Claims
- 1. An on-line process for removing copper deposits from the blades attached to the rotor of steam turbine wherein said process comprises:
adding an effective copper deposit-removing amount of an oxime to an injection point of an electric generating power plant comprising a pre-boiler system, a steam generator, a steam turbine, a condenser, and an electric generator, such that the system contains a source of copper, and such that the oxime reaches a temperature of at least 30° C. and contacts the blades attached to the rotor of the steam turbine.
- 2. The process of claim 1 wherein the oxime is methyl ethyl ketoxime.
- 3. The process of claim 2 wherein the source of copper is from one or more components of the one or more of the components of the steam generator made of alloys of copper.
- 4. The process of claim 3 wherein the dosage of oxime injected into the power plant is from 50 ppb to 150 ppb.
- 5. The process of claim 4 wherein the injection point of the oxime is selected from the group consisting of the feedwater of the lower pressure steam turbine and the boiler steam drum of the steam generator.
- 6. The process of claim 5 wherein the steam turbine contains a high-pressure turbine, an intermediate pressure turbine, and a low-pressure turbine.
- 7. The process of claim 6 wherein the oxime is continuously fed to the injection point for a period of 1 to 4 weeks.
- 8. The process of claim 7 wherein the steam turbine is a condensing steam turbine.
CROSS-REFERENCE TO RELATED APPLICATIONS AND CLAIM TO PRIORITY
[0001] Applicants hereby claim priority to U.S. provisional application serial No. 60/266,915 filed on Feb. 7, 2001, which is hereby incorporated by reference.
Provisional Applications (1)
|
Number |
Date |
Country |
|
60266915 |
Feb 2001 |
US |