The disclosure relates to a method for determining the optimal arrangement of wave energy converters in wave power parks comprising several wave energy converters.
When designing wave power parks many parameters need to be considered and taken into account. The list comprises dominant or primary wave direction, dominant and primary wind direction, dominant or primary wavelength and therewith dominant or primary wave period. Each and every wave climate, in particular in coastal areas, thus about 0 to 10 km from the shore, has a predominant wave condition meaning predominant wave direction where the waves are coming from, predominant wavelength, predominant wave amplitude and predominant wave frequency.
Research has shown that it is important to be aware and know these parameters as good and as exact as possible prior to the actual planning and in particular prior to the installation of the wave power park.
In cases these parameters are not known, not investigated and/or not taken into consideration when planning and building a wave power park, then the resulting problem may require expensive measures, such as installing equipment that tolerates much higher electric power (voltage and current strength) or power fluctuations than what is actually necessary if proper investigation and planning takes place. This leads to increased use of resources and higher cost. In addition, unproper planning can lead to an unstable power supply, which poses problems for the operator, since the grid usually requires a rather stable power input with a comparably high base load.
In the past some sort of energy storage, for example in the form of capacitors or batteries has been proposed to flatten out power fluctuations and avoid equipment damage. Up to this day it has proven to be either technically difficult to use energy storage (batteries) or too expensive (capacitors). It is however conceivable that the option of energy storage to handle power fluctuations on a short term basis, can be used in the future. In particular capacitors could be of interest once economic and reliable solutions are available.
The inventor of the present disclosure has realized that with proper planning and careful investigation of the predominant wave climate in a coast- or shore region of interest it is possible to substantially optimize the power output, the amount of resources used and also optimize the use of financial resources. The inventor further discovered that two parameters are of particular importance, namely the predominant wave direction of incoming waves and the predominant wavelength of the incoming waves. The inventor finally discovered that each wave energy converter has two energy peaks per wave cycle, which determines the arrangement of the wave energy converters along a primary wave direction at a certain distance from one another for optimal power output and minimized power fluctuation.
Disclosed herein is a method for determining the arrangement of wave energy converters in a wave power park in a sea- or lake area comprising the steps of:
Measuring wavelength and wave direction over a period of time;
Collecting all values measured for the wavelength and the wave direction in a matrix;
Statistically determining, from the matrix, a predominant wavelength and a predominant wave direction;
Arranging an amount X of wave energy converters at a regular intervals over a distance that corresponds to half of the length of the predominant wavelength (PWL) or a multiple thereof, wherein the distance is measured in a direction at least more or less parallel to the predominant wave direction.
Arranging the wave energy converters at a regular interval over a distance that corresponds at least half of the length of the wavelength results in a stable power output, since the power peak of each wave energy converter occurs not at the same time as the adjacent neighbouring wave energy converter. This reduces power peaks and fluctuations and stabilizes the power output of the plurality of wave energy converters.
It is further explained herewith that a multiple means ½, 1, 1½, 2, 2½ or 0.5, 1, 1.5, 2, 2.5 and so on of the predominant wavelength. It is thus in particular also possible to equally distribute the amount of X wave energy converters along an entire length of the predominant wavelength as measured in a direction at least more or less parallel to the predominant wave direction.
In an embodiment of the disclosure X is a whole number, and wherein the interval (IL) between two adjacent wave energy converters is calculated by
whereby K is a number from 1 to 10 or higher, such as 1 to 100.
The above provides a basis for calculating the interval between immediately adjacent wave energy converters. The result will be a distance/interval in meters along which the wave energy converters are then spaced.
The method may further comprise the step of arranging the plurality of wave energy converters so that at least adjacent neighbouring wave energy converters are arranged shifted, as seen in a direction along the predominant wave direction.
The above may be understood as to arrange the plurality of wave energy converters on a line that is arranged perpendicular or inclined compared to the predominant wave direction. Even circular, elliptic is possible as long as immediate neighbouring wave energy converters are arranged shifted, as seen in a direction along the predominant wave direction. This means that immediate or adjacent neighbouring wave energy converters are not arranged on a straight line oriented parallel with the predominant wave direction, but instead shifted as seen along a direction that is parallel or corresponds to the predominant wave direction.
