The present invention relates to a wind turbine blade installation system and related methods of wind turbine blade installation.
Wind turbine blade installation typically involves the lifting up of wind turbine blades to a rotor hub or head of a nacelle on top of a tower of a wind turbine. Given the height of most wind turbines (around or above 100 meters) this can be dangerous and thus time-consuming and costly process.
Known methods may utilise a plurality of high-reaching cranes supported at ground level and connecting to various parts of the blade to iteratively lift the blade further and further up until it reaches the nacelle of the wind turbine. This can be a peculiar process in the typically high-wind conditions of wind turbine installation farms/field, where strong winds can cause dangerous swaying of the crane cables and thus blade itself. Further, swaying can sometimes reach resonance, resulting in very high frequency and amplitude movement of the crane cables/blade. This is both dangerous and can often make final alignment of the blade with the rotor hub or head of a nacelle very difficult. Cranes mounted to the towers themselves may also require complex and time-consuming assembly and disassembly processes, further increasing cost and construction time.
Other methods may utilise air-vehicles, such as helicopters, to airlift the blades directly up to the nacelle. This can however be very expensive given the required tonnage of the helicopter(s) required to lift the blades and resulting fuel consumption. Further, high-wind conditions can often deem flight un-safe, thereby stalling if not completely preventing airlifting as an option.
Therefore, there is a need to provide a wind turbine blade installation system, and corresponding method, that at least partly circumnavigates the above-mentioned problems of known methods and systems.
In this specification, where reference has been made to external sources of information, including patent specifications and other documents, this is generally for the purpose of providing a context for discussing the features of the present invention. Unless stated otherwise, reference to such sources of information is not to be construed, in any jurisdiction, as an admission that such sources of information are prior art or form part of the common general knowledge in the art.
For the purpose of this specification, where method steps are described in sequence, the sequence does not necessarily mean that the steps are to be chronologically ordered in that sequence, unless there is no other logical manner of interpreting the sequence.
It is an object of the present invention to provide a wind turbine blade installation system and/or method which overcomes or at least partially ameliorates some of the abovementioned disadvantages or which at least provides the public with a useful choice.
In a first aspect the present invention may be said to be a method for installing a wind turbine blade to a rotor head of a nacelle located on top of a tower of a wind power generator, the method comprising:
Preferably the at least one carriage is an upper carriage secured to the blade during hoisting at or proximate the blade root.
Preferably said hoisting is by a support cable or rope releasably attached to the blade and/or the at least one carriage (preferably the upper carriage).
Preferably the method further comprises, prior to said hoisting, attaching a support cable or rope to (preferably an anchor such as a hoist anchor of) the blade and/or at least one carriage.
Preferably the method comprises, prior to said hoisting, attaching a support cable or rope to the blade and/or at least one carriage when the blade, with said at least one carriage secured to it, is in a substantially horizontal condition supported by ground adjacent the tower.
Preferably the blade, prior to said hoisting, is supported by the ground on a support vehicle or support rack.
Preferably the blade is transitioned from its horizontal condition to its vertical tower guided hoisting condition by a crane.
Preferably the blade is transitioned from its horizontal condition to its vertical tower guided hoisting condition by a crane that can lift the blade.
Preferably the blade is transitioned from its horizontal condition to its vertical tower guided hoisting condition by a crane that can lift the blade at a location spaced from the hoist anchor.
Preferably the location spaced apart, is defined by a lifting anchor of the blade.
Preferably the lifting anchor is located more proximate the blade tip than then where the hoisting of the blade occurs.
Preferably the at least one carriage is an upper carriage secured to the blade during hoisting at or proximate the blade root and wherein the location spaced apart is defined by a second of said at least one carriage, secured to the blade more proximate the blade tip.
Preferably the crane comprises a lifting boom and a lifting cable or rope that extends from the lifting boom to the blade to lift the blade.
Preferably the crane is vehicle mounted.
Preferably, in the horizontal condition, the blade and the at least one carriage are separated from the tower.
Preferably the crane and the support cable in concert suspend and move the blade from its horizontal condition to its hoisting condition.
