opening remote controlled subsurface safety valve for securing the portion of the well tubing above the subsurface safety valve when set;
- mounting a full-strength safety joint in the well tubing above the full opening remote controlled subsurface safety valve;
- setting the subsurface tubing hanger in the well for supporting the string of well tubing below the subsurface tubing hanger;
- setting the holddown for securing the portion of the well tubing above the subsurface safety valve in the well; and
- activating the safety joint to reduce the strength of the safety joint to insure separation of the well tubing above the subsurface safety valve in the event of damage to the wellhead.
Parent Case Info
This is a division, of application Ser. No. 2,197, filed Jan. 9, 1979 now U.S. Pat. No. 4,260,021.
US Referenced Citations (3)
Divisions (1)
|
Number |
Date |
Country |
Parent |
2197 |
Jan 1979 |
|