The present disclosure relates to a work machine, a weighing method, and a system including the work machine.
PTL 1 (Japanese Patent Laying-Open No. 2001-99701) proposes a technique for measuring the weight of a load mounted on a load mount unit in a wheel loader.
PTL 1: Japanese Patent Laying-Open No. 2001-99701
In the above-mentioned literature, during the operation to raise a boom after excavation, the weight of the load mounted on the load mount unit is measured based on the boom angle and the pressure difference between the head pressure and the bottom pressure of a boom cylinder.
The boom cylinder pressure may not be stable during the operation to raise the boom. This may prevent accurate measurement of the weight of the load that is to be measured based on the boom cylinder pressure.
The present disclosure proposes a work machine, a weighing method, and a system including the work machine, by which a load in a bucket can be accurately weighed.
According to an aspect of the present disclosure, a work machine including a work implement, an input receiving unit, and a controller is provided. The work implement includes a bucket. The input receiving unit receives a weighing start input for starting to weigh the load in the bucket. When the input receiving unit receives the weighing start input, the controller determines whether an automatic weighing start condition is satisfied or not. The automatic weighing start condition includes a condition that the work implement is not performing an excavation work. When the automatic weighing start condition is satisfied, the controller controls an operation of the work implement to weigh the load in the bucket.
According to an aspect of the present disclosure, a weighing method for a work machine is provided. The work machine includes: a work implement including a bucket; and an input receiving unit. The weighing method is a method of weighing a load in the bucket. The input receiving unit receives a weighing start input for starting to weigh a load in the bucket. The weighing method includes the following steps including: a first step of, when the input receiving unit receives the weighing start input, determining whether an automatic weighing start condition is satisfied or not, the automatic weighing start condition including a condition that the work implement is not performing an excavation work; and a second step of, when the automatic weighing start condition is satisfied, controlling an operation of the work implement to weigh the load in the bucket.
According to an aspect of the present disclosure, a system including a work machine is provided. The system includes a work machine, an input receiving unit, and a controller. The work machine includes a work implement including a bucket. The input receiving unit receives a weighing start input for starting to weigh a load in the bucket. When the input receiving unit receives the weighing start input, the controller determines whether an automatic weighing start condition is satisfied or not. The automatic weighing start condition includes a condition that the work implement is not performing an excavation work. When the automatic weighing start condition is satisfied, the controller controls an operation of the work implement to weigh the load in the bucket.
According to the present disclosure, the load in the bucket can be accurately weighed.
Embodiments will be hereinafter described with reference to the accompanying drawings. In the following description, the same components are denoted by the same reference characters. Their names and functions are also the same. Accordingly, the detailed description thereof will not be repeated.
<Overall Configuration>
In an embodiment, a wheel loader 1 will be hereinafter described as an example of a work machine.
As shown in
Traveling unit 4 causes the vehicular body of wheel loader 1 to travel and includes running wheels 4a and 4b. Wheel loader 1 is a wheeled vehicle including running wheels 4a and 4b as rotating bodies for traveling on both sides of the vehicular body in a left-right direction. Wheel loader 1 is movable as running wheels 4a and 4b are rotationally driven, and also, can perform a desired work using work implement 3.
In the present specification, the direction in which wheel loader 1 travels straightforward is referred to as a front-rear direction of wheel loader 1. In the front-rear direction of wheel loader 1, the side where work implement 3 is located with respect to vehicular body frame 2 is referred to as a frontward direction, and the side opposite to the frontward direction is referred to as a rearward direction. The left-right direction of wheel loader 1 is orthogonal to the front-rear direction in a plan view of wheel loader 1 situated on a flat ground. The right side and the left side in the left-right direction in facing forward are defined as a right direction and a left direction, respectively. A top-bottom direction of wheel loader 1 is orthogonal to a plane defined by the front-rear direction and the left-right direction. In the top-bottom direction, the ground side is defined as a lower side and the sky side is defined as an upper side.
