The present disclosure relates generally to plasma processing. In particular, but not by way of limitation, the present disclosure relates to interoperation of equipment coupled to a plasma processing system.
Plasma processing systems for etching and deposition have been utilized for decades, but advancements in processing techniques and equipment technologies continue to create increasingly more complex systems. At the same time, the decreasing dimensions of structures created with workpieces requires increasingly precise control and interoperation of plasma processing equipment. Current control methodologies and associated systems are not capable of addressing several issues that are associated with the complex systems of today and tomorrow; thus, there is a need for new and improved control over disparate, yet interdependent, plasma processing equipment.
According to an aspect, a power delivery system comprises at least one modulating supply configured to provide power to a plasma load. The modulating supply modulates plasma properties where the modulation of the plasma properties has a repetition period, T. The system also comprises a match network configured to impedance match an output of the modulating supply to the plasma load; a first sensor configured to measure at least one parameter of the power at an output of the modulating suppl; and a controller. The controller is configured to receive the measured parameter signal from the sensor; receive a user power delivery requirement; analyze the at least one of measured parameter signal and the user power delivery requirement; instruct one or more of the modulating supply or the match network to adjust one or more operating parameters in order to meet the user power delivery requirements; and send a synchronization signal with a synchronization signal repetition period that is an integer multiple of T to at least one piece of equipment connected to the plasma system to synchronize the modulating supply and the at least one piece of equipment.
Another aspect may be characterized as a non-transitory, tangible processor readable storage medium encoded with instructions comprising instructions to monitor electrical characteristics of a power output of a modulating supply that modulates plasma properties where the modulation of the plasma properties has a repetition period, T; provide the electrical characteristics of the power output to a controller; and analyze the electrical characteristics of the power output. The characteristics of a characterized waveform with the repetition period T are communicated to at least one piece of equipment connected to plasma processing system to enable synchronization of pieces of equipment connected to the plasma processing system, and instructions are relayed to the modulating supply and a match network, based on the analyzing of the electrical characteristics, enabling simultaneous tuning of the modulating supply and the match network.
Yet another aspect may be characterized as a power control system of a power delivery system. The power delivery system comprises a first sensor configured to monitor power output of a modulating supply and impedance seen by the modulating supply, wherein the modulating supply is configured to provide power to a plasma via a match network that modulates the plasma. The power delivery system also comprises a controller in communication with the first sensor. The controller is configured to manage tuning of the modulating supply and the match network, where the tuning accounts for the power output of the modulating supply and the impedance seen by the modulating supply and characterize a waveform with a repetition period, T, containing at least one of information about the modulation of the plasma or a desired waveform of a piece of equipment connected to a plasma processing system to produce a waveform dataset. The controller is also configured to send the waveform dataset to at least one piece of equipment connected to the plasma processing system.
The word “exemplary” is used herein to mean “serving as an example, instance, or illustration.” Any embodiment described herein as “exemplary” is not necessarily to be construed as preferred or advantageous over other embodiments.
Preliminary note: the flowcharts and block diagrams in the following Figures illustrate the architecture, functionality, and operation of possible implementations of systems, methods and computer program products according to various embodiments of the present invention. In this regard, some blocks in these flowcharts or block diagrams may represent a module, segment, or portion of code, which comprises one or more executable instructions for implementing the specified logical function(s). It should also be noted that, in some alternative implementations, the functions noted in the block may occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently, or the blocks may sometimes be executed in the reverse order, depending upon the functionality involved. It will also be noted that each block of the block diagrams and/or flowchart illustrations, and combinations of blocks in the block diagrams and/or flowchart illustrations, can be implemented by special purpose hardware-based systems that perform the specified functions or acts, or combinations of special purpose hardware and computer instructions.
While the following disclosure generally refers to wafer plasma processing, implementations can comprise any substrate processing within a plasma chamber. In some instances, objects other than a substrate can be processed using the systems, methods, and apparatus herein disclosed. In other words, this disclosure applies to plasma processing of any object within a sub-atmospheric plasma processing chamber to effect a surface change, subsurface change, deposition or removal by physical or chemical means.
This disclosure may utilize plasma processing and substrate biasing techniques as disclosed in U.S. Pat. Nos. 9,287,092, 9,287,086, 9,435,029, 9,309,594, 9,767,988, 9,362,089, 9,105,447, 9,685,297, 9,210,790. The entirety of these applications is incorporated herein by reference. But it should be recognized that the reference in this specification to any prior publication (or information derived from it), or to any matter which is known, is not an acknowledgment or admission or any form of suggestion that the prior publication (or information derived from it) or known matter is conventional, routine, or forms part of the common general knowledge in the field of endeavor to which this specification relates.
For the purposes of this disclosure, source generators are those whose energy is primarily directed to generating and sustaining the plasma, while “bias supplies” are those whose energy is primarily directed to generating a surface potential for attracting ions and electrons from the plasma.
An example of the interrelations of the plasma processing equipment is the effect that modulating supplies (e.g., source generators 112, bias generators 108, and other modulating supplies discussed further herein) have on plasma properties (and control of the same). More specifically, modulating supplies can cause strong modulation of plasma properties such as the impedance presented by the plasma 102 to equipment of the plasma processing system 100. Plasma modulation can also cause aliasing of measurements of plasma properties. Additional details about the effects of modulation of plasma properties are discussed further herein.
Shown in
The bias generators 108 depicted in
The system controller 116 in the embodiment of
Referring next to
Aspects of the present disclosure address challenges faced in the prior art by recognizing that traditional and even cutting edge components of plasma processing systems are still limited by their autonomous design. For example, bias supplies, source generators and match networks are often independently operated. This disclosure describes systems, methods, and apparatuses for integrating communication, measurement, and control amongst components of a power delivery system (also known as a power generation and delivery system). Some advantages of this approach comprise the ability to provide accurate power regulation over a wide dynamic range, faster power stabilization during transients, and decreased reflected power, for both pulsed and continuous wave (CW) power.
The one or more sensors 611, 614, 618 monitor the power for the local controller 612. In particular, the first sensor 614 can monitor a power output of the source generator 112 as well as an impedance seen by the source generator 112. The local controller 612 analyzes measurements provided by the first sensor 614 (and optionally also the second sensor 618) in light of the power delivery requirements. It can determine operating parameters for the source generator 112 and match network 604 judged sufficient to meet the power delivery requirements, and can instruct (or relay instructions to) the source generator 112 and the match network 204 to adjust internal parameters of those components in order to meet the power delivery requirements.
In addition, in some implementations, the local controller may be configured to operate with the functionality of the system controller 116. It is also contemplated that the external controller 616 may be configured to operate with the functionality of the system controller 116. Moreover, the functionality of the system controller 116 may be implemented across one or more local controllers 612 and one or more system controllers 616. Thus, the aspects of integrating communication, measurement, and control amongst components of a power delivery system (described with reference to
This unified power delivery system 600, or the herein disclosed use of a local controller 612 in conjunction with the first sensor 614 (and optionally the second sensor 618 and third sensor 611), has a number of advantages. First, by unifying control and operation of various components of the power delivery system 600, novel power delivery methods are enabled, such as the ability to simultaneously tune the match network 604 and the source generator 112 or tune the match network 604 while pulsing or changing the waveform of the source generator 112 output. Second, this system and approach enables rapidly-adjustable, accurate, and consistent power delivery to the plasma 102. The speed of the power delivery system 600 is particularly useful in dynamic power applications (e.g., pulsed source generator 112 output).
The ability to more rapidly adjust power delivery can in part be attributed to avoidance of delays that traditional systems see when sensors must first measure frequency before measuring impedance. The local controller 612 may provide the first sensor 614 with operating parameters of the generator, such as frequency, so that the first sensor 614 need not measure frequency before beginning to sample for impedance. Earlier sampling means that impedance can be determined faster than in the art. The local controller 612 can also provide the first sensor 614 with an indication of the start of pulsing or a change in a power waveform, thus preventing the first sensor 614 from having to detect such a change before sampling begins. This also enables the first sensor 614 to begin measuring impedance sooner than sensors in the art.
The power delivery system 600 also improves the accuracy of power delivery. For example, when multiple sensors are used to measure power and impedance each sensor has an error function associated with that sensor resulting from calibrations that are made to each sensor. By using a single sensor 614 to measure power and impedance, only a single calibration is performed, and therefore less error is introduced.
In addition, having a greater number of sampling points can improve impedance measurements. In the art, sampling typically can only begin after a pulse or change in the generator waveform has been detected, whereas here, the local controller 612 may indicate to the first sensor 614 a start of a pulse or change in the source generator 112 waveform before or when the pulse or waveform change occurs. As such, the first sensor 614 can begin sampling earlier than is possible in the art, thus enabling more accurate impedance measurements.
