The object of the invention is a wind turbine assembling method, said wind turbine comprising a tower, a nacelle and a rotor which, by using suitable means, achieves an increase in the speed of the assembling of a wind turbine and thus in that of a wind farm consisting of several wind turbines. Another object of the present invention is the wind turbine assembled according to the above method.
The wind turbines comprise a tower, a nacelle which houses the electrical generator and a rotor formed in turn by at least two blades. The tower of the wind turbine supports the nacelle and the rotor. Large wind turbines have steel, lattice, or reinforced concrete towers or even mixed-type towers, the latter comprising sections of different materials, for example, a lower section of concrete and an upper section of steel or lattice.
The larger the diameter of the rotor, the higher the rated power of the wind turbines which in turn involves the use of higher towers. The increase in tower height may necessarily require that the tower be divided into several annular sections which are stacked during the wind turbine assembly stage thus forming the full height of the tower. Dividing the tower into sections has the advantage that each section has a size such that its transport by road or rail is easier.
One of the most commonly used materials for large towers is concrete, since it involves acceptable production costs compared to those for the production of steel towers of similar characteristics. However, the weight of each concrete tower section can easily exceed one hundred tons, this fact being infrequent for metal tower sections, so stacking the concrete sections requires heavy-tonnage lifting and positioning means. The cost of using such lifting and positioning means, which may be for example a crane, is directly related to the tonnage that it is capable of handling and the time of use thereof. This high-tonnage crane is also used for lifting and positioning the nacelle, as the weight of the nacelle may also exceed 100 tons.
The design of wind turbine components and the design of the connections between them once placed, should take into account the loads they will be subjected to throughout their useful life to ensure the proper functioning thereof. In particular, the connections between different sections comprising concrete are adapted to withstand the loads induced by the rotor, these being the loads resulting from the wind falling on the surface of the rotor and the rotor weight loads.
It is known in the prior art that the procedure for assembling a wind turbine comprises the following stages:
This method for the assembly of wind turbines has the disadvantage that the use of the crane involves a lot of time since the connecting of sections takes a long time, i.e. the hardening of the binding material takes time, and meanwhile the crane is inactive.
The method object of the invention is implemented in a wind turbine comprising a tower, a nacelle and a rotor. The tower is of the type comprising stackable annular sections, at least two of these annular sections being made of concrete. The assembly procedure is of the type comprising the following steps:
The method object of the invention is characterized in that the main connection of the concrete annular sections between each other by main connecting means is performed after stacking the nacelle onto the upper annular section.
Therefore, unlike the method known in the prior art, there is a first phase in which the stacking of all the annular sections and the nacelle is performed and subsequently the main connections between the annular sections made of concrete are carried out. Thus, the technical effect of increasing the speed of assembling a wind turbine is achieved, which results in reducing the time of use and therefore the cost of using a crane during the assembly of the wind turbine, since during the latter phase of performing the main connections the use of a high-tonnage crane is not required.
Before assembling the wind rotor on the tower and nacelle assembly, the main connections are carried out, since once the wind rotor is placed the wind turbine is subjected to loads induced by the rotor, i.e. as a result of wind falling on the surface of the rotor and due to the weight of the rotor itself. The wind turbine design stage comprises a phase involving the calculation of both extreme and fatigue dimensioning loads, to verify the proper sizing of each of the components and their respective connections. Such dimensioning loads are laid down in regulations and always include the complete wind turbine, including the rotor, because once the rotor is placed, the loads can be major although the turbine is not yet connected to the grid. Without the implementation of these main connections the wind turbine could be irreversibly damaged when the rotor is placed. Once the main connections have been carried out, a low-tonnage crane places the rotor on the nacelle.
Therefore, main connection refers to that carried out to withstand the loads of the wind turbine induced by the rotor, both due to the impact of wind and due to the rotor's own weight. Examples of main connections may include the following among others:
The proposed assembly procedure can be applied both to concrete towers and mixed-type towers. Mixed-type towers comprise at least one concrete part, usually at the lower part, and an upper metal or lattice part.
Another object of this invention is a wind turbine comprising a tower, a nacelle and a rotor, said tower comprising stacked annular sections having at least two of them made of concrete, and main connecting means for connecting the sections to each other and for connecting the upper section to the nacelle, said main connection means being adapted to withstand loads induced by the wind turbine rotor. The wind turbine is characterized in that it further comprises auxiliary connecting means for connecting the annular sections made of concrete to each other, said auxiliary connecting means being adapted to withstand assembly loads and loads induced by wind on the wind turbine in absence of the rotor, but not loads induced by the rotor.