Vehicular body frame 2 includes a front frame 2a and a rear frame 2b. Front frame 2a and rear frame 2b constitute vehicular body frame 2 having an articulated structure.
Work implement 3 and a pair of left and right running wheels (front wheels) 4a are attached to front frame 2a. Work implement 3 is disposed on the front side of the vehicular body and is supported by the vehicular body of wheel loader 1. Work implement 3 is driven by hydraulic oil from a work implement pump 25 (see
A proximal end portion of boom 14 is attached by a boom pin 9 to front frame 2a so as to be rotatable. By a bucket pin 17 located at a distal end of boom 14, bucket 6 is attached to boom 14 so as to be rotatable.
Front frame 2a and boom 14 are coupled to each other by a pair of boom cylinders 16. Each boom cylinder 16 is a hydraulic cylinder. Each boom cylinder 16 has a proximal end attached to front frame 2a and a distal end attached to boom 14. As boom cylinder 16 extends and contracts by hydraulic oil from work implement pump 25 (see
Work implement 3 further includes a bucket cylinder 19. Bucket cylinder 19 is a hydraulic cylinder and serves as a work tool cylinder that drives bucket 6 as a work tool. When bucket cylinder 19 extends and contracts by hydraulic oil from work implement pump 25 (see
Cab 5 and a pair of left and right running wheels (rear wheels) 4b are attached to rear frame 2b. Cab 5 is disposed behind boom 14. Cab 5 is placed on vehicular body frame 2. A seat on which an operator sits, an operation device 49 (described later), and the like are disposed inside cab 5.
Wheel loader 1 includes engine 20, a motive power extraction unit 22, a motive power transmission mechanism 23, a cylinder driving unit 24, a first angle detector 29, a second angle detector 48, and a first processor 30 (a controller).
Engine 20 is a diesel engine, for example. Engine 20 is accommodated in the accommodation space covered by an engine hood 7 (
Motive power extraction unit 22 is a device that distributes the output from engine 20 to motive power transmission mechanism 23 and cylinder driving unit 24. Motive power transmission mechanism 23 is a mechanism that transmits the driving force from engine 20 to front wheels 4a and rear wheels 4b, and serves as a transmission, for example. In wheel loader 1, both front wheels 4a attached to front frame 2a and rear wheels 4b attached to rear frame 2b constitute driving wheels that receive driving force to cause wheel loader 1 to travel. Motive power transmission mechanism 23 changes the speed of rotation of an input shaft 21 and outputs the resultant rotation to an output shaft 23a.
Cylinder driving unit 24 includes work implement pump 25 and a control valve 26. The output from engine 20 is transmitted to work implement pump 25 through motive power extraction unit 22. The hydraulic oil discharged from work implement pump 25 is supplied to boom cylinder 16 and bucket cylinder 19 through control valve 26.
First hydraulic pressure detectors 28a and 28b for detecting hydraulic pressure (cylinder pressure) in an oil chamber of boom cylinder 16 are attached to boom cylinder 16. Wheel loader 1 includes first hydraulic pressure detectors 28a and 28b. First hydraulic pressure detectors 28a and 28b correspond to the cylinder pressure sensing units of the embodiment that sense the cylinder pressure in boom cylinder 16. First hydraulic pressure detectors 28a and 28b include a pressure sensor 28a for detecting head pressure and a pressure sensor 28b for detecting bottom pressure, for example.
Pressure sensor 28a is attached to the head side of boom cylinder 16 (the side from which a piston rod of boom cylinder 16 protrudes). Pressure sensor 28a can detect the pressure (head pressure) of the hydraulic oil in the cylinder head-side oil chamber of boom cylinder 16. Pressure sensor 28a outputs a detection signal showing the head pressure in boom cylinder 16 to first processor 30.
Pressure sensor 28b is attached to the bottom side of boom cylinder 16 (the side from which the piston rod of boom cylinder 16 does not protrude). Pressure sensor 28b can detect the pressure (bottom pressure) of the hydraulic oil in the cylinder bottom-side oil chamber of boom cylinder 16. Pressure sensor 28b outputs a detection signal showing the bottom pressure in boom cylinder 16 to first processor 30.