Moreover, a measure of impedance depends on the frequency of the signal being measured; thus, errors in measuring frequency translate to errors in the impedance that is measured. Prior art impedance measurements are often made after a sensor in the match network measures frequency, thus introducing unnecessary error. Alternatively, when using a broadband sensor, error is introduced by analog variation in the broadband sensor as a function of frequency. By making the first sensor 614 aware of the frequency that the source generator 112 is producing, rather than requiring the first sensor 614 to measure the frequency at the match network, the first sensor 614 sees less error in impedance measurements than sensors in the prior art. Also, because the first sensor 614 does not have to measure frequency, it can take more samples, and a larger sample size improves accuracy.
In addition, because every component (e.g., source generator 112, first sensor 614, match network 604, optional second sensor 618) in a power delivery system is different, operating parameters of a power delivery system are preferably adjusted when different components are substituted. Traditional power supplies do not account for variations between components. In contrast, the local controller 612 is aware of the various components of the power delivery system 600 and adjusts its instructions to the source generator 112 and the match network 604 accordingly.
Component variations can be taken into account by identification of the components to the local controller 612. For instance, the bias supply 408, source generator 112, and/or match network 604 can identify themselves to the local controller 612 via brand, model, serial number or other identifying information. Also, they can provide operating characteristics such as status, set point (e.g., power level, frequency, etc), repetition period T, and configuration, to name a few. This can be done via the RF engine 613 and the impedance control system 615, respectively. The first and second sensors 614, 618 can also identify themselves to the local controller 612. Authentication may take place via an authentication algorithm. As such, in one embodiment, only specific types or brands of bias supply 408, source generator 112, and match network 604 are operable when connected via the transmission medium 608. The local controller 612 can also query the bias supply, source generator 112, the match network 604, and the sensors 614, 618 to determine their unit type, serial number, part number, or any other identifying information. With this knowledge, the local controller 612 can tailor instructions to the source generator 112, bias supply 408, and/or the match network 604 to account for variations in components, thus allowing the power delivery system 600 to provide more accurate and consistent power than is possible in the art.
The power delivery system 600 also improves the consistency (or quality) of power delivery because of the ability to measure both power and impedance. In part, consistency is improved via the greater accuracy described above (e.g., decreased error stack-up and earlier and more extensive sampling). Consistency is also improved, because, where the prior art had difficulty maintaining stability in multiple control loops of a power delivery system, the single controller 612 can control the multiple control loops and ensure stability and synchronization between the control loops.
A number of design aspects enable these advantages. For example, a single sensor 614 may be used to monitor both power output of the source generator 112 and an impedance seen by the source generator 112. The first sensor 614 can measure voltage, current, phase, impedance, and power at an output of the source generator 112. The first sensor 614 can be arranged at an output of the source generator 112. The first sensor 614 can measure impedance seen by the source generator 112 in addition to power from the source generator 112 because of the ability to remotely measure impedance, a feature not possible in the art. Remote impedance measurements look at impedance at a location physically remote from the first sensor 614 (or the calibration point), for instance at a location some physical distance along the first transmission medium 608 from the first sensor 614 (e.g., at an input of the match network 604).
Inaccuracies in traditional impedance measurements meant that remote monitoring of impedance was difficult if not impossible. The first sensor 614 may overcome these challenges for several reasons. For example, the first sensor 614 may have a more linear response with respect to increasing voltage standing wave ratio referenced to the calibration impedance than sensors in the art, and in addition, the first sensor 614 may more closely measure a phase of the source generator 112 output power.
Typically, sensors can be calibrated to operate optimally close to a center operating impedance (e.g., 50Ω), but due to their nonlinear response to impedance variations, as impedance moves away from the calibration impedance, sensor accuracy degrades rapidly. This inaccuracy for physically local measurements is amplified when making measurements over large physical distances. In contrast, in many implementations, the sensor 614 has a more linear response on the voltage standing wave ratio circle, which enables accurate impedance measurements at impedances far from the impedance calibration point and therefore at physically remote locations.
In addition, the first sensor 614 may be able to more closely measure a phase of the source generator 112 output than could prior generations of sensors. In particular, at high phase angles there is extreme sensitivity to phase angle measurement accuracy, and hence, high sensitivity in the resulting impedance and power measurements. Since the first sensor 614 can more accurately measure phase angle, it is better able to remotely measure impedance.
In an embodiment, the first sensor 614 is a directional coupler. A directional coupler can measure the scaled power of forward and reverse power as well as the phase difference between them. The directional coupler can then pass the scaled power and phase difference back to the local controller 612. Scaled power is a voltage that the directional coupler provides to a measurement system that is proportional to an output voltage of the source generator 112 operating into its nominal load condition (e.g., 50Ω).
The advantages described above are secondly enabled by unified control and monitoring of the power delivery system 600 through a single local controller 612. The local controller 612 can receive and analyze information from the source generator 112, the match network 604, the first sensor 614, and the optional second sensor 618. The local controller 612 may run one or more algorithms to analyze information received regarding the power delivery system 600 and determines procedures to take in order to ensure consistent power delivery to the plasma 102. The local controller 612 can also issue instructions for other components in the power delivery system 600, such as the source generator 112 and match network 604, to carry out certain actions and procedures.
Since the local controller 612 monitors all measurements and distributes all control signals and instructions, many of an operator's responsibilities are alleviated and the speed with which the source generator 112 and match network 604 adjust to power and impedance fluctuations is enhanced. Such a configuration also simplifies the hardware requirements of the power delivery system 600 since fewer leads and signal lines are required. By minimizing the number of leads and signal lines, the source generator 112 and match network 604 can be controlled via smaller and less complex software and firmware.
Because the local controller 612 manages operation of both the source generator 112 and the match network 604, simultaneous tuning of those components is possible. The local controller 612 can instruct an RF engine 613 of the source generator 112 to adjust an amplitude, carrier frequency, power frequency, pulse width, pulse duty cycle, or waveform of the source generator 112 power output. The local controller 612 can also instruct an impedance control system 615 of the match network 604 to adjust an impedance of the match network 604, for instance by having a motor drive board adjust variable capacitors of the match network 604.
Available tuning options can dictate how the local controller 612 manages the power delivery system 600. Where the source generator 112 frequency is fixed, the local controller 612 can pass instructions to the match network 604 to adjust impedance. Where the source generator 112 frequency is variable, the local controller 612 can (1) pass instructions to the match network 604 to alter the impedance that the source generator 112 sees, (2) pass instructions to the source generator 112 to alter the power output frequency, or (3) pass instructions to the match network 204 to alter the impedance that the source generator 112 sees and to the source generator 112 to alter its power output frequency. Since the source generator 112 frequency is more quickly adjusted than the impedance of the match network 604, instructing the source generator 112 to tune via frequency in addition to or instead of the match network 204 adjusting impedance, can be preferable where fast tuning is required. In other words, impedance matching can be performed via simultaneous tuning of the source generator 112 and the match network 604.
More consistent and accurate power can be delivered when the local controller 612 takes into account information provided by the optional second sensor 618. For instance, the optional second sensor 618 can provide data characterizing the power delivered to the plasma 102; thus, enabling the local controller 612 to more accurately and consistently provide tuning instructions to the source generator 112 and the match network 604. Measurements from the optional second sensor 618 can also be used for chamber matching—to improve consistent power delivery between chambers operating in parallel, but each with a different power delivery system. The local controller 612 can also use these measurements to improve wafer to wafer consistency, uniform processing across the wafer surface, end point detection (e.g., via monitoring light emissions from the plasma), and arc management. Although not illustrated, in some embodiments, the optional second sensor 618 can be arranged within the plasma chamber or in contact with the wafer.
In an embodiment, the power provided to the plasma 102 may be altered for various setpoints (e.g., from a first setpoint to a second setpoint). The match network 604 may not be able to adjust fast enough to maintain consistent power delivery to the plasma 102 when the source generator 112 switches between power setpoints. To overcome this challenge, a test run can be used to determine preferred set points for the match network 604 corresponding to each source generator 112 set point. The test run happens before a device, semiconductor, or any other object to be processed, is placed in the plasma chamber. The match network 604 and source generator 112 are then tuned for the various source generator 112 set points. Parameters that can be tuned comprise source generator 112 frequency, pulse width, and match network 604 impedance. This tuning is carried out without anything in the chamber so that slow tuning can take place without harming the device in the chamber. Parameters that are determined to be preferred for various source generator 112 set points can be stored in a memory. During actual plasma processing, the local controller 612 can issue instructions for the source generator 112 and the match network 604 to operate at the preferred parameters associated with the various setpoints. In this way, the match network 604 and source generator 112 do not have to tune during processing, but rather can quickly be set to the preferred parameters as determined in the test run.