Preferably the crane and the support cable in concert suspend and move the blade from its horizontal condition to its hoisting condition by bringing the at least one carriage in contact with an outer surface or surfaces of the tower.
Preferably the crane is disconnected from the blade once the blade is vertical and the at least one carriage is located against the tower.
Preferably the crane is disconnected from the blade once the blade is fully suspended only by the hoisting cable or rope.
Preferably in the hoisting condition, at least two and preferably 3 carriages are releasably secured to the blade at spaced apart locations, are guided by the tower located intermediate the blade and the tower.
Preferably in the hoisting condition, and upper carriage is releasably secured to the blade at or proximate the blade root, a lower carriage is releasable secured to the blade proximate the blade tip and independent from the upper carriage.
Preferably the at least one carriage comprises of wheels or bearings able to move on and over the surface of surfaces of the tower during said hoisting.
Preferably the wheels or bearings help prevent the blade, during hoisting from swinging relative to the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined distance from the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined radial position from the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined tangential position from the tower.
Preferably the positioning of the blade is achieved by said at least one carriage.
Preferably said at least one carriage (preferably at least said upper carriage) comprises a mechanism that allows the relative position of the blade and the tower to be adjusted.
Preferably said mechanism is an at least two axis translation mechanism.
Preferably said mechanism is an at least two axis translation mechanism able to displace the blade radially and tangentially relative to the tower at said carriage.
Preferably the mechanism is able to cause the moving of the blade to insert the root bolts into the bolt apertures.
Preferably the at least one carriage is in sliding or rolling contact with the tower during hoisting of the blade.
Preferably the hoisting occurs from a hoist point above the blade.
Preferably the hoist point is fixed relative to the tower.
Preferably the hoist point is located such that there is a gravitational bias on the blade and its secured carriage(s) during hoisting towards the tower surface of surfaces.
Preferably a winch to hoist the blade is supported by the ground on which the tower is supported.
Preferably a winch to hoist the blade is secured by the ground on which the tower is supported.
Preferably a winch to hoist the blade is secured to and on the ground on which the tower is supported.
Preferably the support cable or rope during hoisting extends from the blade or said at least one carriage upwardly to a hoist point.
Preferably the support cable or rope during hoisting extends from the blade or said at least one carriage upwardly to a hoist point and from the hoist point toward the ground to a hoist winch.
Preferably after securing the blade the at least one carriage is removed from the blade.
Preferably after securing the blade the at least one carriage is removed from the blade and lowered to the ground.
Preferably after securing the blade the at least one carriage is removed from the blade and lowered to the ground by the support cable.
Preferably the blade is delivered from a remote location to the wind power generator by a support vehicle preferably being a road vehicle (e.g. by a truck, e.g. on the trailer of the truck).
Preferably the blade is delivered from a remote location to the wind power generator by a support vehicle and the crane is mounted to said vehicle.
In a further aspect the present invention may be said to be a method for removing a wind turbine blade from a rotor head of a nacelle located on top of a tower of a wind power generator, the method comprising:
Preferably the at least one carriage is secured to the blade before said lowering.
Preferably the at least one carriage is an upper carriage secured to the blade during lowering at or proximate the blade root.
Preferably wherein said lowering is by a support cable or rope releasably attached to the blade and/or the at least one carriage (preferably the upper carriage).
Preferably the method further comprises, prior to said lowering (and preferably prior to said un-securing), attaching a support cable or rope to (preferably a hoist anchor of) the blade and/or at least one carriage.
Preferably the blade is lowered onto a support vehicle or support rack.
Preferably the blade is transitioned from vertical tower guided hoisting condition to its horizontal condition to by a crane.
Preferably the blade is transitioned from vertical tower guided hoisting condition to its horizontal condition to by a crane that can lift the blade.
Preferably the blade is transitioned from vertical tower guided hoisting condition to its horizontal condition to by a crane that can lift the blade at a location spaced from the hoist anchor.
Preferably the location spaced apart, is defined by a lifting anchor of the blade.
Preferably the lifting anchor is located more proximate the blade tip than then where the lowering of the blade occurs.