First angle detector 29 is, for example, a potentiometer attached to boom pin 9. First angle detector 29 detects a boom angle showing a lift angle of boom 14. First angle detector 29 outputs a detection signal showing the boom angle to first processor 30.
Specifically, as shown in
First angle detector 29 may be a stroke sensor disposed in boom cylinder 16. First angle detector 29 corresponds to a boom angle sensing unit of the embodiment that senses boom angle θ1 indicating an angle of boom 14 with respect to the vehicular body of wheel loader 1.
Second angle detector 48 is a potentiometer, for example. Second angle detector 48 detects a bucket angle indicating an angle of bucket 6 with respect to boom 14. Second angle detector 48 outputs a detection signal indicating the bucket angle to first processor 30. Second angle detector 48 may be a proximity switch. Alternatively, second angle detector 48 may be a stroke sensor disposed on bucket cylinder 19.
As shown in
Wheel loader 1 includes a weighing start switch 45. Weighing start switch 45 is operated by an operator. Weighing start switch 45 is disposed, for example, inside cab 5. When weighing start switch 45 is operated by the operator, weighing start switch 45 outputs a signal indicating the details of the operation to first processor 30.
When first processor 30 is not performing the process of weighing the load in bucket 6, weighing start switch 45 is operated, and weighing start switch 45 outputs a signal to first processor 30 indicating that weighing start switch 45 has been operated. Thereby, first processor 30 recognizes that the operation to start the automatic weighing has been performed. While first processor 30 is performing the process of weighing the load in bucket 6, weighing start switch 45 is operated to output the signal to first processor 30 indicating that weighing start switch 45 has been operated. Thereby, first processor 30 recognizes that the operation to forcedly terminate the automatic weighing has been performed.
Weighing start switch 45 corresponds to an input receiving unit of the embodiment that receives a weighing start input for starting to weigh the load in bucket 6. Weighing start switch 45 may be any type of switch such as a push button switch, a toggle switch, or a rotary switch, for example. The input receiving unit is not limited to a switch but may have any configuration to which an operator can input an instruction to start weighing. For example, the input receiving unit may be configured of a touch panel.
First processor 30 is configured of a microcomputer including a storage device such as a random access memory (RAM) and a read only memory (ROM), and a computing device such as a central processing unit (CPU). First processor 30 may be implemented as a part of the function of the controller of wheel loader 1 that controls the operations of engine 20, work implement 3 (boom cylinder 16, bucket cylinder 19, and the like), motive power transmission mechanism 23, a display unit 40, and the like.
First processor 30 receives inputs including mainly: a signal of boom angle θ1 detected by first angle detector 29; a signal of the bucket angle detected by second angle detector 48; a signal of the head pressure of boom cylinder 16 detected by pressure sensor 28a; a signal of the bottom pressure of boom cylinder 16 detected by pressure sensor 28b; and a signal issued from weighing start switch 45 and indicating that weighing start switch 45 has been operated.
First processor 30 includes a storage unit 30j. Storage unit 30j stores a program for controlling various operations of wheel loader 1. First processor 30 performs various processes for controlling the operation of wheel loader 1 based on the program stored in storage unit 30j. Storage unit 30j is a non-volatile memory and provided as an area in which necessary data is stored.
Wheel loader 1 includes display unit 40. Display unit 40 is a monitor disposed in cab 5 and viewed by the operator. Display unit 40 shows information. Display unit 40 shows, for example, information related to the weight of the load in bucket 6 that is calculated by first processor 30.
<Functional Blocks in First Processor 30>
First processor 30 shown in
From pressure sensor 28a, pressure acquiring unit 30a receives an output of a detection signal indicating the head pressure of boom cylinder 16. From pressure sensor 28b, pressure acquiring unit 30a receives an output of a detection signal indicating the bottom pressure of boom cylinder 16. Pressure acquiring unit 30a calculates a pressure difference between the head pressure and the bottom pressure (the boom pressure) of boom cylinder 16. Pressure acquiring unit 30a outputs a signal of the calculated boom pressure to load weight calculating unit 30c.