The local controller 612 can also take into account the following non-limiting aspects characterizing the power delivery system 600: component efficiency characteristics, control algorithm parameters, variable capacitor position in the match network 604, diagnostics such as faults and warnings, component health metrics, component history logs, and component status requests.
The local controller 612 can also take into account non-electrical characteristics of the plasma 102 when managing operations of the source generator 112 and the match network 604. For instance, the local controller 612a can consider chamber pressure, gas chemistry in the chamber, ion energy of the plasma, light intensity of the plasma, spectral content of light emitted by the plasma, and plasma arcing to name a few non-limiting examples. In an embodiment, the optional second sensor 618 can monitor non-electrical characteristics of the plasma 102 or the plasma processing chamber (not illustrated), such as chamber pressure, gas chemistry in the chamber, ion energy of the plasma, light intensity of the plasma, spectral content of light emitted by the plasma, and plasma arcing, to name a few non-limiting examples.
As illustrated, the local controller 612 is the lone conduit for user interaction with the power delivery system 600. In one embodiment, a user can interface with an external controller 616, which is in communication with the local controller 612. User control of the source generator 112 and match network 604 is made via the local controller 612 by way of the external controller 616. However, one of skill in the art will recognize that user interaction with the power delivery system is not necessarily limited to the local controller 612.
The first sensor 614 can optionally be implemented along with an optional second sensor 618 (or load sensor). The optional second sensor 618 can be arranged at an output of the match network 604 (618a) or somewhere between and including the match network 204 and the plasma 102 (618b). The optional second sensor 618 is configured to characterize the power delivered to the plasma 102 and can measure voltage, current, phase, impedance, or power at the output of the match network 604 or anywhere between the match network 604 and the plasma 102. In an embodiment, the optional second sensor 618 can be coupled to the plasma 102 and can be arranged within the plasma processing chamber or coupled to a wafer during processing.
The local controller 612 can manage communications between the source generator 112 (in particular, the RF engine 613), the first sensor 614, the match network 604 (in particular, the impedance control system 615), and the optional second sensor 618, between itself and these components, and between these components and a user (e.g., via the external controller 616). These communications can be made via signal paths 625a or 625b that are internal to the source generator 112 and match network 604 respectively, or via signal path 626, which is generally external to the source generator 112 and the match network 204 (although can comprise portions that are internal to the source generator 112 and the match network 604).
In the illustrated embodiment, the signal path 626 is a bus (signals can travel in both directions and multiple signals can travel along the same path). However, in other embodiments, various components can have their own signal paths to the local controller 612. In other embodiments, there can be more than one bus-type signal path, and in yet other embodiments there can be a combination of bus-like and non-bus signal paths.
In some embodiments, the signal path 626 can be replaced by communications via the transmission medium 608. In other words, communications from the optional second sensor 618 to the local controller 612 can be modulated on the power signal transmitted between the source generator 112 and the match network 604. Communications between the various components illustrated can be via a serial communication protocol such as RS-485. Alternatively, one or more of these communications can be made via a wireless connection or via a wired or wireless network. For instance, the signal path 626 can be implemented as a local area network (LAN).
Referring to
In
The local controller 612, the RF engine 613, the first sensor 614, the impedance control system 615, and the optional second 618 and third 611 sensors can comprise any processor, such as, but not limited to, a central processing unit (CPU), a field programmable gate array (FPGA), a programmable logic device (PLD), a digital signal processor (DSP), or a combination of one or more CPU's, FPGA's, PLD's, and/or DSP's. Any of these components can comprise or be in communication with its own memory or a shared memory where the memory can be configured to store information such as configurations of the source generator 112, bias supply 408, and the match network 604 or trends in the power delivered to the plasma 102. The memory can be part of the local controller 612 or can be part of either the source generator 112 or the match network 604. In an embodiment, the memory can be a part of the RF engine 613 or the impedance control system 615.
The local controller 612 can comprise hardware, software, firmware, or a combination of these. For instance, the local controller 612 can comprise a processor, memory, and software running on the processor that is configured to analyze data from the first, second, and or third sensors 614, 618, 611 and determine how and when to instruct the source generator 112, match network 604, and/or bias supply 408 to adjust internal parameters of those components.
The RF engine 613, first sensor 614, impedance control system 615, and the optional second sensor 618 can each comprise logic such as a processor that receives instructions and transmits information to the local controller 612. Alternatively, the local controller 612 can handle all logic and control functions for each of the RF engine 613, first sensor 614, impedance control system 615, and the optional second sensor 618.
The power delivery requirements can be programmed into the local controller 612, can reside on a memory accessible by the local controller 612, or provided by a user (user power delivery requirements). In an embodiment, the first, second, and third sensors 614, 618, 611 are either V-I sensors (capable of measuring voltage, current, and phase) or directional couplers able to measure phase. In some implementations only one of the two second sensor 618 positions (618a or 618b) is implemented.
The transmission mediums 608, 610 can be implemented as high power cables (e.g., coaxial cables) or transmission lines. They can also be electrical connections between an adjacent or connected source generator 112 and match network 204. In an embodiment, the source generator 112 is connected to the match network 604 as part of a unified power delivery system 600 such that the transmission medium 608 is merely an internal electrical connection between two subcomponents of the power delivery system 600. In another embodiment, the source generator 112 and the match network 204 are so interconnected that a transmission medium 608 does not exist. In other words, the source generator 112 and match network 604 can be part of a single box, container, package, or unit. Such an embodiment could entail greater integration of sub-components (e.g., power sources, memory, and processors, to name a few) and communications between the source generator 112 and the match network 604. Some sub-components within the source generator 112 and match network 604 can be shared. For instance, the match network 604 can be made such an integral part of the source generator 112 that the source generator 112 and the match network 604 can both share a filter and/or final combiner of the source generator 112.
In an embodiment, a power control system can comprise the local controller 612, the first sensor 614, and optionally the second sensor 618. The power control system can be used to modify existing power delivery systems to enhance their power delivery capabilities as discussed above.
The sensors 714a, 714b, 714c can also relay identifications of themselves including information such as configuration and operating parameters to the local controller 712. The generators 702a, 702b, 702c and the match networks 704a, 704b, 704c can also identify themselves to the local controller 712, for instance via the RF engines 713a, 713b, 713c and the impedance control systems 715a, 715b, 715c, respectively.
The local controller 712 can manage communications between the generators 702a, 702b, 702c, the match networks 704a, 704b, 704c, and the sensors 714a, 714b, 714c. The local controller 712 is also configured to pass instructions to the generators 702a, 702b, 702c and the match networks 704a, 704b, 704c regarding how and when to adjust internal parameters. In this way the local controller 712 enables the generators 702a, 702b, 702c and the match networks 704a, 704b, 704c to operate in unison and in a fashion that takes into account variations between components as well as operation of other components. In some instances, this unified operation of the power delivery system 700 can also consider non-electrical factors such as plasma chamber gas chemistry or processing end point. In an embodiment, a frequency of the generators 702a, 702b, 702c can be tuned while also tuning the match networks 704a, 704b, 704c.
In this multi-generator embodiment, a particular challenge in the art is generating consistent power since each generator 702a, 702b, 702c sees the other generators 702a, 702b, 702c through the transmission mediums 710a, 710b, 710c or the plasma 102 (depending on the configuration). In other words, traditional multi-generator systems are plagued by cross talk interaction between the generators 702a, 702b, 702c. By enabling the generators 702a, 702b, 702c and match networks 704a, 704b, 704c to communicate with each other via the local controller 712 and to be controlled with the local controller 712 taking into account the operation of all of these components simultaneously, consistent and accurate power can be provided to the plasma 102.
In an embodiment, a user can interface with an external controller 716, which is in communication with the local controller 712. The external controller 716 can send and receive both instructions and data to and from the local controller 712. User control of the generators 702a, 702b, 702c and match networks 704a, 704b, 704c is made via the local controller 712 by way of the external controller 716.
While the local controller 712 is illustrated as being part of generator 702a, it can also be a part of generator 702b or generator 702c. Alternatively, all other locations within the power delivery system 700 can also be used.
Furthermore, the local controller 712 can communicate with an RF engine 713a, 713b, 713c of each generator 702a, 702b, 702c and an impedance control system 715a, 715b, 715c of each match network 704a, 704b, 704c. In particular, the local controller 712 can communicate with and pass instructions to these subcomponents. In this way, the local controller 712 can instruct the generators 702a, 702b, 702c and match networks 704a, 704b, 704c to alter operating parameters such as pulse frequency and variable capacitor position, to name two non-limiting examples.
The sensors 814a, 814b, 814c and the generators 802a, 802b, 802c can identify themselves to the local controller 812 via the RF engines and the impedance control systems 815a, 815b, 815c, respectively.