Preferably, in the horizontal condition, the blade and the at least one carriage are separated from the tower.
Preferably the crane and the support cable in concert suspend and move the blade from its vertical lowering condition to its horizontal condition.
Preferably the lowering occurs from a hoist point above the blade.
Preferably a winch to lower the blade is supported by the ground on which the tower is supported.
Preferably a winch is secured by the ground on which the tower is supported.
Preferably a winch is secured to and on the ground on which the tower is supported.
In a further aspect the present invention may be said to be a system for installing and/or removing a wind turbine blade to or from a rotor head of a nacelle located on top of a tower of a wind power generator, the system comprising
In a further aspect the present invention may be said to be a system for installing and/or removing a wind turbine blade to or from a rotor head of a nacelle located on top of a tower of a wind power generator, the system comprising
Preferably the at least one carriage is an upper carriage secured to the blade during hoisting at or proximate the blade root.
Preferably said hoisting and/or lowering is by a support cable or rope able to releasably attach to the blade and/or the at least one carriage (preferably the upper carriage).
Preferably a crane is provided able to lift the blade and in concert with the support cable to cause the blade to transition between its vertical condition parallel and adjacent the tower and a horizontal condition distal more the tower.
Preferably the crane that can lift the blade.
Preferably the crane that can lift the blade at a location spaced from the hoist anchor.
Preferably location spaced apart, is defined by a lifting anchor of the blade.
Preferably the lifting anchor is located more proximate the blade tip than then where the hoisting of the blade occurs.
Preferably the at least one carriage is an upper carriage able to be secured to the blade during hoisting at or proximate the blade root and wherein the location spaced apart is defined by a second of said at least one carriage, secured to the blade more proximate the blade tip.
Preferably the crane comprises a lifting boom and a lifting cable or rope that extends from the lifting boom to the blade to lift the blade.
Preferably the crane is vehicle mounted.
Preferably in the horizontal condition, the blade and the at least one carriage are separated from the tower.
Preferably the crane and the support cable in concert suspend and move the blade from its horizontal condition to its hoisting condition.
Preferably at least two and preferably 3 carriages are provided to be releasably secured to the blade at spaced apart locations.
Preferably the at least one carriage comprises of wheels or bearings able to move on and over the surface of surfaces of the tower during said hoisting.
Preferably the wheels or bearings help prevent the blade, during hoisting from swinging relative to the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined distance from the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined radial position from the tower.
Preferably the at least one carriage comprises of wheels or bearings able to move over the surface of surfaces of the tower and hold said blade at where the at least one carriage is secured to the blade at a predetermined tangential position from the tower.
Preferably said at least one carriage comprising a mechanism that allows the relative position of the blade and the tower to be adjusted to position the blade root in alignment with a blade mounting flange of the rotor head so that root bolts are able to insert into the root bolt apertures, by adjusting the position of the blade relative to the tower using the at least one carriage
Preferably said mechanism is an at least two axis translation mechanism.
Preferably said mechanism is an at least two axis translation mechanism able to displace the blade radially and tangentially relative to the tower at said carriage.
Preferably the mechanism is able to cause the moving of the blade to insert the root bolts into the bolt apertures.
Preferably at least one carriage is adapted and configured to be in sliding or rolling contact with the tower during hoisting and/or lowering of the blade.
Preferably the hoisting and/or lowering occurs from a hoist point above the blade.
Preferably hoist point is fixed relative to the tower.
Preferably the hoist point is located such that there is a gravitational bias on the blade and its secured carriage(s) during hoisting towards the tower surface of surfaces.
Preferably a winch to hoist and/or lower the blade is supported by the ground on which the tower is supported.
Preferably a winch to hoist and/or lower the blade is secured by the ground on which the tower is supported.
Preferably a winch to hoist and/or lower the blade is secured to and on the ground on which the tower is supported.
Preferably the support cable or rope during hoisting extends from the blade or said at least one carriage upwardly to a hoist point.
Preferably the support cable or rope during hoisting extends from the blade or said at least one carriage upwardly to a hoist point and from the hoist point toward the ground to a hoist winch.