This reduces the effect of the wake of floating bodies or buoys arranged upstream the predominant wave direction on floating bodies or buoys arranged downstream the predominant wave direction.
The method may further include the step of arranging the plurality of wave energy converters on a V-shaped line, a U-shaped line, on a horseshoe shaped line, on a semi-elliptic line or a semi-circular line.
The above described line shapes describe lines on which the wave energy converters are arranged as seen from the sky towards the ocean—or lake floor.
The described line shapes improve energy harvesting, maintenance handling and at the same time it takes the optimal interval spacing in view of the predominant wavelength and shifting in view of the predominant wave direction between immediate neighbouring wave energy converters into account.
The wave energy converters may comprise a floating body, a wire, a housing anchored in the sea- or lakebed, said housing comprising a stator and a seesawing translator, whereby the seesawing translator is connected via the wire to the floating body.
The plurality of wave energy converters may be equally distributed in multiple arrays, wherein each array comprises one or more V-shaped line(s), U-shaped line(s), horseshoe-shaped line(s), on semi-elliptic line(s) or semi-circular line(s), as seen towards the lake- or ocean floor and wherein the wave energy converters are arranged, at least more or less regularly spaced on the V-shaped lines, U-shaped lines, horseshoe shaped lines, semi-elliptic lines or semi-circular lines. The described lines above may be summarized with the term symmetric, open concave Line or Geometry. Each array may comprise two symmetric, open concave lines or geometries arranged parallel with another and with a symmetry axis oriented parallel to the predominant wave direction.
The method may further comprise the step of connecting the amount of X wave energy converters to an inverter wherein X is a number chosen from the range of 4 to 8 wave energy converters, and wherein the distance between two adjacent wave energy converters connected to the inverter is calculated according to the above formula.
X may be any amount chosen from 5 to 7 wave energy converters, such as for example 5 wave energy converters.
This leads to a stable power output and therewith to a stable load/strain and exposure of the corresponding converters or inverter systems. There may be a plurality of converter system or inverter system integrated in a marine substation, each converter/inverter—system handling about 4 to 8 wave energy converters, preferably 5 to 7 wave energy converters and more preferably 5 wave energy converters.
In addition to the above, herein the following definitions are used to explain and describe the disclosure.
Predominant Wave Direction of Incoming Waves
Every coastal area has one primary or predominant wave direction. In some cases there may be two main wave directions, one about 180 degrees turned to the other. In particular in shore areas the primary wave direction is however rather stable and varies only with a few degrees. This can be used when wave power parks are planned and installed, since they are typically installed in coastal areas close to the shore, for example within 0-10 km from the shore. Determining the primary or predominant wave direction is important for the planning and the operation of the wave power park. Herein the predominant wave direction is relating to the direction along which the waves travel, thus along which the wave peaks and wave troughs move. The predominant wave direction can of course vary from area to area depending on winds, currents, sea-shore structure and sea-base structure.
Predominant Wavelength of Incoming Waves
Similar to the above described predominant wave direction it is possible to determine the predominant wavelength of the incoming waves. This can be measured with buoys and sensors for instance. The predominant wavelength can be determined by measuring the wave period thus how long it takes from peak to peak or trough to trough and then by determining the speed of the incoming waves.
Neighboring Wave Energy Converters
Herein the term neighboring energy converters or immediate neighboring wave energy converters describes two energy converters that are immediately adjacent one another without any other wave energy converter arranged in between. If a group of wave energy converters is connected to an inverter, then the wave energy converters of this group are spaced a quarter of the predominant wavelength to the next one and so one in order to reduce power fluctuations and stabilize electric energy output from the that converter.
Wave Front
The wave front is a direction along which the wave troughs and wave peaks extend. The wave front is typically oriented perpendicular to the (primary) wave direction. As the primary wave direction so can the wave front vary its direction depending on winds, sea-shore structure and so on.
Wavelength
The term wavelength used herein describes the length of an incoming ocean wave from peak to peak or trough to trough thus a length as measured in centimeters or meters (or any other length dimension for that matter) of an entire cycle of the ocean wave.
