In the current state of the art, a space transformer is connected to a testing PCB (or other PCB) through an interposer (spring contactor array), is mechanically bolted to the PCB, or is attached through direct solder attach. But these attachment/connection approaches suffer from significant drawbacks.
The interposer technique suffers from non-uniform planarity and high resistance-via-values.
Solder attach is done after PCB assembly-when expensive components are already on the board. Solder attach is difficult and prone to failure, and when it fails the expensive components may be damaged/destroyed and unusable. Also, planarity between the PCB and space transformer is difficult to insure. Additionally, solder attach does not allow for recess mounting to the PCT.
What is needed is improved method(s) for attaching a space transformer to a PCB.
A method for attaching two electronics boards, e.g., a testing PCB and a space transformer, comprises tack welding resin prepreg and a mylar film to a testing PCB; laser drilling via holes in the resin prepreg and mylar film such that the holes are aligned on one side of the resin prepreg with connection/capture pads on the testing PCB and aligned (after attachment) on the other side of the resin prepreg with connection capture pads on a space transformer, filling the via holes with sintering paste; applying a pressure treatment to remove air, bubbles, and voids from the sintering paste; removing the mylar film; and using a lamination press cycle to attach a space transformer to the resin prepreg.
A system and method are disclosed for mounting a space translator to a testing PCB.
The following table is for convenience only, and should not be construed to supersede any potentially inconsistent disclosure herein.
A process for attaching a space transformer to a testing PCB may comprise the process disclosed herein below.
In the disclosure herein, the abbreviation “mm” is used for millimeter.
At step 910, resin prepreg and a mylar layer/film may be tack welded to the testing PCB.
The benefit of thinner prepreg may be that it is easier to fill with sintering paste as described herein below.
As shown in
In one embodiment, prepreg 120 and mylar film 130 may be tack-welded to testing PCB 105 using a mylar bag and a vacuum laminator at 225 degrees Fahrenheit. As is understood in the art, other materials, temperatures, and or procedures may be used for tack welding or attaching prepreg 120 and mylar 130 to testing PCB 105.
As shown in
As shown in
At step 940, the testing PCB (with resin prepreg, drilled holes, and sintering paste in the drilled holes) is treated in a pressurized oven to remove air pockets from the via holes. Although a pressurized oven may be used, the heat may not be necessary. The pressure may by itself (i.e., without heat) remove air pockets from the bottoms of the via holes. In one embodiment. 8-bar pressure may be used. Additionally, the pressure may compress the sintering paste to the pad.
In one embodiment, the pressure oven (although the temperature feature of the oven is not used) may be a pressure/vacuum oven. A 30-minute cycle may be used for a vacuum cycle and a pressure cycle. The vacuum cycle may be 5 minutes. The pressure cycle may be 8-bar pressure for 20 minutes. The cycle may complete with 5 minutes to de-gas the chamber. The vacuum cycle may suck air and gasses out of the chamber, including sucking air and bubbles from the sintering paste. The pressure/compression cycle may compress the sintering pate and push air out of the sintering paste.
In one embodiment, the pressurized oven is run at 8-bar pressure for 20 minutes.
Other parameters may be used as long as the air pockets are removed from the via holes or substantially removed from the via holes. At step 950, a determination may be made regarding optionally adding additional sintering paste to the laser-drilled holes to ensure that the holes are sufficiently filled. This additional filling with sintering paste is necessary only if the holes are not sufficiently filled. If it is determined to add additional sintering paste, processing returns to step 930 for adding sintering paste and treating in a pressurized oven at step 940.
If at step 950 it is determined to not add additional sintering paste, at step 960 the testing PCB may optionally be inspected for voids and/or incomplete fill. If void, incomplete fill, and/or other problems are discovered, then steps 130-160 may be repeated.
As shown in
At step 970, space transformer 160 is attached to testing PCB 105 using a lamination press cycle.