Another object of this invention is the assembly method for the assembling of a plurality of wind turbines in a wind farm, wherein each wind turbine comprises stackable annular sections of which at least two annular sections are made of concrete. For each wind turbine the method comprises performance of the following:
To complement the description being made and for the sake of a better understanding of the characteristics of the invention according to a preferred practical embodiment thereof, attached as an integral part of said description are a set of drawings wherein, for the purpose of illustration and not limiting the scope of the invention, the following is shown:
In performing a main connection for connecting the annular sections (3, 4, 5, 6) made of concrete to each other, it is common to use mortar or grout (10), which is injected both into an horizontal joint between the surfaces of two adjacent annular sections (3, 4, 5, 6) and in the space between the bars (8) and housings (9). This ensures that the bars (8) withstand bending stress once the rotor has been placed on the nacelle (2) in the case of lateral loads caused by the pushing effect of wind on the rotor, both when the wind turbine is in operation or when stopped for overhaul work prior to connecting the turbine to the mains or for maintenance work. The total time required for carrying out said main connections is that required to perform the mortar or grout (10) injection, plus the time required for the mortar or grout (10) to harden in each of the main connections. Therefore, the total execution time of main connections amounts to over 24 hours in general, often being over 48 or even 72 hours.
Typically the centre of gravity of the nacelle (2) is offset from the axis of the tower (1). The offset frequently involves advancement of the nacelle in the direction of the hub with respect to the axis of the tower (1) due to the presence of very heavy components in the front part of the nacelle (2) in relation to the rear part, such as the hub itself, an low-speed shaft or bearings.
To withstand the offset of the centre of gravity of the nacelle (2) and the presence of lateral loads due to the effect of wind on the surface of the tower (1) and the nacelle (2) during the assembling stage, the procedure comprises a stage for the stabilizing of each of the annular sections (3, 4, 5, 6) made of concrete, for example of the second annular section (4) on the first annular section (3), before placing the nacelle (2). This stabilization step is performed using auxiliary connection means adapted to withstand assembly loads and loads induced by the wind on the wind turbine in absence of the rotor, but not loads induced by the rotor.
These auxiliary connections must be capable of transmitting the abovementioned loads to the base of the tower (1), withstanding not only compression stress but also bending, tensile and shear stress and enabling loads to be withstood during the assembly and loads induced by the wind by the pushing effect on the tower and the nacelle and the offset centre of gravity of the nacelle with respect to the axis of the tower.
The method for performing the auxiliary connections between annular sections (3, 4, 5, 6) of the tower (1) when the sections are made of concrete is far less costly time-wise than the performance of the main connections between said annular sections (3, 4, 5, 6) since such connections withstand a lower load. Thus, the operating time of the high-tonnage crane can be reduced.
The stabilization of annular sections (3, 4, 5, 6) of the tower (1) when the sections are not made of concrete or the stabilization of the nacelle (2) can be performed using the very same main connection means, e.g. threaded connections, but having a smaller torque than that specified for the wind turbine having a rotor in place. Alternatively, auxiliary means may also be used for the stabilizing of such elements, provided it saves time in the completion of the first assembly stage of the wind turbine.
Once these components have been joined using main or auxiliary connections, as appropriate, the tower (1) and nacelle (2) assembly withstands for at least several weeks the loads associated with the wind and the nacelle (2) weight runout with respect the axis of the tower (1).
Once the rotor has been placed, the assembly will withstand loads induced by said rotor due to the wind load on the surface of the blades and the rotor's own weight. Therefore, the rotor is placed after performing all main connections of annular sections (3, 4, 5, 6) to each other and main connections of the tower (1) and the nacelle (2) to the hub.
The intermediate phase of stabilization using auxiliary connecting means prior to placement of the nacelle has different embodiments that are described hereunder:
Auxiliary connections having resin (11) allow the tower (1) and nacelle (2) assembly to withstand during a period of several weeks loads associated to the wind and to the offset weight of the nacelle (2) with respect to tower (1) axis.
The number of connections between bar (8)—housing (9) assemblies in which these resins are used (11) for the implementation of auxiliary connections is less than the total number of bar (8)—housing (9) assemblies of each annular section (3, 4, 5, 6) made of concrete. In a preferred embodiment, see
The combination of a number of auxiliary connections being less than the main connections, together with a shorter execution and curing time of said auxiliary connections enables the entire process to be performed continuously with a single crane (7) and thus reduce the operating time of the high-tonnage crane (7) for the assembly of the wind turbine. Said crane (7) can be used from that time to assemble another wind turbine in the wind farm.
For this purpose the annular sections (3, 4, 5, 6) made of concrete comprise a recess (12) open towards the interior of the section (3, 4, 5, 6) and located at the lower part of some of the housings (9) so that the stage of stabilization comprises access to the bars (8) of an upper annular section (3, 4, 5, 6) through the recesses (12) of the lower annular section (3, 4, 5, 6) and the tightening of a retaining element (13) on the bar (8).