From first angle detector 29, angle acquiring unit 30b receives an output of a detection signal indicating boom angle θ1. Angle acquiring unit 30b outputs a signal indicating the acquired boom angle θ1 to load weight calculating unit 30c.
Load weight calculating unit 30c calculates the load weight in bucket 6 based on the signal indicating boom angle θ1 output from angle acquiring unit 30b and the signal indicating the boom pressure output from pressure acquiring unit 30a. The method of calculating the load weight in load weight calculating unit 30c will be described later in detail with reference to
Storage unit 30j stores the load weight output from load weight calculating unit 30c. Load weight output unit 30f outputs the load weight output from load weight calculating unit 30c or read from storage unit 30j to display unit 40. Display unit 40 causes a screen or the like to show the load weight.
<Method of Calculating Load Weight>
The following describes an example of a method of calculating a load weight.
When boom angle θ1 and boom pressure Pτ at a certain time point are obtained, the load weight at that time point can be calculated. For example, assuming that boom angle θ1=θk and boom pressure Pτ=Pτk at a certain time point mk as shown in
As shown in
When Pτk is located between PτA and PτC as shown in
The method of calculating the load weight in bucket 6 is not limited to the examples shown in
<Excavation Operation>
Wheel loader 1 of the embodiment performs: an excavation operation for scooping an excavation target 100 such as soil onto bucket 6; and a loading operation for loading a load L (excavation target 100) in bucket 6 onto a transportation machine such as a truck bed (an object onto which a load is loaded) of a dump truck. Wheel loader 1 repeatedly performs the excavation operation and the loading operation to excavate excavation target 100 and loads excavation target 100 onto a transportation machine such as a dump truck.
As shown in
As shown in
The line of “forward and rearward movement operation” shows a determination condition about the operation performed by the operator to move wheel loader 1 forward or rearward, which is indicated by a circle mark.
The line of “work implement operation” shows a determination condition about the operation performed on work implement 3 by the operator, which is indicated by a circle mark. More specifically, the line of “boom” shows a determination condition about the operation performed on boom 14. Also, the line of “bucket” shows a determination condition about the operation performed on bucket 6.
The line of “work implement cylinder pressure” shows a determination condition about the current hydraulic pressure in a cylinder of work implement 3, e.g., the hydraulic pressure in a cylinder bottom chamber of boom cylinder 16. In this case, four reference values A, B, C, and P are set in advance for the hydraulic pressure. Based on these reference values A, B, C, and P, a plurality of pressure ranges (a range lower than reference value P, a range of reference values A to C, and a range of reference values B to P) are defined. These four reference values A, B, C, and P are defined in relation of A>B>C>P in descending order.
By using a combination of determination conditions about “forward and rearward movement operation”, “boom”, “bucket”, and “work implement cylinder pressure” for each work step, first processor 30 can determine whether the step that is currently performed is an excavation work or not.
A specific operation of first processor 30 in performing control shown in
Combinations of the determination conditions about “forward and rearward movement operation”, “boom”, “bucket”, and “work implement cylinder pressure” corresponding to the respective work steps shown in
First processor 30 compares the combination of the type of the current forward and rearward movement operation, the type of the current boom operation, the type of the current bucket operation, and the current lift cylinder hydraulic pressure that have been recognized (i.e., the current work state) with the previously stored combination of the determination conditions for “forward and rearward movement operation”, “boom”, “bucket”, and “work implement cylinder pressure” corresponding to the respective work steps. As a result of this comparison process, first processor 30 determines whether the combination of the determination conditions best matching with the current work state is an excavation work or not.
In the excavation step shown in
<Flow of Weighing Load L in Bucket 6>
Wheel loader 1 in the present embodiment automatically weighs load L based on the operator's operation to measure the weight of load L mounted in bucket 6. FIG. 8 is a flowchart illustrating a weighing method of weighing a load in bucket 6 according to an embodiment.
