Claims
- 1. A process for controlling the provision of conditioned water to a plurality of heat exchangers, under the control of zone controllers, said process comprising the steps of:periodically polling the plurality of zone controllers for the heat exchangers to obtain information concerning current and future demands for conditioned water by the zone controllers; determining whether there is a sufficient level of current demands for conditioned water from said zone controllers; determining whether there is a sufficient level of current and future demands for conditioned water from said zone controllers when there is not a sufficient level of current demands for conditioned water; and providing conditioned water to the heat exchangers in response to a determination that there is a sufficient level of current demands for conditioned water or if there is a sufficient predominance of current and future demands for conditioned water from said zone controllers.
- 2. The process of claim 1 further comprising the step of:storing in a system controller the information obtained from the zone controllers; and computing, within the system controller, a future demand for conditioned water for any zone controller not having a current demand for conditioned water.
- 3. The process of claim 2 wherein said step of computing a future demand for conditioned water comprises the step of:computing a start time for providing conditioned water to any zone controller not having a current demand for conditioned water.
- 4. The process of claim 3 wherein the information obtained from each zone controller includes the next future setpoint and associated start time for the next future setpoint for the zone controller, a currently sensed temperature for the zone associated with the zone controller, and a factor for the respective zone controller defining the amount of time necessary to adjust the sensed temperature in the respective zone by one degree; andwherein any start time for a zone controller is computed as a function of the difference between the next future setpoint for the zone controller and the current temperature for the zone controller, the difference being multiplied by the factor for the zone controller.
- 5. The process of claim 3 wherein said step of determining whether there is a sufficient level of current and future demands for conditioned water from said zone controllers comprises the steps of:adding the number of current demands for conditioned water in the array of information to the number of start times in the array; and comparing the added number of current demands for conditioned water and future start times with a minimum level of required demands for conditioned water.
- 6. The process of claim 5 further comprising the steps of:determining a start time for providing conditioned water to any heat exchanger associated with a zone controller having a current or future demand for conditioned water when there is a sufficient predominance of current and future demands.
- 7. The process of claim 6 wherein said step of determining a start time for providing conditioned water to any heat exchanger associated with a zone controller having a current or future demand for conditioned water comprises the steps of:determining the number of current demands for conditioned water in the stored information; determining the number of computed start times that need to be counted and combined with the number of current demands for conditioned water in the stored information in order to exceed a minimum number of zone controllers necessary to provide conditioned water; successively selecting the next to occur start time until the number of start times that needed to be counted have been counted; and selecting the last successively selected next to occur start time as the start time for providing conditioned water.
- 8. The process of claim 1 wherein the conditioned water is heated water and wherein the current and future demands for conditioned water are demands for heat.
- 9. The process of claim 1 wherein the conditioned water is chilled water and wherein the current and future demands for conditioned water are demands for cooling.
Parent Case Info
This application is a division, of application Ser. No. 09/572/901 filed May 17, 2000, now U.S. Pat. No. 6,467,537, which issued on Oct. 22, 2002.
US Referenced Citations (18)
Foreign Referenced Citations (1)
Number |
Date |
Country |
1 113 231 |
Jul 2001 |
EP |