Preferably the system further comprises a support vehicle.
Preferably the support vehicle can support the blade.
Preferably the support vehicle can deliver the blade to or from a remote location to or from the wind power generator.
Preferably the support vehicle is road vehicle (e.g. by a truck).
The term ‘comprising’ as used in this specification and claims means ‘consisting at least in part of’. When interpreting statements in this specification and claims which include the term ‘comprising’, other features besides the features prefaced by this term in each statement can also be present. Related terms such as ‘comprise’ and ‘comprised’ are to be interpreted in a similar manner.
It is intended that reference to a range of numbers disclosed herein (for example, 1 to 10) also incorporates reference to all rational numbers within that range (for example, 1, 1.1, 2, 3, 3.9, 4, 5, 6, 6.5, 7, 8, 9 and 10) and also any range of rational numbers within that range (for example, 2 to 8, 1.5 to 5.5 and 3.1 to 4.7) and, therefore, all sub-ranges of all ranges expressly disclosed herein are hereby expressly disclosed. These are only examples of what is specifically intended and all possible combinations of numerical values between the lowest value and the highest value enumerated are to be considered to be expressly stated in this application in a similar manner.
This invention may also be said broadly to consist in the parts, elements and features referred to or indicated in the specification of the application, individually or collectively, and any or all combinations of any two or more said parts, elements or features, and where specific integers are mentioned herein which have known equivalents in the art to which this invention relates, such known equivalents are deemed to be incorporated herein as if individually set forth.
As used herein the term ‘(s)’ following a noun means the plural and/or singular form of that noun.
As used herein the term ‘and/or’ means ‘and’ or ‘or’, or where the context allows both.
The invention consists in the foregoing and also envisages constructions of which the following gives examples only.
The invention will now be described by way of example only and with reference to the drawings in which:
With reference to the above drawings, in which similar features are generally indicated by similar numerals, a wind turbine blade installation system according to a first aspect of the invention is generally indicated by the numeral 1000.
Likewise, an example wind turbine tower 200 is shown in
Generally, the blade 10 has an uppermost blade root 12, a central portion 14 and a blade tip 16. The root 12 generally may have a substantially cylindrical or tubular configuration, as shown in
The term ‘bolt’ as used herein merely as one example of means used to couple together the blade mounting flange 222 of the rotor head 220 of the wind turbine nacelle 210. Other fastening means may be employed known to those skilled in the art depending on the specific configurations of the wind turbine 200 as whole, the nacelle 210, its rotor head 220, the blade mounting flange(s) thereof 220, and/or the root configuration of a given blade 10.
The blade is shown in
Shown removably secured to the blade 10 in
Generally, at least one carriage is employed in the system 1000 described herein and is provided to assist in moving the blade 10 from its substantially horizontal condition to a substantially vertical orientation, where the blade root 12 is oriented upwardly and higher than the blade tip 16 oriented downwardly, as shown and described in relation to
However, in
Generally, at least an upper carriage 1020 is employed by the system 1000 at or proximate the blade root 12, however second, third or even more carriages may be advantageous to employ depending on the length or other features of the blade 10 to be installed.
The second or intermediate carriage 1040, when employed in combination with the first or upper carriage 1020, is generally placed at or proximate the central portion 14 of the blade 10, between the root 12 and tip 16. However, more generally, it may be placed anywhere along the blade 10, spaced apart from the blade root 12 at where the first carriage 1020 is placed, and generally more towards or proximate the blade tip 16 than said first carriage 1020.
Also shown in
Those skilled in the art will appreciate that the number of, and positions of, the carriages, and the lifting anchor 1100, employed in the systems and methods described herein are variable and may depend on any number of design, installation and engineering considerations, such as in particular, optimising balance/centre of gravity and reducing swaying/rotation of the blade 10 during lifting.
For instance, in the example embodiment shown where two carriages are employed, the first or upper carriage 1020 is generally provided at the blade root 12, with the second carriage 1040 provided at the central portion 14, and the lifting anchor 1100 provided at or near the blade tip 16.