As shown in
Then, it is determined whether an automatic weighing start condition is satisfied or not (step S2).
First, it is determined whether work implement 3 is performing an excavation work or not (step S11). The determination in step S11 is made using the determination in the work step as an example of the determination made during an excavation work. First processor 30 refers to the table shown in
When it is determined that the current step is not excavation and work implement 3 is not performing an excavation work (NO in step S11), then, it is determined whether or not work implement 3 is performing a soil ejection work (step S12). In the determination in step S12, based on the combination of the determination conditions of “forward and rearward movement operation”, “boom”, “bucket”, and “work implement cylinder pressure”, first processor 30 determines whether the current work step is a soil ejection step of mounting a load in bucket 6 onto a transportation machine such as a dump truck, or another step.
Since load L in bucket 6 decreases during the soil ejection work of work implement 3, the load weight in bucket 6 is not kept fixed. When the soil ejection work ends, bucket 6 no longer contains load L to be weighed. In order to accurately weigh load L in bucket 6, the automatic weighing start condition includes a condition that work implement 3 is not performing a soil ejection work.
When it is determined that the current step is not a soil ejection step and work implement 3 is not performing a soil ejection work (NO in step S12), then, it is determined whether or not boom angle θ1 is smaller than a weighing lower limit angle (step S13). First processor 30 sets, in advance, the range of boom angle θ1 suitable for weighing the load in bucket 6. First processor 30 sets the angle range so as to weigh the load in bucket 6 when boom angle θ1 falls within the prescribed angle range. This angle range may be input to first processor 30 by the operator and stored in storage unit 30j, or may be input to first processor 30 through communication from outside and stored in storage unit 30j.
As to the angle range, for example, boom angle θ1 may range from −20° to +20°. In this case, the lower limit value of the angle range (the “weighing lower limit angle” in step S13) is −20°. The upper limit value of the angle range (the “weighing upper limit angle” in step S33 (
First processor 30 compares boom angle θ1 input from first angle detector 29 with the weighing lower limit angle stored in storage unit 30j. Then, first processor 30 determines whether or not boom angle θ1 is smaller than the weighing lower limit angle.
When it is determined that boom angle θ1 is smaller than the weighing lower limit angle and the angle of boom 14 with respect to the vehicular body of wheel loader 1 falls out of the angle range suitable for weighing (YES in step S13), then, it is determined whether or not boom 14 is being operated to be raised/lowered (step S14). First processor 30 determines whether it receives a signal or not from detection sensor 49b of operation device 49 for indicating that operation member 49a is being operated to instruct an operation to raise or lower boom 14.
When a signal indicating an instruction to raise or lower boom 14 is not input from detection sensor 49b, and it is determined that boom 14 is not being operated to be raised or lowered (NO in step S14), then, it is determined whether or not a failure occurs in any of the sensors (step S15). The sensors for which it is determined in step S15 about existence of a failure specifically include first angle detector 29 for detecting boom angle θ1, second angle detector 48 for detecting the bucket angle, and pressure sensors 28a and 28b for sensing the cylinder pressure of boom cylinder 16. When first processor 30 does not receive signals from any of these sensors, or when any of the signals input from these sensors indicates an abnormal value falling out of the normal range, first processor 30 determines that a failure occurs in the corresponding sensor.
When it is determined that no failure occurs in each of the sensors (NO in step S15), the process proceeds to step S16, and then, it is set that the automatic weighing start condition is satisfied.
When it is determined in step S11 that work implement 3 is performing an excavation work (YES in step S11), when it is determined in step S12 that work implement 3 is performing a soil ejection work (YES in step S12), when it is determined in step S13 that boom angle θ1 is equal to or larger than the weighing lower limit angle (NO in step S13), when it is determined in step S14 that boom 14 is being operated to be raised or lowered (YES in step S14), or when it is determined in step S15 that a failure occurs in any of the sensors (YES in step S15), and then, the process proceeds to step S17, and it is set that the automatic weighing start condition is not satisfied.