The lamination press cycle cures prepreg 120 and sintering paste 150. Many lamination press technologies, methods, and/or tools are known in the art. In general, a lamination press cycle uses a combination of pressure and temperature. In one embodiment, the pressure may be set at 450 psi and the temperature ramp-up pattern may be, in degrees Fahrenheit, 180, 195, 300, 365, with the temperature remaining at 365 degrees Fahrenheit for 240 minutes. In general, a person of ordinary skill in the art will be able to adjust, modify, and or tune the parameters for the lamination press cycle. Additionally, the particular prepreg that is used may have specific lamination cycle parameters.
The attachment method described herein may have several benefits. One benefit is that the attachment may occur during the PCB manufacturing process, thereby avoiding damage to components that may be on the PCB after completion of some or all of PCB manufacturing. Another advantage is that the space transformer may be attached to the PCB so that the space transformer is recessed relative to the PCB surface, and possibly flush with the PCB surface.
Although this disclosure focuses on attaching a space transformer to a PCB, the methods. techniques, technologies, and innovations disclosed herein apply similarly to attaching a PCB to a PCB, or attaching a space transformer to a space transformer.
Number | Name | Date | Kind |
---|---|---|---|
4726480 | Hagan | Feb 1988 | A |
5370759 | Hakotani | Dec 1994 | A |
5407511 | Nakatani | Apr 1995 | A |
5647966 | Uriu | Jul 1997 | A |
5744758 | Takenouchi | Apr 1998 | A |
5972482 | Hatakeyama | Oct 1999 | A |
6096411 | Nakatani | Aug 2000 | A |
6237218 | Ogawa | May 2001 | B1 |
6739040 | Nakamura | May 2004 | B1 |
7939179 | DeVos | May 2011 | B2 |
9445511 | Kanda | Sep 2016 | B2 |
20020045394 | Noda | Apr 2002 | A1 |
20020178942 | Takenaka | Dec 2002 | A1 |
20030138553 | Takenaka | Jul 2003 | A1 |
20040135652 | Uchida | Jul 2004 | A1 |
20050016764 | Echigo | Jan 2005 | A1 |
20050046537 | Hagios | Mar 2005 | A1 |
20050066805 | Park | Mar 2005 | A1 |
20050129877 | Akada | Jun 2005 | A1 |
20050197020 | Park | Sep 2005 | A1 |
20060030226 | Park | Feb 2006 | A1 |
20060191133 | Nakao | Aug 2006 | A1 |
20070024297 | Ismail | Feb 2007 | A1 |
20070024298 | Khoo | Feb 2007 | A1 |
20070108586 | Uematsu | May 2007 | A1 |
20080129629 | Kimura | Jun 2008 | A1 |
20090051041 | Otsuka | Feb 2009 | A1 |
20090260858 | Nakai | Oct 2009 | A1 |
20100001748 | Sasaki | Jan 2010 | A1 |
20100219852 | Yamada | Sep 2010 | A1 |
20110124299 | Koujima | May 2011 | A1 |
20110277655 | Ko | Nov 2011 | A1 |
20120325533 | Yoshimura | Dec 2012 | A1 |
20130020394 | Koujima | Jan 2013 | A1 |
20130126221 | Kanda | May 2013 | A1 |
20130153276 | Kubo | Jun 2013 | A1 |
20140176286 | Okada | Jun 2014 | A1 |
20140224532 | Hashimoto | Aug 2014 | A1 |
20150235753 | Chatani | Aug 2015 | A1 |
20160145458 | Walker, Jr. | May 2016 | A1 |
20160295707 | Takano | Oct 2016 | A1 |
20160304682 | Liu | Oct 2016 | A1 |
20170017733 | Kuczynski | Jan 2017 | A1 |
20170122981 | Nasu | May 2017 | A1 |
20170283571 | Taketa | Oct 2017 | A1 |
20190106194 | Tajiri | Apr 2019 | A1 |
20210059058 | Hsu | Feb 2021 | A1 |
20210253813 | Koshi | Aug 2021 | A1 |
20210276276 | Tanaka | Sep 2021 | A1 |
Number | Date | Country | |
---|---|---|---|
20230053225 A1 | Feb 2023 | US |