However, in another embodiment, only a first carriage 1020 may be employed at the blade root 12, with no second carriage, and the lifting anchor 1100 provided at or near the blade tip 16. In such a case, the first carriage 1020 and lifting anchor 1100 positions may vary from those shown in
Similarly, in another embodiment, only a first and second carriage 1020, 1040 may be employed, with no lifting anchor 1100 provided. In such a case, the second carriage 1040 may be moved further toward the blade tip 16, once more to achieve a different centre of gravity when lifting the blade 10.
The first or upper carriage 1020 generally comprises of a mounting structure 1022, taking the form of a truss 1024 having two mounting flanges 1026 that connect to the root 12 of the blade 10. In particular the mounting flanges 1026 are configured (shaped/dimensioned) to match and thereby connect to the annular ring of root bolt apertures 12A of the blade root 12. Any number of mounting flanges 1026 may be provided and arranged in various ways about the root 12 of the blade 10. However, here there is shown two mounting flanges 1026 arranged at opposite ends of the root 12 circumference.
The embodiment three-axis translation mechanism is exemplary only, and many other structures and means other than rollers/rails could be employed to provide three-axis translation of the carriage 1020, such that, the position of the blade 10 (i.e., of the mounting structure 1022 which connects to the blade 10) relative the tower 200 (i.e., of the guiding structure 1032 which contacts the tower 200 surface thereby guiding the blade 10 up the tower 200) to be adjusted.
To that end, the guiding structure 1032 comprises of a plurality of guiding legs 1034, configured depending on the expect outer diameter(s) of the tower 200 to generally extend around the outer periphery of the tower 200. As such, mounted to the guiding legs 1034 are a plurality of rollers 1036 which may contact the outer periphery/surface(s) of the tower 200 so as to provide rolling or sliding contact and thus movement of the carriage 1020 as a whole up the tower 200 as the blade 10 is being lifted. Mounted to extremities of the forward-most guiding legs 1034 are hoisting points 1038 to which by a support cable or rope 1400 may be releasably attached. Mounted to the rear of the guiding structure 1032 is hoisting point (not shown) to which the tensioning cables 1200 described above can connect.
The second carriage 1040 generally comprises of a mounting structure 1042, taking having mounting legs 1044 that connect to the central portion 14 of the blade 10. This may be via direct connection (i.e., using fasteners etc.) or via e.g. ratcheted straps, tensioned cables or the like, or any other suitable means of coupling said mounting legs 1044 to surfaces or anchors of the central portion 14 of the blade 10.
The embodiment angular pivoting mechanism is exemplary only, and many other structures and means other than rollers/rails could be employed to provide angular pivoting of the carriage 1040, such that, the angular pitch/position of the central portion 14 of the blade 10 (i.e., of the mounting structure 1042 which connects to the central portion 14) relative the tower 200 (i.e., of the guiding structure 1046 which contacts the tower 200 surface thereby guiding the blade 10 up the tower 200) to be adjusted.
To that end, the guiding structure 1046 comprises of a plurality of guiding legs 1048, configured depending on the expect outer diameter(s) of the tower 200 to generally extend around the outer periphery of the tower 200. As such, mounted to the guiding legs 1048 are a plurality of rollers 1049 which may contact the outer periphery/surface(s) of the tower 200 so as to provide rolling or sliding contact and thus movement of the carriage 1040 as a whole up the tower 200 as the blade 10 is being lifted. Mounted to the rear and front of the guiding structure 1046 are hoisting points 1047 to which the tensioning cables 1200 described above can connect.
The lifting system 1000, and related example lifting processes and methods will now be described.
The cables 1400 then extend and escape outwardly from the walls of the tower 200, proximate and underneath the nacelle 210 thereof. This is shown in
It is by way of these hoisting means, e.g. tensioned cables 1400 that lift the first carriage 1020 up the tower 200, that the blade 10 is lifted.
In some embodiments, the winching arrangement 1300 may be provided within the interior of the tower 200 itself, but still at ground/foundation level, with its hoisting means, e.g. tensioned cables 1400 extending upwardly to the top of the tower 200.