Then, the process of determining whether the automatic weighing start condition is satisfied or not ends (“END” in
Referring back to
At the time when automatic weighing is started, boom angle θ1 is smaller than the weighing lower limit angle as determined in step S13, and work implement 3 is located at a position close to the ground. Thus, a process of raising boom 14 is first performed (step S21). First processor 30 outputs a control signal to control valve 26 to control the flow rate and the direction of the hydraulic oil supplied to boom cylinder 16, to thereby cause boom cylinder 16 to extend. Boom 14 rotates about boom pin 9, and boom 14 and bucket 6 attached to the distal end of boom 14 rise. As boom 14 rises, the absolute value of boom angle θ1 gradually decreases.
Then, it is determined whether or not boom angle θ1 is equal to or larger than the weighing lower limit angle (step S22). The determination in step S22 is repeated until boom angle θ1 becomes equal to or larger than the weighing lower limit angle. During this determination step, boom 14 continues to rise.
When it is determined that boom angle θ1 is equal to or larger than the weighing lower limit angle (YES in step S22), boom pressure Pτ is then acquired (step S23). From pressure sensor 28a, pressure acquiring unit 30a receives an output of a detection signal indicating the head pressure of boom cylinder 16. From pressure sensor 28b, pressure acquiring unit 30a receives an output of a detection signal indicating the bottom pressure of boom cylinder 16. Pressure acquiring unit 30a calculates a pressure difference between the head pressure and the bottom pressure (boom pressure Pτ) of boom cylinder 16. Pressure acquiring unit 30a outputs a signal of the calculated boom pressure Pτ to load weight calculating unit 30c.
Then, boom angle θ1 is acquired (step S24). From first angle detector 29, angle acquiring unit 30b receives an output of a detection signal indicating boom angle θ1. Angle acquiring unit 30b outputs a signal indicating the acquired boom angle θ1 to load weight calculating unit 30c.
Then, the load weight is calculated (step S25). Referring to
In this way, a series of processes related to automatic weighing in step S3 ends (“END” in
Referring back to
First, it is determined whether work implement 3 is performing an excavation work or not (step S31). In step S31, the same determination as that in step S11 (
When it is determined that work implement 3 is not performing an excavation work (NO in step S31), it is then determined whether work implement 3 is performing a soil ejection work or not (step S32). In step S32, the same determination as that in step S12 (
When it is determined that work implement 3 is not performing a soil ejection work (NO in step S32), it is then determined whether or not boom angle θ1 is larger than the weighing upper limit angle (step S33). First processor 30 compares boom angle θ1 input from first angle detector 29 with the weighing upper limit angle stored in storage unit 30j. Then, first processor 30 determines whether or not boom angle θ1 is larger than the weighing upper limit angle.
When it is determined that boom angle θ1 is not larger than the weighing upper limit angle, i.e., boom angle θ1 is equal to or smaller than the weighing upper limit angle (NO in step S33), then, it is determined whether an instruction to operate boom 14 is issued or not by another control (step S34). First processor 30 determines whether or not a control signal for changing the cylinder length of boom cylinder 16 so as to raise or lower boom 14 is output to control valve 26 by a process in another functional block not shown in
In addition to the determination as to whether an instruction to raise or lower boom 14 is issued or not by the control process in first processor 30, it may also be determined whether or not boom 14 is operated to be raised/lowered by operation device 49 operated by the operator.
In addition, first processor 30 may determine whether a control signal for stopping boom 14 is output or not to control valve 26 by a process in another functional block not shown in
When it is determined that an instruction to operate boom 14 is not issued (NO in step S34), it is then determined whether a failure occurs or not in any of the sensors (step S35). In step S35, the same determination as that in step S15 (
When it is determined that no failure occurs in any of the sensors (NO in step S35), it is then determined whether an operation to forcedly terminate the automatic weighing has been performed or not (step S36). When the operator operates weighing start switch 45 during execution of automatic weighing and a signal indicating that a switch operation has been performed is output from weighing start switch 45 to first processor 30, then, first processor 30 recognizes that the operation to forcedly terminate the automatic weighing has been performed.
