This application claims priority of European Patent Office application No. 11176941.0 EP filed Aug. 9, 2011. All of the applications are incorporated by reference herein in their entirety.
The present disclosure relates to a wind farm, a method for operating a wind farm, a program element, a computer readable medium and a wind farm controller.
Wind farms are becoming more and more popular as an ecological replacement for conventional or nuclear power plants. Up to several hundred individual wind turbines may be pooled in a single wind farm.
Each wind turbine transforms kinetic energy gathered from the wind via its wind turbine blades into rotational energy of its wind turbine rotor which wind turbine rotor then drives a wind turbine generator. Although envisaged not under all constrains a constant speed of the rotor and/or the wind turbine generator may be achievable. Such speed deviations may translate into frequency and/or voltage deviations. However, consumers rely on constant frequency and/or voltage. Hence, wind turbines may comprise converters that convert electrical power produced by the wind turbine generator to electrical power of constant frequency and voltage. Furthermore, wind turbines may comprise a wind turbine transformer to transform the voltage provided by the converter to a higher level and thereby reduce power losses due to lower current and/or keep costs associated to cables low.
The electrical power generated by each wind turbine is then fed into a collector grid, which provides upper grid and thereby consumers with electrical power.
Conventionally, synchronous generators operating at a constant speed, e.g. synchronous generators of fossil fuelled, nuclear, or hydroelectric power stations, are used to support alternating current grids. In case of a grid fault these synchronous generators may provide up to approximately ten times more current than during normal operation, thereby supporting the grid. Collector grids of wind farms fed by wind turbines with converters are limited in supporting the grid at grid fault, because they can only provide approximately nominal current. The reason for this low current is the small thermal time constants in the converters. Accordingly, secure and reliable operation of upper grid and collector grids of wind farms may be compromised and there may be a higher risk of blackout.
Hence, there may be a need for a wind farm, a method for operating a wind a program element, a computer readable medium, and a wind farm controller, which may enhance the current and thereby the apparent power supplied by wind farms under grid faults.
This need may be met by the subject matter according to the independent claims. Different embodiments are described by the dependent claims.
According to a first aspect there is provided a wind farm comprising a collector grid and a wind turbine being connected to the collector grid, wherein the wind turbine comprises a wind turbine transformer, and a wind turbine transformer bypass switch.
This aspect may be based on the idea that up-transforming voltage provided by a wind turbine converter implies down-transforming the associated current. However, wind turbine converters of wind turbines are composed of semi-conductor components generally characterized by small thermal time constants. These wind turbine converters may often provide only limited additional current in case of a grid fault. Accordingly, a wind turbine may provide only little additional active or reactive power to the collector grid. The wind turbine transformer bypass switch may allow for bypassing the transformer in case of a collector grid failure. A sudden voltage drop of the collector grid voltage may be seen, for example, as a collector grid voltage. This may occur at grid faults, such as for example short circuit faults at the upper grid or collector grid. Other grid failures may include frequency shifts. Bypassing the transformer may for a given collector grid voltage provide more current and thereby more apparent power to the upper grid and the collector grid.
According to an exemplary embodiment of the wind farm, the wind farm comprises a converter over voltage protector.
Bypassing the wind turbine transformer via the wind turbine transformer bypass switch may increase the voltage at the wind turbine converter. The voltage may be higher than the voltage in undisturbed operation. Thus, a converter over voltage protector may prevent that the voltage exceeds a rated converter voltage. A converter over voltage protector may be realized in form of a varistor, which limits the voltage. Alternatively, the converter over voltage protector may be realized by other types of limiters.
According to another exemplary embodiment of the wind farm, the wind farm further comprises a wind farm transformer connected to the collector grid and a general power grid, and a wind faun transformer bypass switch.