In other embodiments, the winching arrangement 1300 may instead be provided directly beneath the nacelle 210, within the interior of the tower 200, with its hoisting means, e.g. tensioned cables 1400 extending downwardly to aforementioned idle pulleys 1410.
Those skilled in the art will envisage variations of where to position the winching arrangement 1300 and how to route the cables thereof, i.e., the winches may even be mounted at the top of the tower 200, in lieu of said idle pulleys 1410.
However, it is generally preferable that the cables 1400 extend from near the nacelle 210, so that as the blade is being lifted, it can be brought as close as possible to the rotor head 220 of the tower 200.
It is also generally preferable that the cables be mostly routed through the interior of the tower 200, so as to avoid or reduce them swaying as experienced by cables/cranes in the typically high-wind wind turbine installation fields/farms. This may thereby reduce risk and assisting in final alignment of the blade 10 with the rotor head 210.
Also shown in
The lifting anchor 1100 is shown throughout the figures arranged about the blades 10 periphery, and having two upper hoisting points 1100A thereabove, to which a cable of the crane 1500 connects, and a lower hoisting point 1100B 1040 (visible in
Those skilled in the art will appreciate that in some embodiments, a lifting anchor 1100 may not be needed, and a second, third, fourth etc. carriage can simply be moved further toward the blade tip 16, with the crane 1500 connecting thereto to assist in suspension of the blade tip 16.
Further, in some embodiments, the lifting anchor 1100 may be provided with a wheeled or roller arrangement so as to assist in its guidance up the surfaces of the tower 200.
However, generally, the extent to which the first carriage 1020 extends ‘down’ (relative the blades horizontal condition) from the blade root 12 means that often the blade tip 16 may not at all contact the tower 200 during lifting.
In
In
In
Finally, in
A detailed view of this is seen in
Once aligned, the root bolts may be passed through both sets of apertures 12A, 222A and fastened to complete installation of the blade 10 onto the rotor head 210.
In some instances, it may be required that minor adjustments be made to the blade 10 position so as to completely align both sets of apertures 12A, 222A.
This may be done in a number of ways. Slack may be given to the hoisting cables 1400 so as to permit minor movement of the blade 10. Further, more or less tension may be provided at one winch of the winch arrangement 1300 compared to the other winch, so as to effect a corresponding increase/decrease in tension or length of one hoisting cable 1400 relative the other. This may cause a slight sagging of the blade 10 at one side thereof once more permitting more some. Movement of the blade 10 in both these instances may be actioned by the worker(s) 1600, since the suspended blade 10 may not require more than manual labour to move small increments at such a height (e.g., the worker(s) 1600 within the nacelle 210 may pull the blade towards themselves, with the worker(s) 1600 within the rotor head 210 and atop the temporarily deck 12B assisting in this maneuverer).
Those skilled in the art may envisage other means of assisting alignment of the apertures 12A, 222A, such as, for instance, placing alignment rails on the blade mounting flange 222 of the rotor head 220 and corresponding guide rails on the blade root 12, such that as the root 12 approaches the rotor head 220, the alignment and guide rails cooperate and bring the two into correct coaxial alignment.
Further, in some embodiments, the plurality of rollers 1036 of the first or upper carriage 1020, and the plurality of rollers 1049 of the second carriage 1040 may be actuatable (i.e., the rotational positions thereof may be movable remotely) and may even be driven by motors, sufficient to provide only minor movements necessary to make the requisite minor adjustments to the blade 10 position.
In other words, modifications can be made to the rollers of the carriage(s) so that they not only passive provide sliding or rotational contact between the carriage(s) and tower 200 surface(s), but also provide activatable and controllable movement via motors and the like driving said rollers. Actuation jacks may also be provided extending from the carriage(s) and configured to push against the surfaces of the tower 200, to adjust the pitch angle of the blade 10 as necessary.
Further, while the roller and rail configurations of the three-axis translation mechanism of the first or upper carriage 1020 and of the angular pivoting mechanism of the second carriage 1020 may be passive, and thus slack so as to permit free movement of the various sub-structures of the carriage(s), they may instead also be actuated or driven, such that minor movements of the blade 10 can be effected from a remote location, to assist in final alignment of the apertures 12A, 222A.