Separately from weighing start switch 45, a forced termination switch operated by the operator may be provided inside cab 5. In this case, upon receipt of the signal indicating that the operator has operated the forced termination switch, first processor 30 may recognize that the operation to forcedly terminate the automatic weighing has been performed.
When it is determined that the operation to forcedly terminate the automatic weighing has not been performed (NO in step S36), the process proceeds to step S37, and then, it is set that the forced termination condition is not satisfied.
When it is determined in step S31 that work implement 3 is performing an excavation work (YES in step S31), when it is determined in step S32 that work implement 3 is performing a soil ejection work (YES in step S32), when it is determined in step S33 that boom angle θ1 is larger than the weighing upper limit angle (YES in step S33), when it is determined in step S34 that an instruction to raise or lower boom 14 has been issued (YES in step S34), when it is determined in step S35 that a failure occurs in any of the sensors (YES in step S35), or when it is determined that an operation to forcedly terminate the automatic weighing has been performed (YES in step S36), then, the process proceeds to step S38, and it is set that the forced termination condition is satisfied.
Then, the process of determining whether the forced termination condition is satisfied or not ends (“END” in
Referring back to
As shown in
It is preferable that weighing of load L in bucket 6 can be completed in a short time period since the productivity of the excavating and loading operations by wheel loader 1 can be enhanced. When it is determined that a sufficiently accurate load weight could be acquired without having to conduct a prescribed number of times of load weight calculation, it may be determined that the condition for terminating the weighing has been satisfied based on the determination in step S5. For example, when the load weight obtained in the first calculation and the load weight obtained in the second calculation are equal to each other or are not strictly equal to each other but the difference therebetween is sufficiently small, then, it may be determined that a sufficiently accurate load weight could be acquired by two times of load weight calculations, and thereby may be determined that the condition for terminating the weighing has been satisfied. Alternatively, for example, the weight of load L may be fixed only by one load weight calculation, and then, it may be determined that the condition for terminating the weighing has been satisfied.
When it is determined in step S5 that the condition for terminating the weighing has been satisfied, weighing of the load in bucket 6 is terminated and the load weight in bucket 6 is fixed. For example, the average value of the results obtained by multiple calculations of the load weight and stored in storage unit 30j may be fixed as a load weight in bucket 6. Alternatively, for example, the load weight calculated in step S3 immediately before the determination made in step S5 that the condition for terminating the weighing has been satisfied may be fixed as a load weight in bucket 6.
Then, a process of stopping boom 14 is performed (step S6). First processor 30 outputs a control signal to control valve 26 to perform control to stop changes in flow rate and direction of the hydraulic oil supplied to boom cylinder 16, to thereby stop boom cylinder 16. This prevents boom 14 from rotating about boom pin 9, with the result that boom 14 and bucket 6 attached to the distal end of boom 14 stop.
Then, the process proceeds to step S7, and the load weight is displayed. Load weight output unit 30f outputs the fixed load weight in bucket 6 to display unit 40. Display unit 40 causes a screen or the like to show the load weight.
When it is determined in step S2 that the automatic weighing start condition is not satisfied (NO in step S2), i.e., when it is set in step S17 in
In this way, a series of processes ends (“END” in
The following summarizes characteristic configurations, functions and effects about the work machine according to the above-described embodiment. Note that the constituent elements in the embodiment are denoted by reference characters, which are however provided merely by way of example.