For this, the annular sections (3, 4, 5, 6) made of concrete comprise some first lugs (14) adjacent to the upper base and some second lugs (15) joined to the first lugs (14) and adjacent to the lower base, so that the stage of stabilization comprises interposing connecting dowel rods (16) for connecting some first lugs (14) and some second lugs (15) and the blocking of said connecting dowel rods (16).
Said lugs (14, 15) can be positioned and fixed to the walls of the annular sections (3, 4, 5, 6) in a factory at the time of manufacture thereof, or alternatively performed on site when assembling the wind turbine. Preferably, and for each connection, one of the lugs (14) is factory-fixed to one of the sections (3) and another is fixed to the adjacent section (4) when assembling the tower (1), allowing adjustment of the position to ensure contact of the planes of the lugs (14, 15). Thus the problems of tolerances in components of large dimensions are overcome.
In the same manner as in the first embodiment of the stage of stabilization, the second example and the third example require a small number of auxiliary connections which are uniformly distributed along the perimeter of the circle in which they are inscribed, so the assembly loads are transmitted evenly from one annular section (3, 4, 5, 6) made of concrete to another annular section (3, 4, 5, 6) made of concrete.
Where the hanging platform (17) is suspended from the nacelle (2), and since the nacelle (2) is normally attached to the tower (1) via a bearing and a yaw mechanism, said yaw mechanism can be actuated in order to access the joints between annular sections (3, 4, 5, 6) along the entire perimeter of the annular sections for the execution of the main connections.
The annular sections (3, 4, 5, 6) may be formed from the connection of different segments or prefabricated voussoirs, i.e., the sections may be vertically divided into several segments which are assembled one beside another on an assembly platform located in the wind farm.
The auxiliary connection means comprises tensioning cables (18) having an upper end (19) and a lower end (20). The upper end (19) is connected to the tower (1), preferably to the upper annular section (6) of the part of the tower (1) made of concrete. The lower end (20) is connected in such a way that the tensioning cables (18) are tensioned in such way so as to provoke compression stress on the tower (1). If all the annular sections (3, 4, 5, 6), are made of concrete, the whole tower (1) is subject to compression stress. If, otherwise, only some of the annular sections (3, 4, 5, 6) are made of concrete, the tensioning cables (18) are tensioned in such a way so as to provoke compression stress on the part of the tower (1) made of concrete.
For example, the lower end (20) may be directly connected to the tower (1) at a lower position than that of the upper end (19). In a more particular way, the lower end (20) may be fixed to a foundation (21) upon which the tower (1) rests, as shown in
At least some of the tensioning cables (18) are mounted before the nacelle, whilst some of said tensioning cables may be mounted after the nacelle.
Additionally, a first tension of the tensioning cables (18) before mounting the nacelle may be different from a second tension of the tensioning cables (18) after having mounted the nacelle.
In a preferred embodiment, the first tension applied to the tensioning cables (18) is substantially lower than the second tension finally applied to the tensioning cables (18) to withstand the loads induced by the rotor.
In a preferred embodiment, the number of tensioning cables (18) for the implementation of auxiliary connections before the mounting of the nacelle is less than the total number of tensioning cables (18) used for the final assembly of the wind turbine, after having mounted the nacelle. In a more preferred embodiment, the number of tensioning cables (18) in the stabilization phase is at least three and they are tensioned at a tension that is less than the 50% of the tension finally applied to the cables to withstand the loads induced by the rotor.
In an embodiment, the tensioning cables (18) used as auxiliary connections are uniformly distributed along the perimeter of a circle in which they are inscribed, thus the assembly loads are transmitted evenly from one annular section (3, 4, 5, 6) to another (3, 4, 5, 6) both made of concrete.
In a preferred embodiment, the tensioning cables (18) run along the tower (1) between the tower foundation and the upper base of the upper section (6) of the tower, which is made of concrete.
In a preferred embodiment, the maximum wind speed that the wind turbine can withstand during the assembly phase, when the rotor is not mounted yet, without main nor auxiliary connections is calculated. Then the auxiliary connections described above are only performed if the weather forecast foresees the possibility of overcoming this maximum wind speed.
Number | Date | Country | Kind |
---|---|---|---|
201131110 | Jun 2011 | ES | national |
Number | Name | Date | Kind |
---|---|---|---|
1206484 | Swan | Nov 1916 | A |
20080040983 | Fernandez Gomez | Feb 2008 | A1 |
20090000227 | Jakubowski | Jan 2009 | A1 |
20100290918 | Pedersen | Nov 2010 | A1 |
20120047840 | Gregor | Mar 2012 | A1 |
20140044554 | Lafferty | Feb 2014 | A1 |
20140175038 | Arlaban Gabeiras | Jun 2014 | A1 |
Number | Date | Country |
---|---|---|
19936603 | Feb 2001 | DE |
1889988 | Feb 2008 | EP |
WO 2010049313 | May 2010 | WO |
Number | Date | Country | |
---|---|---|---|
20130001954 A1 | Jan 2013 | US |