Wave Energy Converter
The arrays and arrangements described herein mainly refer to wave energy converters of the type as described in EP2318697 B1. Such a wave energy converter typically comprises a floating body, a wire and a housing anchored in the sea- or lakebed. The housing comprising a linear stator and a seesawing translator, whereby the seesawing translator is connected via the wire to the floating body. When waves move the floating body up and down the wire pulls the translator up and down in a seesawing movement. This produces energy since the translator moves along the stator, which creates inductive energy. This is on type of wave energy converter for which the described array is suitable, there may however be other types of wave energy converters that can be arranged in an array as described.
A Cluster or Array of Wave Energy Converters
The term cluster or array of wave energy converters used herein describes an arrangement of somewhere in between 10 to 30 wave energy converters arranged in an array and connected to a marine substation. A wave power park may consist of several such arrays. When the geometric arrangement of an array is described herein it is always described as seen in the bird (or drone) view thus from the top down; from the sky towards the ocean surface and seabed, respectively.
Symmetric, Open Concave Line or Geometry (as Seen from Above)
Herein a symmetric, open, concave line or geometry describes a line that is either V-shaped, U-shaped, at least more or less half elliptic, Y-shaped, at least more or less half circled, concave or any combination thereof. When the geometry of the symmetric, open concave line is described herein, it is always described as seen in the bird (or drone) view thus from the top down; from the sky towards the ocean surface and seabed, respectively.
The present disclosure will now be described, for exemplary purposes, in more detail by way of an embodiment(s) and with reference to the enclosed drawings, in which:
The three dashed lines in
Turning now to
Measuring S01 wavelength and wave direction over a period of time;
Collecting S02 all values measured for the wavelength and the wave direction in a matrix;
Statistically determining S03, from the matrix, a predominant wavelength (PWL) and a predominant wave direction;
Arranging S05 an amount X of wave energy converters at regular intervals over a distance that corresponds to half of the length of the predominant wavelength (PWL) or a multiple thereof, wherein the distance is measured in a direction at least more or less parallel to the predominant wave direction.
The period of time may be several months or a few years, it should at least include data of all seasons, thus summer, autumn, winter and spring. In addition, at least two to four measurements should be performed every day, such as morning, evening and night.
The statistical determination of the predominant wave direction and the predominant wavelength is determined by a frequency of occurrence and/or a probability density function of characteristic values and may be done using available tools such as for example Microsoft excel or specialized programs, such as high-level programming languages.
The method may further comprise the step of calculating S04 the regular interval between two adjacent wave energy converters using the following formula:
wherein K is a whole number chosen from 1 to 10.
Spacing the wave energy converters according to the value of the interval IL evens out the fluctuations in the power output of the amount X of the wave energy converters.
The wave energy converters 1, 1a, 1b, 1c, 1d, 1e may also be spaced according to another calculation, the requirement being that the interval between two immediately adjacent wave energy converters is regular as measured in a direction along the predominant wave direction PWL.
In an embodiment the amount X of wave energy converters 1, 1a, 1b, 1c, 1d, 1e may further be arranged S06 on a V-shaped line, a U-shaped line, on a horseshoe shaped line, on a semi-elliptic line or a semi-circular line.
A further step may comprise the connection S07 of the amount X of wave energy converters 1, 1a, 1b, 1c, 1d, 1e to one single inverter system. This leads to a stable power load on the inverter system.
The inverter system is typically embedded in a marine substation. The marine substation may comprise more than one inverter system. The components of the various inverter systems can also be shared within the marine substation. In an example the marine substation may comprise four inverter system, each inverter system being connected to five wave energy converters 1, 1a, 1b, 1c, 1d, 1e, which five wave energy converters 1, 1a, 1b, 1c, 1d, 1e are regularly spaced over ½ of the predominant wave length and the interval IL between two adjacent wave energy converters is thus 1/10 of the predominant wavelength (PWL).
A wave power park typically comprises several arrays of wave energy converters (not shown) and these arrays are oriented so that they take the predominant wave direction and the predominant wavelength into account. The method described herein allows to arrange and position the wave energy converters in an optimal manner to achieve a stable power output, increase efficiency, and increase applicability of the entire system.
Number | Date | Country | Kind |
---|---|---|---|
20178668.8 | Jun 2020 | EP | regional |
This application is a U.S. national phase of International Application No. PCT/SE2021/050543, filed on Jun. 7, 2021, which claims priority to European Application No. 20178668.8, filed Jun. 8, 2020, both of which are incorporated by reference herein in their entirety.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/SE2021/050543 | 6/7/2021 | WO |