Claims
- 1. A method of processing waste material comprising the following steps:
obtaining drilling waste material from a first offsite location; obtaining aggregate from a second location; transporting the drilling waste and aggregate to a treatment site; and processing transported material, on an impervious layer, said processing including at least the steps of: mixing the aggregate, the drilling waste and a binder to form an environmentally safe, structurally sound road base material.
- 2. The method of claim 1, wherein, prior to the mixing step, the aggregate and the drilling waste material is transported, via a screw auger, to a mixing location.
- 3. The method of claim 1, wherein, prior to the mixing step, the step of separation is undertaken, wherein the drilling waste and the aggregate are passed through a screen.
- 4. The method of claim 3, wherein the screen includes a shaker.
- 5. The method of claim 3, wherein, after the separation step, the step of moving is undertaken, wherein the materials separated are moved to a mixer via the use of one or more of the following: a screw conveyor, a pneumatic conveyor or direct feed with heavy equipment, or a belt conveyor.
- 6. The method of claim 1, wherein prior to the mixing step, the step of storing is undertaken wherein the drilling waste and the aggregate are stored at the treatment site on impervious layers.
- 7. The method of claim 6, wherein, after the storing step, the drilling waste and the aggregate are moved, in a moving step, via an excavator to the mixer for mixing therein.
- 8. The method of claim 1, wherein, prior to the mixing step, the drilling waste and the aggregate are placed in a separator, the separator placed above the mixer of the mixing step so that the material passing through the separator will enter the mixer of the mixing step.
- 9. The method of claim 1, wherein, after the mixing step, the material mixed is moved to a stacking location for storage.
- 10. The method of claim 9 wherein the mixed material is moved by one of the following: belt conveyor, screw conveyor, pneumatic conveyor, or by heavy equipment.
- 11. The method of claim 1, wherein, after the mixing, the material is tested for leachates.
- 12. The method of claim 1, wherein, after the mixing step, the material is tested for at least one of the following physical properties: stress, strain, compression, vheem stability, or any other test for indicating the suitability of the material for use as a roadbase.
Parent Case Info
[0001] This patent claims priority from and is a continuation-in-part of U.S. Patent application Ser. No. 10/062,119 filed Jan. 31, 2002, which in turn claims priority from and the benefit of 60/299,225 filed Jun. 19, 2001. This patent also claims priority from and is a continuation-in-part of U.S. patent Ser. No. 10/736,337 filed Dec. 15, 2003, the specification which is incorporated herein by reference, which application does in turn claim priority from U.S. Application No. 60/433,425 filed Dec. 13, 2002.
Provisional Applications (2)
|
Number |
Date |
Country |
|
60299225 |
Jun 2001 |
US |
|
60433425 |
Dec 2002 |
US |
Continuation in Parts (2)
|
Number |
Date |
Country |
Parent |
10062119 |
Jan 2002 |
US |
Child |
10801410 |
Mar 2004 |
US |
Parent |
10736337 |
Dec 2003 |
US |
Child |
10801410 |
Mar 2004 |
US |