The power delivery system 800 can interface with users via an external controller 816. The external controller 816 can be in communication with the local controller 812 and send and receive both instructions and data to and from the local controller 812.
As in previous embodiments, the local controller 812 can be arranged as part of the generator 802a, as illustrated, or as part of any of the other components within the power delivery system 800 or adjacent to any of these components, but still within the power delivery system 800.
While impedance control systems 815a, 815b, 815c are illustrated for each match network 804a, 804b, 804c, one of skill in the art will recognize that these can either represent separate hardware (or software or firmware) components, or a single hardware component comprising a separate logical block for each match network 804a, 804b, 804c. In an alternative embodiment, a single impedance control system (not illustrated) may control operating parameters of all three match networks 804a, 804b, 804c.
In another embodiment, the sensors 814a, 814b, 814c can be replaced by a single sensor located between the match networks 804a, 804b, 804c and the plasma 102. The single sensor can measure voltage, current, phase, impedance, and power just as the three sensors 814a, 814b, 814c illustrated are configured to.
Although the generators 802a, 802b, 802c and the match networks 804a, 804b, 804c are illustrated as communicating with the local controller 812 via the same signal paths (in a bus configuration), in other embodiments, each component may have a separate signal path to the local controller. Alternatively, the generators 802a, 802b, 802c may have one signal path to the local controller 812 while the match networks 804a, 804b, 804c have another signal path to the local controller 812. The sensors 814a, 814b, 814c can also have their own signal path to the local controller 812.
The power delivery system 900 can interface with users via an external controller 916. The external controller 916 can be in communication with the local controller 912 and send and receive both instructions and data to and from the local controller 912.
Although the generators 902a, 902b, 902c and the match networks 904a, 904b, 904c are illustrated as communicating with the local controller 912 via the same signal paths (in a bus configuration), in other embodiments, each component may have a separate signal path to the local controller. Alternatively, the generators 902a, 902b, 902c may have one signal path to the local controller 912 while the match networks 904a, 904b, 904c have another signal path to the local controller 912.
While each external controller of
Although the multi-generator embodiments illustrated in
Referring next to
In this implementation, the voltages V1, V2, and V3 may be DC-sourced voltages. As shown, the first switch, S1, is disposed to switchably connect the first voltage, V1, to the output, Vout, through and inductive element and the second switch, S2, is disposed to switchably couple the second voltage, V2, to the output, Vout, through an inductive element. In this implementation the two switches connect to a common node, 1070, and a common inductive element, L1, is disposed between the common node and an output node, Vout. Other arrangements of the inductive elements are possible. For example, there may be two separate inductive elements with one inductive element connecting S1 to Vout and another connecting S2 to Vout. In another example one inductive element may connect S1 to S2 and another inductive element may connect either S1 or S2 to Vout.
While referring to
In this embodiment the third voltage, V3, is applied to the output node, Vout, through a second inductive element L2 to further decrease a level of the voltage at the output node along a fourth portion 1166 of the voltage waveform. As shown in
Thus, S1 momentarily connects and then disconnects the first voltage, V1, to the output, Vout, through the first inductive element L1, and after a period of time, S2 connects and then disconnects the second voltage (e.g., ground) to the output, Vout, through the first inductive element L1. The third voltage, V3, is coupled to the output, Vout, through a second inductive element L2. In this implementation, the first voltage, V1, may be higher than the third voltage V3, and the momentary connection and disconnection of the first voltage, V1, to the output Vout causes the voltage of the output, Vout, to increase along the first portion 1160 of the voltage waveform to a first voltage level, Va, and the first voltage level, Va, is sustained along the second portion of the waveform 1162. The first voltage level Va may be above the first voltage, V1, and the second voltage, V2, (e.g., ground) may be less than the first voltage level, Va. The momentary connecting and then disconnecting of the second voltage, V2, causes the voltage of the output, Vout, to decrease at the third portion 1164 to the second voltage level Vb that is below the second voltage, V2 (e.g., ground).
As an example, V1 may be −2000 VDC; V2 may be ground; V3 may be −5000 VDC; V0 may be −7000 VDC; Vb may be −3000 VDC; and Va may be 3000 VDC. But these voltages are merely exemplary to provide context to relative magnitude and polarities of the voltages described with reference to
Referring next to
In some embodiments, as shown in
The bias supply 1008 depicted in
One modulation scheme comprises modulating the third portion 1164 of the voltage waveform to effectuate desired ion energies of ions impinging upon the workpiece 103 in the plasma chamber 101. As an example, the bias supply 408, 508, 1008 may alternate a magnitude of the third portion 1164 of the voltage waveform between two or more levels to effectuate an alternating surface potential of the workpiece 103 in the plasma between two or more distinct levels. As another example, a slope of the fourth portion 1166 of the voltage waveform may be adjusted to change a level of current that is provided to an electrode 104 (to compensate for ion current that impinges upon the workpiece 103) to achieve a desired spread of ion energies (e.g., around a center ion energy). Successful use of bias supplies 408, 508, 1008 as a bias generator in many plasma processing systems requires careful system design.
System Synchronization and Communication
Modulating supplies such as the source generators 112, bias generators 108, remote plasma sources 205, and bias supplies 408, 508, 1008 can cause strong modulation of plasma properties. Examples of plasma properties, without limitation, comprise an impedance presented by the plasma, plasma density, sheath capacitance, and a surface potential of the workpiece 103 in the plasma 102. As discussed above, the modulation of the voltage and/or current applied by the bias supplies 408, 508, 1008 is one potential cause of modulating plasma properties.
Source generators 112 may also modulate plasma properties by modulating electromagnetic fields impacting the plasma 102. In particular, source generators 112 may pulse the power (e.g., RF power) that is applied by a source generator 112. Moreover, a magnitude of voltage of the power applied by a source generator 112 may be changed. The addition of one or more additional source generators 112 adds additional complexity. And it is also contemplated that one or more bias supplies 408, 508, 1008 may modulate the voltage (Vout shown in
As discussed above, a remote plasma source 205 may replace, or augment, a source generator 112. But remote plasma sources 205 may also be modulating supplies that are configured to modulate plasma properties by modulating properties of gases in the plasma chamber 101.
In addition to control challenges, one modulating supply may affect (e.g., in an adverse manner) operation of another modulating supply. As a specific, non-limiting, example, the bias supplies 408, 508, 1008 may impart power at a level that results in plasma modulation, which in turn, cause undesirable changes in the load impedance presented to a source generator 112. In addition, strong plasma modulation can also cause aliasing of measurements of plasma properties. The aliasing may prevent accurate measurements of forward and reflected power; thus, preventing an operator from detecting damaging power levels and/or prevent proper control over at least one of the source matching network 113 or the bias matching network 110.
Synchronization of equipment connected to the plasma system may mitigate the adverse effects of plasma modulation (e.g., damaging power and aliasing), and as a consequence, synchronization is highly desired. But the complex, time varying, aspects of plasma modulation (e.g., resulting from potentially many modulating supplies) can make synchronization difficult.
Referring to
The depicted components of the synchronization controller 1416 may be realized by hardware, firmware, software and hardware or combinations thereof. The functional components of the synchronization controller 1416 may be distributed about the plasma processing system and duplicated in equipment that is connected to the plasma processing system. And as discussed further herein, the synchronization controller 1416 may be implemented as a master device or slave device.
The user interface 1450 enables an operator to interact with the plasma processing system so that the operator may control aspects of the synchronization and the operator may receive information about conditions of the equipment and the plasma chamber 101. The user interface 1450 may be realized, for example, by one or more of a touch screen, pointing device (e.g., mouse), display, and keyboard.
The waveform-characterization module 1452 is generally configured to generate a waveform dataset that characterizes a waveform (e.g., a waveform of a modulation of the plasma or a waveform output (or desired to be output) by equipment) of the plasma processing system. The waveform-repetition module 1454 is configured to determine a repetition period, T, for a piece of equipment connected to the plasma system, and the waveform-communication module 1456 is configured to communicate the waveform dataset to at least one of the piece of equipment or another piece of equipment connected to the plasma processing system. The synchronization module 1458 is configured to send a synchronization pulse with a synchronization-pulse-repetition-period (which is an integer multiple of T) to one or more pieces of equipment connected to the plasma system.
While referring to
As shown in
Referring briefly to
Referring again to
Although
One or more of the source generators 112 may synchronize a property of the output of the source generator(s) 112 with the characterized waveform (that has the repetition period T). The property of the output of the source generator(s) 112 may be at least one of voltage, current, power, frequency, or generator source impedance. And the output of the source generator(s) 112, for example, may comprise (within one repetition period) pulsed power followed by continuous wave power. And the waveform dataset may comprise a time series of values indicating one or more aspects of power (e.g., voltage, current, phase, etc.) for the repetition period. The source generator 112 may synchronize pulsing with a particular waveform applied by the bias supply 408, 508, 1008 that may, for example, modulate a magnitude of the negative voltage swing (the third portion 1164) in a different manner while the source generator 112 is pulsing as compared to when the source generator 112 is operating in a continuous-wave mode of operation. This use case is only an example, and various other types of processing steps may prompt synchronization among pieces of plasma processing equipment.