The collector grid may be connected to a general power grid via a wind farm transformer. The wind farm transformer may up-transform the collector grid voltage to a level acceptable for conventional transmission lines operating at e.g. at 380 kV. Providing such a wind farm with a wind farm transformer bypass switch may help to support general power grids as more current may be fed into the general power grid. This may especially be useful if few conventional synchronous generators are connected to the general power grid.
According to a second aspect there is provided a method for operating a wind farm wherein the method comprises measuring a collector grid voltage, and bypassing a wind turbine transformer if the measured collector grid voltage is below a first predetermined threshold voltage.
At collector grid faults the collector grid voltage may drop below a first predetermined threshold voltage. The first predetermined threshold voltage may be lower than the rated converter voltage. It may therefore be possible to bypass the wind turbine transformer and let the converter operate at the collector grid voltage and thereby supply more active and reactive power to the collector grid, i.e. to support the collector grid.
According to a first embodiment of the method for operating a wind farm the method further comprises interrupting the bypassing of the wind turbine transformer if the collector grid voltage is above a second predetermined threshold voltage.
When the collector grid recovers from the grid fault the collector grid voltage may exceed the rated converter voltage. Interrupting the bypassing of the wind turbine transformer when the collector grid voltage is above a second predetermined threshold voltage may then protect the converter against over voltage.
According to a second embodiment of the method for operating a wind faint, the method further comprises selecting the first predetermined threshold voltage to be equal to or selecting the first predetermined threshold voltage to be different from the second predetermined threshold voltage.
Selecting the first predetermined threshold voltage to be equal to the second predetermined threshold voltage may reduce the number of control parameters and the operating complexity.
If the first predetermined threshold voltage and the second predetermined threshold voltage are selected to be different from each other the risk of oscillations from a bypassing state to a non-bypassing state may be reduced.
According to another embodiment of the method for operating a wind farm the method further comprises very fast, in particular instant interrupting of bypassing the wind turbine transformer and thereby minimizing the over voltage at the wind turbine converters.
According to a further embodiment of the method for operating a wind farm the method further comprises delaying the bypassing of the wind turbine transformer. In other words, a delay time for switching from a non-bypassing state to a new bypassing state may be included to reduce voltage fluctuations.
According to a further embodiment of the method for operating a wind farm, the method further comprises measuring a general power grid voltage, and bypassing a wind farm transformer if the general power grid voltage is below a third predetermined threshold voltage.
It may be advantageous to collect the electrical power produced by the individual wind turbines at a collector grid voltage below the general power grid voltage normally used for transmission lines. Accordingly, a wind farm transformer may be provided to transform the collector grid voltage to a general grid voltage. Bypassing the wind farm transformer when the general power grid voltage is below a third predetermined threshold voltage may support the general power grid in the same way as has been described above for a collector grid, when providing the collector grid with a wind turbine transformer bypass switch.
According to a still further embodiment of the method for operating a wind farm, the method further comprises interrupting the bypassing of the wind farm transformer if the general power grid voltage is above a forth predetermined threshold voltage.
When the general power grid recovers from the grid fault the general power grid voltage may exceed the rated collector grid voltage. It may, for example, be difficult to ensure a sufficient insulation level of the wind turbine in these circumstances.
Interrupting the bypassing of the wind farm transformer when the general power grid voltage is above a forth predetermined threshold voltage may thus ensure safe operation of the wind turbine.
According to another embodiment of the method for operating a wind farm the method further comprises selecting the third predetermined threshold voltage to be equal to or different from the forth predetermined threshold voltage.
Selecting the third predetermined threshold voltage to be equal to the forth predetermined threshold voltage may reduce the number of control parameters and the operating complexity.
If the third predetermined threshold voltage and the forth predetermined threshold voltage are selected to be different from each other the risk of oscillations from a bypassing state to a non-bypassing state may be reduced.
According to yet another embodiment of the method for operating a wind farm, the method further comprises a very fast, in particular instant interrupting of bypassing the wind farm transformer.