It will be noted that
It will be appreciated that this may be done in conjunction with routing further cables 1400 through the lateral idle pulleys 1410. Any number of hoisting cables 1400 can be used, and any number of idle pulleys 1410, at various circumferential positions underneath the nacelle 210, to lift the first or upper carriage 1020.
It will also be appreciated that, prior to final coupling/fastening of the root bolts through the apertures 12A, 222A, the mounting flanges 1026 that connect to the root 12 of the blade 10 must be at least partially disconnected therefrom, so they do not inhibit the final pressing together of the root 12 with the blade mounting flange 222. For instance, some of the root bolts may first be partially fastened, the mounting flanges 1026 that connect to the root 12 then disconnected, after which the blade is supported by the partially fastened root bolts, then all root bolts positioned and fully fastened to complete installation of the blade 10.
The overall dimensions and geometries of the carriage(s) may be adjusted on a case by case basis to assist in appropriate distancing and alignment of the blade 12 root and tip 16 relative the tower 200. For instance, in relation to the first carriage 1020, the distance between the hoisting points 1038 (to which the hoisting cables 1400 connect) and the mounting flanges 1026 (and/or other means to which the root 12 of the blade connect) may determine the off-set distance of the blade root 12 relative the surface(s) of the tower 200 as it approaches it's final alignment and installation position.
These various forces FX, C.O.G, FT, FY1 and FY2 must all be resolved by way of appropriate configuration of the tension/lifting force imparted by the hoisting cables 1400, as well as in some embodiments, by the crane 1500. In some instances, the crane 1500 may not be a significant contributor to upward vertical lifting force, and so may be considered negligible. However, generally most of these forces must be balanced to ensure a gradual and smooth transition of the blade 10 from a substantially horizontal condition of
It should also be noted that a moment about the blades 10 centre of gravity C.O.G may also be created due to the distance therefrom that the first and second vertical lifting forces FY1, FY2 may act to rotate the blade in opposite directions (i.e., FY1 may rotate the blade 10 clockwise where's FY2 may rotate the blade 10 counter-clockwise, relative
To that end, the skilled person may appreciate that changes in the blade 10 position actioned by means of the three-axis translation mechanism of the first or upper carriage 1020, as well as by means of the angular pivoting mechanism of the second carriage 1040, can be used to carefully adjust the blades 10 position during its transition from a substantially horizontal condition of
Thus, F1 and F2 vertical lifting forces of each hoisting cable 1400 may need to be adjusted to account for the moment created by their different distances to said off-set centre of gravity C.O.G. Section A-A also illustrates these differences in distances of F1 and F2 to C.O.G., shown as D1 and D2 when viewed from a section extending across the hoisting points 1038 of the carriage 1020 to which the hoisting cable 1400 connect and lift the blade 10.
It should be noted that, the aforementioned examples of various aspects of the system and methods described herein may be configured to adjust the blade's position during final alignment of both sets of apertures 12A, 222A, may be equally employed by those skilled in the art when resolving the force considerations described above in relation to
The system 1000 and methods described herein may therefore provide a safe and cost-effective means of lifting and installing wind turbine blades, whereby:
It will also be appreciated that an inverse or reverse order of the methods/systems described above may be employed in removal or uninstallation of a blade 10 from a rotor head 210. For example:
Where in the foregoing description reference has been made to elements or integers having known equivalents, then such equivalents are included as if they were individually set forth.
Although the invention has been described by way of example and with reference to particular embodiments, it is to be understood that modifications and/or improvements may be made without departing from the scope or spirit of the invention.
In addition, where features or aspects of the invention are described in terms of Markush groups, those skilled in the art will recognise that the invention is also thereby described in terms of any individual member or subgroup of members of the Markush group.
Number | Date | Country | Kind |
---|---|---|---|
2021903775 | Nov 2021 | AU | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/IB2022/061311 | 11/23/2022 | WO |