In addition, the source generator 112 may advance or delay changes in a property of the output of the source generator 112 with respect to changes in the characterized waveform with a repetition period T. As discussed above, the characterized waveform in some implementations may characterize the modulation of the plasma properties. The characterized waveform may also characterize a waveform of the source generator 112 or another modulating supply (depending upon how the source generator 112 is configured to operate).
The equipment coupled to the plasma processing system (and synchronized as disclosed herein) is certainly not limited to modulating supplies. For example, the at least one piece of equipment that the dataset is sent to (Block 1504) may comprise equipment that is configured to measure properties of the plasma processing system. For example, the measurements may comprise at least one of a measurement of plasma properties, properties of power delivered to the plasma system, or properties of gas delivered to the plasma system. By way of further example, the equipment that is configured to measure properties may comprise one or more of the source measurement and diagnostics system 114 and the bias measurement and diagnostics system 111. Those of ordinary skill in the art recognize that the source measurement and diagnostics system 114 and the bias measurement and diagnostics system 111 may comprise one or more sensors (e.g., directional couplers and/or VI sensors) in connection with hardware to sample and analyze properties of power delivered to the plasma system (which may be used to measure plasma impedance as a plasma property). In the context of a plasma processing system utilizing the remote plasma source 205, properties of the gas delivered to the plasma processing system may be measured (e.g., utilizing optical or other measurement techniques). As discussed herein, plasma modulation can cause aliasing of measurements of plasma properties, so synchronizing measurements to within time windows to avoid misleading transient values (or during time windows where modulation is at a local minima) is beneficial.
Other equipment that may be synchronized comprises matching networks. For example, the impedance matching network may synchronize measurements indicative of impedance with the characterized waveform. By synchronizing the measurements with time windows where measurements are not misleading (e.g., when there not large changes in power levels applied to the plasma), matching may be improved. Examples of impedance matching networks comprise the source matching network 113 and the bias matching network 110.
The waveform dataset 1605 may be sent (Block 1504) via digital communication link to one or more of the pieces of equipment coupled to the plasma processing system. The communication link may comprise the system control bus 117, which may be realized by known digital links (for example, without limitation, ethernet). In many implementations, the waveform dataset 1605 may be communicated once, and then the synchronization pulse prompts each piece of equipment to operate in response to the waveform dataset in a repeating manner.
The synchronization signal may be sent (Block 1506) via the near-real-time communication link 119 to equipment coupled to the plasma processing system. As an example, the near-real-time link may be an analog communication link to provide a single analog output with an identifiable fundamental pulse (also referred to as a “tick”)), and if required, update pulses (also referred to as “update-ticks”) are sent in between the fundamental pulses. In addition, the synchronization signal may comprise an indication of a start of the synchronization signal repetition period as well as at least one indication that a period of time since the start of the synchronization signal repetition period has elapsed.
The start of the synchronization signal repetition period may be indicated by a pulse of a first duration and the indication that a period of time since the start of the synchronization signal repetition period has elapsed may be indicated by a pulse of a second duration that is different from the first duration. For example, the first duration may be longer than the second duration or vice versa.
In some implementations, the synchronization signal comprises an indication of the start of the synchronization signal repetition period where the start of the synchronization signal repetition period is further modified at least once to indicate a time of day or to indicate that a new waveform is taking effect.
Referring to
As shown in
By utilizing precision oscillators, synchronization can be maintained with good precision. For example, using 50 ppm oscillators in all equipment, a change in a waveform can be predicted with better than 50 ns accuracy for a fundamental pulse repetition rate as low as 10 kHz. For longer pulse repetition periods one can add additional synchronization pulses every 100 μs to maintain synchronization within 50 ns accuracy.
Synchronization between a source generator 112 and bias supply 408, 508, 1008 may entail lowering voltage or cutting off voltage at the end of a given bias supply pulse. For example, it may be desirable to avoid ending an RF pulse in the midst of a bias supply pulse. Alternatively, pulsing or periodic reductions in voltage, may start and end at the same point/phase in the bias supply pulse, but for different pulses. In other words, it may be desirable to set the pulse on length equal to an integer number of bias supply pulses, whether or not the envelope pulse is in phase with a start or end to an individual bias supply pulse.
The previously described embodiments provide novel and nonobvious systems and methods to create laminate films, among other use cases. Examples such as diamond like carbon, which when deposited with plasma processing has very high stresses that can result in peeling of the film, can now be processed to incorporate low stress graphite or amorphous carbon layers so that the overall film still exhibits diamond like carbon properties but at lower stresses. In some films, it may be desirable to deposit the film in one period followed by a period where the plasma chemistry is modified by pulsing control and a high bias is applied to densify the film. Aspects described herein enable production of nano-level “Bragg” structures consisting of alternative layers with different optical properties produced by combining pulsing and bias voltage control in each respective period as illustrated earlier. Said another way, a first chemistry can be achieved for a first period of time to deposit a first layer, then a second chemistry can be achieved for a second period of time to deposit a second layer. This can be repeated numerous times to achieve a “Bragg” structure. The different chemistries can be achieved by variations in one or more of: bias voltage; duty cycle of two or more bias voltages; alterations in the timing of bias voltage, source pulsing; duty cycle of source pulsing; source voltage; and source voltage and pulsing in combination.
The methods described in connection with the embodiments disclosed herein may be embodied directly in hardware, in processor-executable code encoded in a non-transitory tangible processor readable storage medium, or in a combination of the two. Referring to
This display portion 2012 generally operates to provide a user interface for a user, and in several implementations, the display is realized by a touchscreen display. In general, the nonvolatile memory 2020 is non-transitory memory that functions to store (e.g., persistently store) data and processor-executable code (including executable code that is associated with effectuating the methods described herein). In some embodiments for example, the nonvolatile memory 2020 comprises bootloader code, operating system code, file system code, and non-transitory processor-executable code to facilitate the execution of the methods described herein (e.g., the methods described with reference to of
In many implementations, the nonvolatile memory 2020 is realized by flash memory (e.g., NAND or ONENAND memory), but it is contemplated that other memory types may also be utilized. Although it may be possible to execute the code from the nonvolatile memory 2020, the executable code in the nonvolatile memory is typically loaded into RAM 2024 and executed by one or more of the N processing components in the processing portion 2026.
The N processing components in connection with RAM 2024 generally operate to execute the instructions stored in nonvolatile memory 2020 to enable control and synchronization among equipment coupled to a plasma processing system. For example, non-transitory, processor-executable code to effectuate methods of synchronously pulsing and changing voltages of the source generators and bias supplies may be persistently stored in nonvolatile memory 2020 and executed by the N processing components in connection with RAM 2024. As one of ordinarily skill in the art will appreciate, the processing portion 2026 may comprise a video processor, digital signal processor (DSP), micro-controller, graphics processing unit (GPU), or other hardware processing components or combinations of hardware and software processing components (e.g., an FPGA or an FPGA including digital logic processing portions).
In addition, or in the alternative, the processing portion 2026 may be configured to effectuate one or more aspects of the methodologies described herein (e.g., methods of synchronously operating equipment of a plasma processing equipment). For example, non-transitory processor-readable instructions may be stored in the nonvolatile memory 2020 or in RAM 2024 and when executed on the processing portion 2026, cause the processing portion 2026 to perform methods of controlling modulating supplies and other equipment. Alternatively, non-transitory FPGA-configuration-instructions may be persistently stored in nonvolatile memory 2020 and accessed by the processing portion 2026 (e.g., during boot up) to configure the hardware-configurable portions of the processing portion 2026 to effectuate the functions disclosed herein (including the functions of the synchronization controller 1416.
The input component 2030 operates to receive signals (e.g., the synchronization signals or datasets with waveform characterization data) that are indicative of one or more aspects of the synchronized control between equipment of a plasma processing system. The signals received at the input component may comprise, for example, the power control and data signals, or control signals from a user interface. Signals received at the input 2030 may also comprise signals indicative of current, voltage and/or phase received from a V-I sensor or direction coupler, for example. The output component generally operates to provide one or more analog or digital signals to effectuate an operational aspect of control and synchronization between the equipment. For example, the output portion 2032 may out the synchronization signal and/or waveform datasets.
The depicted transceiver component 2028 comprises N transceiver chains, which may be used for communicating with external devices via wireless or wireline networks. Each of the N transceiver chains may represent a transceiver associated with a particular communication scheme (e.g., WiFi, Ethernet, Profibus, etc.). The transceiver component may enable connections with the control bus 117, communication link 119, and/or signal paths 625, 626.