According to a third aspect there is provided a program element for operating a wind farm, the program element, when being executed by a data processor is adapted for controlling and/or for carrying out the method as set forth hereinbefore,
The program element may be implemented as computer readable instruction code in any suitable programming language, such as, for example, JAVA, C++, and may be stored on a computer-readable medium (removable disk, volatile or non-volatile memory, embedded memory/processor, etc.). The instruction code is operable to program a computer or any other programmable device to carry out the intended functions. The program element may be available from a network, such as the World Wide Web, from which it may be downloaded.
According to a forth aspect there is provided a computer-readable medium on which there is stored a computer program for processing a physical object, the computer program, when being executed by a data processor, is adapted for controlling and/or for carrying out the method as set forth above.
The computer-readable medium may be readable by a computer or a processor. The computer-readable medium may be, for example but not limited to, an electric, magnetic, optical, infrared or semiconductor system, device or transmission medium. The computer-readable medium may include at least one of the following media: a computer-distributable medium, a program storage medium, a record medium, a computer-readable memory, a random access memory, an erasable programmable read-only memory, a computer-readable software distribution package, a computer-readable signal, a computer-readable telecommunications signal, computer-readable printed matter, and a computer-readable compressed software package.
According to a fifth aspect there is provided a wind farm controller, the wind farm controller being adapted for controlling a wind farm as set forth hereinbefore with a method as set forth hereinbefore.
It has to be noted that embodiments have been described with reference to different subject matters. In particular, some embodiments have been described with reference to method type claims whereas other embodiments have been described with reference to apparatus type claims. However, a person skilled in the art will gather from the above and the following description that, unless other notified, in addition to any combination of features belonging to one type of subject matter also any combination between features relating to different subject matters, in particular between features of the method type claims and features of the apparatus type claims is considered as to be disclosed with this document.
The aspects defined above and further aspects of the present invention are apparent from the examples of embodiment to be described hereinafter and are explained with reference to the examples of embodiment. The invention will be described in more detail hereinafter with reference to examples of embodiment but to which the invention is not limited.
The illustration in the drawing is schematically.
The voltage of the converted electrical power is typically transformed to a higher voltage by wind turbine transformers 115, 116, 117, 118. Up-transforming the voltage may reduce power losses caused by cable resistances. The converted and transformed electrical power of each wind turbine 102, 103, 104, 105 is then fed into a collector grid 105. However, each wind turbine 102, 103, 104, 105 is furthermore provided with a wind turbine transformer bypass switch 119, 120, 121, 122, which allows bypassing the corresponding wind turbine transformer 115, 116, 117, 118. This may allow supporting the collector grid 106 and/or the upper grid 101 in case of collector grid faults and/or upper grid faults.
The electrical power provided by the collector grid 106 is typically transformed by a wind farm transformer 123 to an even higher voltage level suitable for the transmission lines of an upper grid 101. A wind farm transformer bypass switch 124 is associated to the wind farm transformer 123 and may allow supporting the upper grid 101 with additional current and/or additional apparent power, in particular reactive power, in case of upper grid failures by bypassing the wind farm transformer 123.
As apparent from
While specific embodiments have been described in detail, those with ordinary skill in the art will appreciate that various modifications and alternative to those details could be developed in light of the overall teachings of the disclosure. For example, elements described in association with different embodiments may be combined. Accordingly, the particular arrangements disclosed are meant to be illustrative only and should not be construed as limiting the scope of the claims or disclosure, which are to be given the full breadth of the appended claims, and any and all equivalents thereof.
It should be noted that the term “comprising” does not exclude other elements or steps and the use of articles “a” or “an” does not exclude a plurality. Also elements described in association with different embodiments may be combined. It should also be noted that reference signs in the claims should not be construed as limiting the scope of the claims.
Number | Date | Country | Kind |
---|---|---|---|
EP11176941 | Aug 2011 | EP | regional |