Claims
- 1. A system for scheduling lots of items for manufacturing comprising:
a manufacturing line, with a plurality of stations for processing lots to be manufactured; a tool at said stations for processing said lots; and a lot scheduling processor communicably coupled to said stations and able to compute bottleneck feed factors and critical ratios for each lot based on time needed at bottleneck minus buffer time, planned cycle time for each lot, estimated time until end of the line for each lot, and time until due for each lot.
- 2. The system of claim 1, further comprising a plurality of displays located at said stations and communicably coupled to said lot scheduling processor.
- 3. The system of claim 1, wherein the bottleneck feed factor for a particular lot is calculated by subtracting the ratio of the time needed at bottleneck minus buffer time all over the planned cycle time for said particular lot from one.
- 4. The system of claim 1, wherein the critical ratio for a particular lot is calculated by dividing the time until due for said particular lot by the estimated time to the end of the line for said particular lot.
- 5. The system of claim 1, wherein said lot scheduling processor calculates a ranking for each lot by applying a goal weighing factor to said bottleneck feed factor and by applying the compliment of said goal weighing factor to said critical ratio.
- 6. The system of claim 1, wherein a plurality of lots are arranged in at least one queue and wherein said queue is located at at least one station.
- 7. The system of claim 6, wherein an operator selects a lot to be processed from said queue based on the computations of the lot scheduling processor.
- 8. The System of claim 6, wherein a robotic operator selects a lot to be processed from said at least one queue based on the computations of the lot scheduling processor.
- 9. In a manufacturing line with a plurality of stations and a tool at said stations for processing lots of items to be manufactured and a lot scheduling processor communicably coupled to said stations, a method for scheduling the processing of lots for manufacturing comprising the steps of:
providing, to said lot scheduling processor, the time needed at bottleneck minus buffer time; providing, to said lot scheduling processor, the planned cycle time for each lot; providing, to said lot scheduling processor, the estimated time until end of the line for each lot; providing, to said lot scheduling processor, the time until due for each lot; by said lot scheduling processor, calculating the bottleneck feed factor for each lot; by said lot scheduling processor, calculating the critical ratio for each lot; by said lot scheduling processor, calculating a ranking of said lots based upon said bottleneck feed factors and critical ratios; and processing said lots in order according to said ranking.
- 10. The method of claim 9 further comprising the step of providing, to said lot scheduling processor, a goal weighing factor.
- 11. The method of claim 10, wherein the step of calculating a ranking of lots comprises the step of adding the product of said bottleneck feed factor times a goal weighing factor and the product of said critical ratio times the complement of said goal weighing factor.
- 12. The method of claim 9 further comprising the step of displaying the rankings of each lot at a display device located at said stations.
- 13. The method of claim 9 wherein the step of calculating a bottleneck feed factor for each lot comprises the steps of:
calculating, by said lot scheduling processor, the ratio of the time needed at bottleneck minus buffer all over the planned cycle time for said particular lot; and subtracting, by said lot scheduling processor, the said ratio of the time needed at bottleneck minus buffer all over the planned cycle time from one.
- 14. The method of claim 9 wherein the step of calculating the critical ratio for each lot comprises the steps of:
calculating, by said lot scheduling processor, the ratio of the time until due for said particular lot over the estimated time to the end of the line for said particular lot; and subtracting, by said lot scheduling processor, the said ratio of the time until due for said particular lot over the estimated time to the end of the line for said particular lot from one.
- 15. The method of claim 9 further comprising the step of providing said ranking to an operator.
- 16. A method for scheduling lots for semiconductor manufacturing comprising the steps of:
determining a goal weighing factor; calculating the bottleneck feed factor for each lot in a tool queue; calculating the critical ratio for said each lot in a tool queue; calculating the relative rank of each lot in a tool queue; displaying the relative rank of each lot in a tool queue, for each tool queue; and selecting the lots in each tool queue for tooling according to said relative rank.
- 17. The method of claim 16, wherein the displaying step comprises the step of sending the relative rank of each lot in a tool queue, to a display associated with said tool queue's respective tool.
- 18. The method of claim 16, wherein the displaying step comprises:
providing the relative rank of each lot in a tool queue to a computer network.
- 19. A method for scheduling lots for semiconductor manufacturing, comprising:
determining a goal weighing factor; obtaining the time needed at bottleneck minus buffer; obtaining the planned cycle time for each lot; obtaining the estimated time until the end of the line for each lot; obtaining the time until due for each lot; calculating the bottleneck feed factor for each lot in a tool queue; calculating the critical ratio for said each lot in a tool queue; calculating the relative rank of each lot in a tool queue; and selecting the lots in each tool queue for tooling according to said relative rank.
- 20. A program storage device readable by a machine, tangibly embodying a program of instructions executable by the machine to perform a method for scheduling lots for semiconductor manufacturing, the method comprising the steps of:
receiving the time needed at bottleneck minus buffer time; receiving the planned cycle time for each lot; receiving the estimated time until end of the line for each lot; receiving the time until due for each lot; calculating the bottleneck feed factor for each lot; calculating the critical ratio for each lot; and calculating a ranking of lots based upon said bottleneck feed factors and critical ratios.
- 21. The method of claim 20 further comprising the step of:
receiving a goal weighing factor.
- 22. The method of claim 20, wherein the step of calculating a ranking of lots comprises the step of adding the product of said bottleneck feed factor times a goal weighing factor and the product of said critical ratio times the complement of said goal weighing factor.
- 23. The method of claim 20 further comprising a step of displaying the rankings of each lot at a display device located at said stations.
- 24. The method of claim 20 wherein the step of calculating a bottleneck feed factor for each lot comprises the steps of:
calculating the ratio of the time needed at bottleneck minus buffer time all over the planned cycle time for said particular lot; and subtracting the said ratio from one.
- 25. The method of claim 20 wherein the step of calculating the critical ratio for each lot comprises the following step:
calculating the ratio of the time until due for said particular lot over the estimated time to the end of the line for said particular lot.
- 26. The method of claim 20 further comprising the step of providing said ranking to an operator.
CROSS-REFERENCE TO OTHER APPLICATIONS
[0001] This application claims priority from provisional application No. 60/344,204, filed on Dec. 28, 2001 and which is hereby incorporated by reference.