As will be appreciated by one skilled in the art, aspects of the present invention may be embodied as a system, method or computer program product. Accordingly, aspects of the present invention may take the form of an entirely hardware embodiment, an entirely software embodiment (including firmware, resident software, micro-code, etc.) or an embodiment combining software and hardware aspects that may all generally be referred to herein as a “circuit,” “module” or “system.” Furthermore, aspects of the present invention may take the form of a computer program product embodied in one or more computer readable medium(s) having computer readable program code embodied thereon.
As used herein, the recitation of “at least one of A, B or C” is intended to mean “either A, B, C or any combination of A, B and C.” The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present disclosure. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the disclosure. Thus, the present disclosure is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
The present application for Patent is a Continuation-in-Part of patent application Ser. No. 17/031,027 entitled APPLICATION OF MODULATING SUPPLIES IN A PLASMA PROCESSING SYSTEM, filed Sep. 24, 2020, which is a Continuation of patent application Ser. No. 16/194,125 entitled “APPLICATION OF MODULATING SUPPLIES IN A PLASMA PROCESSING SYSTEM” filed Nov. 16, 2018 and issued as U.S. Pat. No. 10,811,227 on Oct. 20, 2020, which claims priority to Provisional Application No. 62/588,255 entitled “IMPROVED APPLICATION OF AN EV SOURCE IN PLASMA PROCESSING EQUIPMENT” filed Nov. 17, 2017, and assigned to the assignee hereof and hereby expressly incorporated by reference herein.
Number | Name | Date | Kind |
---|---|---|---|
4622094 | Otsubo | Nov 1986 | A |
4693805 | Quazi | Sep 1987 | A |
4891118 | Ooiwa et al. | Jan 1990 | A |
4963239 | Shimamura et al. | Oct 1990 | A |
5057185 | Thomas, III et al. | Oct 1991 | A |
5156703 | Oechsner | Oct 1992 | A |
5160397 | Doki et al. | Nov 1992 | A |
5242561 | Sato | Sep 1993 | A |
5410691 | Taylor | Apr 1995 | A |
5415718 | Ohmi et al. | May 1995 | A |
5427669 | Drummond | Jun 1995 | A |
5487785 | Horike et al. | Jan 1996 | A |
5517084 | Leung | May 1996 | A |
5535906 | Drummond | Jul 1996 | A |
5767628 | Keller et al. | Jun 1998 | A |
5770972 | Freuler et al. | Jun 1998 | A |
5859428 | Fruchtman | Jan 1999 | A |
5907221 | Sato et al. | May 1999 | A |
5936481 | Fujii | Aug 1999 | A |
5983828 | Savas | Nov 1999 | A |
6030667 | Nakagawa et al. | Feb 2000 | A |
6051114 | Yao et al. | Apr 2000 | A |
6110287 | Arai et al. | Aug 2000 | A |
6129806 | Kaji et al. | Oct 2000 | A |
6156667 | Jewett | Dec 2000 | A |
6162709 | Raoux et al. | Dec 2000 | A |
6201208 | Wendt et al. | Mar 2001 | B1 |
6273022 | Pu et al. | Aug 2001 | B1 |
6288493 | Lee et al. | Sep 2001 | B1 |
6291938 | Jewett et al. | Sep 2001 | B1 |
6313583 | Arita et al. | Nov 2001 | B1 |
6326584 | Jewett et al. | Dec 2001 | B1 |
6392210 | Jewett et al. | May 2002 | B1 |
6463875 | Chen et al. | Oct 2002 | B1 |
6478924 | Shamouilian et al. | Nov 2002 | B1 |
6507155 | Barnes et al. | Jan 2003 | B1 |
6544895 | Donohoe | Apr 2003 | B1 |
6568346 | Pu et al. | May 2003 | B2 |
6583572 | Veltrop et al. | Jun 2003 | B2 |
6617794 | Barnes et al. | Sep 2003 | B2 |
6621674 | Zahringer et al. | Sep 2003 | B1 |
6646385 | Howald et al. | Nov 2003 | B2 |
6685798 | Howald et al. | Feb 2004 | B1 |
6694915 | Howald et al. | Feb 2004 | B1 |
6707051 | Shun'ko | Mar 2004 | B2 |
6714033 | Makhratchev et al. | Mar 2004 | B1 |
6724148 | Makhratchev et al. | Mar 2004 | B1 |
6756737 | Doi et al. | Jun 2004 | B2 |
6777037 | Sumiya et al. | Aug 2004 | B2 |
6794301 | Savas | Sep 2004 | B2 |
6819096 | Gonzalez et al. | Nov 2004 | B2 |
6822396 | Gonzalez et al. | Nov 2004 | B2 |
6863018 | Koizumi et al. | Mar 2005 | B2 |
6872289 | Mizuno et al. | Mar 2005 | B2 |
6885153 | Quon | Apr 2005 | B2 |
6885453 | Kaufmann | Apr 2005 | B2 |
6893533 | Holland et al. | May 2005 | B2 |
6913938 | Shanmugasundram et al. | Jul 2005 | B2 |
6920312 | Benjamin | Jul 2005 | B1 |
6924455 | Chen et al. | Aug 2005 | B1 |
6927358 | Gonzalez et al. | Aug 2005 | B2 |
6946063 | Gonzalez et al. | Sep 2005 | B1 |
6984198 | Krishnamurthy et al. | Jan 2006 | B2 |
7005845 | Gonzalez et al. | Feb 2006 | B1 |
7019253 | Johnson et al. | Mar 2006 | B2 |
7046524 | Hoffman et al. | May 2006 | B2 |
7059267 | Hedberg et al. | Jun 2006 | B2 |
7096819 | Chen et al. | Aug 2006 | B2 |
7132618 | Hoffman et al. | Nov 2006 | B2 |
7201936 | Schwarm et al. | Apr 2007 | B2 |
7245084 | Gonzalez et al. | Jul 2007 | B1 |
7253117 | Donohoe | Aug 2007 | B2 |
7297637 | Hedberg et al. | Nov 2007 | B2 |
7373899 | Sumiya et al. | May 2008 | B2 |
7468494 | Gonzalez et al. | Dec 2008 | B2 |
7520956 | Samukawa et al. | Apr 2009 | B2 |
7528386 | Ruzic et al. | May 2009 | B2 |
7645357 | Paterson et al. | Jan 2010 | B2 |
7725208 | Shanmugasundram et al. | May 2010 | B2 |
7737702 | Pipitone | Jun 2010 | B2 |
7764140 | Nagarkatti et al. | Jul 2010 | B2 |
7777179 | Chen et al. | Aug 2010 | B2 |
7783375 | Shanmugasundram et al. | Aug 2010 | B2 |
7811939 | Kushibiki et al. | Oct 2010 | B2 |
7847247 | Denpoh | Dec 2010 | B2 |
8040068 | Coumou et al. | Oct 2011 | B2 |
8140292 | Wendt | Mar 2012 | B2 |
8169595 | Schriever et al. | May 2012 | B2 |
8264154 | Banner et al. | Sep 2012 | B2 |
8319436 | Carter et al. | Nov 2012 | B2 |
8404598 | Liao et al. | Mar 2013 | B2 |
8409398 | Brcka | Apr 2013 | B2 |
8475673 | Edelberg | Jul 2013 | B2 |
8641916 | Yatsuda et al. | Feb 2014 | B2 |
8698107 | Godet et al. | Apr 2014 | B2 |
8742669 | Carter et al. | Jun 2014 | B2 |
8900402 | Holland et al. | Dec 2014 | B2 |
9088267 | Blackburn et al. | Jul 2015 | B2 |
9105447 | Brouk et al. | Aug 2015 | B2 |
9114666 | Valcore, Jr. et al. | Aug 2015 | B2 |
9123509 | Papasouliotis et al. | Sep 2015 | B2 |
9177756 | Holland et al. | Nov 2015 | B2 |
9210790 | Hoffman et al. | Dec 2015 | B2 |
9283635 | Peters | Mar 2016 | B2 |
9287086 | Brouk et al. | Mar 2016 | B2 |
9287092 | Brouk et al. | Mar 2016 | B2 |
9305803 | Morimoto et al. | Apr 2016 | B2 |
9309594 | Hoffman et al. | Apr 2016 | B2 |
9362089 | Brouk | Jun 2016 | B2 |
9378931 | Kwon et al. | Jun 2016 | B2 |
9390893 | Valcore, Jr. et al. | Jul 2016 | B2 |
9425029 | Muto et al. | Aug 2016 | B2 |
9478397 | Blackburn et al. | Oct 2016 | B2 |
9536749 | Marakhtanov et al. | Jan 2017 | B2 |
9593421 | Baek et al. | Mar 2017 | B2 |
9595424 | Marakhtanov et al. | Mar 2017 | B2 |