As shown in
As shown in
Weighing of the load in bucket 6 is performed while boom 14 is being raised in order to ensure the weighing accuracy. The operation to raise boom 14 is controlled not by the operator's operation but by first processor 30. Boom 14 operates along a prescribed operation pattern, which allows boom 14 to be operated in a fixed manner at each weighing. The reproducibility of the operation of boom 14 is enhanced to thereby reduce the unevenness in operation of boom 14 that is caused by the operator's manual operation. Since the uniformity of the transition of boom angle θ1 during weighing of load L in bucket 6 is improved, the weighing accuracy can be improved. The weighing accuracy can be further improved when the operation pattern in which first processor 30 raises boom 14, for example, the speed of raising boom 14, and the like, are set to be suitable for weighing.
As shown in
As shown in
As shown in
First processor 30 can use boom angle θ1 and the bucket angle for determining that work implement 3 is not performing an excavation work. Based on the attitude of work implement 3 detected in real time, first processor 30 can more accurately determine that work implement 3 is not performing an excavation work.
Further, first processor 30 can use the traction force of wheel loader 1 (traveling unit 4) for determining that work implement 3 is not performing an excavation work. By calculating the traction force to distinguish whether the output from engine 20 is used for forward traveling of wheel loader 1 or for holding load L in bucket 6, first processor 30 can more accurately determine that work implement 3 is not performing an excavation work. The traction force of wheel loader 1 can be calculated based on: the rotation speed of the rotation shaft of engine 20 detected by rotation sensor 32 (
As shown in
As shown in
As shown in
As shown in
By applying the above-mentioned weighing method to wheel loader 1 that includes vehicular body frame 2 and running wheels (front wheels 4a and rear wheels 4b) attached to vehicular body frame 2 and also includes work implement 3 disposed forward of vehicular body frame 2, load L in bucket 6 of wheel loader 1 can be accurately weighed.
In the above embodiment, an example has been described in which the operation of boom 14 to perform automatic weighing is an operation to raise boom 14. When performing the automatic weighing, boom 14 may be operated not only to be raised but also to be lowered. When the load is weighed during the operation to lower boom 14, it is determined in step S13 (
In the above embodiment, an example has been described in which boom 14 is automatically stopped when weighing of load L in bucket 6 ends, but the present invention is not limited thereto. First processor 30 may notify the operator that the weighing has ended, to thereby cause the operator to stop boom 14 by the manual operation.
In the above embodiment, an example has been described in which wheel loader 1 includes first processor 30, and first processor 30 mounted in wheel loader 1 performs control to weigh the load in bucket 6. The controller that performs control to weigh the load in bucket 6 does not necessarily have to be mounted on wheel loader 1.
In the above embodiment, an example has been described in which wheel loader 1 includes cab 5 and is a manned vehicle in which an operator is seated inside cab 5. Wheel loader 1 may be an unmanned vehicle. Wheel loader 1 may not include a cab in which an operator is seated to operate wheel loader 1. Wheel loader 1 may not have a steering function executed by an operator who is aboard wheel loader 1. Wheel loader 1 may be a work machine exclusively for remote control. Wheel loader 1 may be controlled by a wireless signal from a remote steering device.
It should be understood that the embodiments disclosed herein are illustrative and non-restrictive in every respect. The scope of the present invention is defined by the terms of the claims, rather than the description above, and is intended to include any modifications within the meaning and scope equivalent to the terms of the claims.
1 wheel loader, 2 vehicular body frame, 2a front frame, 2b rear frame, 3 work implement, 4 traveling unit, 4a front wheel, 4b rear wheel, 6 bucket, 14 boom, 16 boom cylinder, 19 bucket cylinder, 20 engine, 24 cylinder driving unit, 25 work implement pump, 26 control valve, 28a, 28b first hydraulic pressure detector, 29 first angle detector, 30 first processor, 30a pressure acquiring unit, 30b angle acquiring unit, 30c load weight calculating unit, 30f load weight output unit, 30j storage unit, 40 display unit, 45 weighing start switch, 48 second angle detector, 49 operation device, 100 excavation target, 130 controller, L load.
Number | Date | Country | Kind |
---|---|---|---|
2019-238195 | Dec 2019 | JP | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/JP2020/044802 | 12/2/2020 | WO |