9604877 | Veerasamy et al. | Mar 2017 | B2 |
9685297 | Carter et al. | Jun 2017 | B2 |
9754767 | Kawasaki | Sep 2017 | B2 |
9754768 | Yamada et al. | Sep 2017 | B2 |
9761414 | Marakhtanov et al. | Sep 2017 | B2 |
9761419 | Nagami | Sep 2017 | B2 |
9767988 | Brouk et al. | Sep 2017 | B2 |
9788405 | Kawasaki et al. | Oct 2017 | B2 |
9818584 | Miller et al. | Nov 2017 | B2 |
9872373 | Shimizu et al. | Jan 2018 | B1 |
9892888 | Baek et al. | Feb 2018 | B2 |
10607813 | Fairbairn et al. | Mar 2020 | B2 |
10707055 | Shaw et al. | Jul 2020 | B2 |
10791617 | Dorf et al. | Sep 2020 | B2 |
10811227 | Van Zyl et al. | Oct 2020 | B2 |
10811228 | Van Zyl et al. | Oct 2020 | B2 |
10811229 | Van Zyl et al. | Oct 2020 | B2 |
10896807 | Fairbairn et al. | Jan 2021 | B2 |
11011349 | Brouk et al. | May 2021 | B2 |
11189454 | Carter et al. | Nov 2021 | B2 |
11264209 | Van Zyl et al. | Mar 2022 | B2 |
20010014540 | Shan et al. | Aug 2001 | A1 |
20020038631 | Sumiya et al. | Apr 2002 | A1 |
20020115301 | Savas | Aug 2002 | A1 |
20020144786 | Chiang et al. | Oct 2002 | A1 |
20030033116 | Brcka et al. | Feb 2003 | A1 |
20040007326 | Roche et al. | Jan 2004 | A1 |
20040094402 | Gopalraja et al. | May 2004 | A1 |
20050090118 | Shannon et al. | Apr 2005 | A1 |
20050260354 | Singh et al. | Nov 2005 | A1 |
20060088655 | Collins et al. | Apr 2006 | A1 |
20060130971 | Chang et al. | Jun 2006 | A1 |
20060171093 | Ishimura et al. | Aug 2006 | A1 |
20060226786 | Lin et al. | Oct 2006 | A1 |
20070121267 | Kotani et al. | May 2007 | A1 |
20070139112 | Bocock | Jun 2007 | A1 |
20070139122 | Nagarkatti et al. | Jun 2007 | A1 |
20070186856 | Yasui et al. | Aug 2007 | A1 |
20070193975 | Wilson | Aug 2007 | A1 |
20070246163 | Paterson et al. | Oct 2007 | A1 |
20080135400 | Kadlec et al. | Jun 2008 | A1 |
20090077150 | Wendt | Mar 2009 | A1 |
20090200494 | Hatem et al. | Aug 2009 | A1 |
20090255800 | Koshimizu | Oct 2009 | A1 |
20090298287 | Shannon et al. | Dec 2009 | A1 |
20100072172 | Ui et al. | Mar 2010 | A1 |
20100154994 | Fischer et al. | Jun 2010 | A1 |
20100208409 | Bluck et al. | Aug 2010 | A1 |
20100276273 | Heckman et al. | Nov 2010 | A1 |
20100283395 | Van Zyl | Nov 2010 | A1 |
20100296977 | Hancock | Nov 2010 | A1 |
20110031217 | Himori | Feb 2011 | A1 |
20110089023 | Tanaka et al. | Apr 2011 | A1 |
20110095689 | Gilbert | Apr 2011 | A1 |
20110220491 | Hilliard | Sep 2011 | A1 |
20110223750 | Hayash et al. | Sep 2011 | A1 |
20110226617 | Hofmann et al. | Sep 2011 | A1 |
20110248634 | Heil et al. | Oct 2011 | A1 |
20110259851 | Brouk et al. | Oct 2011 | A1 |
20120052599 | Brouk et al. | Mar 2012 | A1 |
20120052689 | Tokashiki | Mar 2012 | A1 |
20120187844 | Hoffman et al. | Jul 2012 | A1 |
20120217221 | Hoffman et al. | Aug 2012 | A1 |
20120318456 | Brouk et al. | Dec 2012 | A1 |
20120319584 | Brouk et al. | Dec 2012 | A1 |
20130122711 | Marakhtanov et al. | May 2013 | A1 |
20130320853 | Carter | Dec 2013 | A1 |
20140061156 | Brouk | Mar 2014 | A1 |
20140062303 | Hoffman et al. | Mar 2014 | A1 |
20140062495 | Carter et al. | Mar 2014 | A1 |
20140148016 | Kanazawa et al. | May 2014 | A1 |
20140173158 | Valcore | Jun 2014 | A1 |
20140265910 | Kobayashi et al. | Sep 2014 | A1 |
20140302682 | Muto et al. | Oct 2014 | A1 |
20140305905 | Yamada et al. | Oct 2014 | A1 |
20150076112 | Sriraman et al. | Mar 2015 | A1 |
20150126037 | Chen et al. | May 2015 | A1 |
20150170886 | Morimoto | Jun 2015 | A1 |
20150270104 | Van Zyl | Sep 2015 | A1 |
20150315698 | Chistyakov | Nov 2015 | A1 |
20150325413 | Km et al. | Nov 2015 | A1 |
20150371827 | Godet et al. | Dec 2015 | A1 |
20160020108 | Ranjan et al. | Jan 2016 | A1 |
20160027616 | Ramaswamy et al. | Jan 2016 | A1 |
20160053017 | Orentas et al. | Feb 2016 | A1 |
20160056017 | Kim et al. | Feb 2016 | A1 |
20160064247 | Tomura et al. | Mar 2016 | A1 |
20160079037 | Hirano et al. | Mar 2016 | A1 |
20160126068 | Lee et al. | May 2016 | A1 |
20160126069 | Kwon et al. | May 2016 | A1 |
20160240353 | Nagami | Aug 2016 | A1 |
20160351375 | Valcore, Jr. et al. | Dec 2016 | A1 |
20170018411 | Sriraman et al. | Jan 2017 | A1 |
20170029941 | Allen et al. | Feb 2017 | A1 |
20170053820 | Bosch et al. | Feb 2017 | A1 |
20170099723 | Nagami et al. | Apr 2017 | A1 |
20170330731 | Van Zyl | Nov 2017 | A1 |
20180047573 | Tanaka et al. | Feb 2018 | A1 |
20180342903 | Luu et al. | Nov 2018 | A1 |
20190066979 | Shoeb et al. | Feb 2019 | A1 |
20190157040 | Fairbairn et al. | May 2019 | A1 |
20190157041 | Zyl et al. | May 2019 | A1 |
20190157042 | Van Zyl et al. | May 2019 | A1 |
20190157043 | Shaw | May 2019 | A1 |
20190172685 | Van Zyl et al. | Jun 2019 | A1 |
20190180982 | Brouk et al. | Jun 2019 | A1 |
20200090905 | Brouk et al. | Mar 2020 | A1 |
20200203128 | Fairbairn et al. | Jun 2020 | A1 |
20210005428 | Shaw et al. | Jan 2021 | A1 |
20210013006 | Nguyen et al. | Jan 2021 | A1 |
20210074513 | Van Zyl et al. | Mar 2021 | A1 |
20210134562 | Fairbairn et al. | May 2021 | A1 |
20210202209 | Van Zyl et al. | Jul 2021 | A1 |
20210241996 | Carter et al. | Aug 2021 | A1 |
20210327679 | Carter et al. | Oct 2021 | A1 |
20210351007 | Carter | Nov 2021 | A1 |
Number | Date | Country |
---|---|---|
1451172 | Oct 2003 | CN |
1839459 | Sep 2006 | CN |
101685772 | Mar 2010 | CN |
201465987 | May 2010 | CN |
101835334 | Sep 2010 | CN |
101978461 | Feb 2011 | CN |
101990353 | Mar 2011 | CN |
102217045 | Oct 2011 | CN |
102405512 | Apr 2012 | CN |
105097404 | Nov 2015 | CN |
106920729 | Jul 2017 | CN |
0 383 570 | Aug 1990 | EP |
1 978 542 | Oct 2008 | EP |
1 129 481 | Feb 2012 | EP |
2 382 459 | May 2003 | GB |
2 400 613 | Oct 2004 | GB |
60-126832 | Jul 1985 | JP |
S62-125626 | Jun 1987 | JP |
02141572 | May 1990 | JP |
H04-193329 | Jul 1992 | JP |
H06243992 | Sep 1994 | JP |
H09-293600 | Nov 1997 | JP |
11087097 | Mar 1999 | JP |
2001-237234 | Aug 2001 | JP |
2001-525601 | Dec 2001 | JP |
2002-050611 | Feb 2002 | JP |
2003-133404 | May 2003 | JP |
200485446 | Mar 2004 | JP |
2004-193564 | Jul 2004 | JP |
2005534187 | Nov 2005 | JP |
2006286254 | Oct 2006 | JP |
2007336148 | Dec 2007 | JP |
2008501224 | Jan 2008 | JP |
2008157906 | Jul 2008 | JP |
2009-071133 | Apr 2009 | JP |
2009514176 | Apr 2009 | JP |
2009-540569 | Nov 2009 | JP |
2010-103465 | May 2010 | JP |
2010219026 | Sep 2010 | JP |
2010-238960 | Oct 2010 | JP |
2011519115 | Jun 2011 | JP |
2011-222292 | Nov 2011 | JP |
2012-104382 | May 2012 | JP |
2015115564 | Jun 2015 | JP |
2005527078 | Sep 2015 | JP |
2016-500132 | Jan 2016 | JP |
6141478 | Jun 2017 | JP |
10-2012-0019428 | Mar 2012 | KR |
200811905 | Mar 2008 | TW |
200915375 | Apr 2009 | TW |
201142068 | Dec 2011 | TW |
201621974 | Jun 2016 | TW |
201637069 | Oct 2016 | TW |
9109150 | Jun 1991 | WO |
0215222 | Feb 2002 | WO |
2004012220 | Feb 2004 | WO |
2010013476 | Feb 2010 | WO |
2010080421 | Jul 2010 | WO |
2010126893 | Nov 2010 | WO |
2012030500 | Mar 2012 | WO |
2012103101 | Aug 2012 | WO |
2013016619 | Jan 2013 | WO |
2014035889 | Mar 2014 | WO |
2017126184 | Jul 2017 | WO |
Entry |
---|
Fujimoto, Kayoko, “Notice for Reasons of Rejection Regarding Japanese Patent Application No. 2020-081092”, Apr. 1, 2021, p. 6, Published in: JP. |
Kudeka, Stephan, “Communication Pursuant to Article 94(3) EPC Regarding Application No. 10 770 205.2”, Jun. 8, 2021, p. 6, Published in: EU. |
Brayton, John Joseph, “Office Action Regarding U.S. Appl. No. 15/495,513”, Apr. 14, 2021, p. 10, Published in: US. |
Luque, Renan, “Office Action Regarding U.S. Appl. No. 16/896,709”, May 25, 2021, p. 36, Published in: US. |
Hammond, Crystal, “Office Action Regarding U.S. Appl. No. 17/031,027”, Apr. 28, 2021, p. 9, Published in: US. |
EPO, “Extended European Search Report Regarding Patent Application No. 18877737.9”, Aug. 25, 2021, p. 165, Published in: EP. |
EPO, “Extended Search Report Regarding European Patent Appliication No. 18877322”, Sep. 14, 2021, p. 129, Published in: EP. |
EPO, “Extended European Search Report Regarding Patent Application No. 18878531.5”, Sep. 1, 2021, p. 126, Published in: EP. |
Harry Kim, “International Search Report and Written Opinion Regarding International Application No. PCT/US2020/027927”, Sep. 17, 2021, p. 14, Published in: US. |
Office Action received for European Patent Application Serial No. 11822326.2 dated Oct. 18, 2018, 6 pages. |
Office Action received for Japanese Patent Application Serial No. 2012508593 dated Apr. 19, 2013, 11 pages. |
Office Action received for Japanese Patent Application Serial No. 2013527088 dated Apr. 21, 2015, 10 pages. |
Office Action received for Japanese Patent Application Serial No. 2014523057 dated Apr. 21, 2015, 11 pages. |
Office Action received for Japanese Patent Application Serial No. 2015529905 dated Aug. 22, 2017, 16 pages. |
Office Action received for Japanese Patent Application Serial No. 2015529905 dated Aug. 24, 2017, 14 pages. |
Office Action received for Japanese Patent Application Serial No. 2015529906 dated May 16, 2017, 13 pages. |
Office Action received for Japanese Patent Application Serial No. 2015529939 dated Sep. 19, 2017, 19 pages. |
Office Action received for Japanese Patent Application Serial No. 2016-043215 dated Jan. 25, 2017, 7 pages. |
Office Action received for Japanese Patent Application Serial No. 2018081644 dated Apr. 16, 2019, 21 pages. |
Office Action received for Japanese Patent Application Serial No. 2018138425 dated Mar. 24, 2020, 7 pages. |
Office Action received for Japanese Patent Application Serial No. 2018138425 dated May 22, 2019, 10 pages. |
Office Action received for Korean Patent Application Serial No. 1020117009075 dated Mar. 25, 2013, 2 pages. |
Office Action received for Korean Patent Application Serial No. 1020137007594 dated Jul. 28, 2014, 2 pages. |
Office Action received for Korean Patent Application Serial No. 1020147004544 dated Feb. 3, 2016, 13 pages. |
Office Action received for Korean Patent Application Serial No. 1020157007273 dated Jan. 30, 2018, 8 pages. |
Office Action received for Korean Patent Application Serial No. 1020157007516 dated Feb. 15, 2017, 18 pages. |
Office Action received for Taiwan Patent Application Serial No. 107140922 dated Feb. 1, 2021, 9 pages. |
Office Action received for Taiwanese Patent Applicatio Serial No. 102130565 dated Apr. 11, 2016, 2 pages. |
Office Action received for Taiwanese Patent Application Serial No. 099113815 dated Jan. 27, 2014, 6 pages. |
Office Action received for Taiwanese Patent Application Serial No. 099113815 dated Jun. 18, 2014, 5 pages. |
Office Action received for Taiwanese Patent Application Serial No. 101127182 dated Aug. 11, 2014, 11 pages. |
Office Action received for Taiwanese Patent Application Serial No. 102130565 dated Jul. 14, 2015, 4 pages. |
Office Action received for Taiwanese Patent Application Serial No. 102130984 dated Feb. 19, 2016, 4 pages. |
Office Action received for Taiwanese Patent Application Serial No. 107140924 dated Apr. 28, 2020, 14 pages. |
Office Action Received for Taiwanese Patent Application Serial No. 107140924 dated Jan. 15, 2021, 12 pages. |
Office Action received for Taiwanese Patent Application Serial No. 107140926 dated May 28, 2020, 12 pages. |
Ohachi, T., et al., “Measurement of Nitrogen Atomic Flux for RF-MBE Growth of GaN and AlN on Si Substrates”, J. of Crystal Growth, vol. 311, 2009, pp. 2987-2991. |
Raoux, S., et al., “Remote Microwave Plasma Source for Cleaning Chemical Vapor Deposition Chambers; Technology for Reducing Global Warming Gas Emissions”, J. Vac. Sci. Technol. B, vol. 17, No. 2, Mar./Apr. 1999, pp. 477-485. |
Rauf, S., et al.. , “Nonlinear Dynamics of Radio Frequency Plasma Processing Reactors Powered by Multifrequency Sources”, IEEE Transactions on Plasma Science, vol. 27, No. 5, Oct. 5, 1999, pp. 1329-1338. |
Requirement for Restriction received for U.S. Appl. No. 12/870,837 dated Dec. 19, 2012, 8 pages. |
Requirement for Restriction received for U.S. Appl. No. 13/193,299 dated Aug. 8, 2013, 7 pages. |
Requirement for Restriction received for U.S. Appl. No. 13/193,345 dated Jun. 6, 2013, 8 pages. |
Requirement for Restriction received for U.S. Appl. No. 13/596,976 dated Feb. 23, 2015, 8 pages. |
Requirement for Restriction received for U.S. Appl. No. 13/597,050 dated Jan. 27, 2015, 7 pages. |
Requirement for Restriction received for U.S. Appl. No. 13/597,093 dated Mar. 23, 2015, 9 pages. |
Second Office Action received for Chinese Patent Application Serial No. 201080003206.X dated May 23, 2014, 6 pages. |
Second Office Action received for Chinese Patent Application Serial No. 201710704712.5 dated Sep. 27, 2019, 11 pages. |
Second Office Action received for Chinese Patent Application Serial No. 201711336133.6 dated Jan. 6, 2020, 7 pages. |
Silapunt, R., et al., “Ion Bombardment Energy Control for Selective Fluorocarbon Plasma Etching of Organosilicate Glass”, J. Vac. Sci. Technol, vol. B 22, No. 2, 2004, pp. 826-831. |
Specification for related U.S. Appl. No. 13/173,752, filed Jun. 30, 2011, 48 pages. |
Specification for related U.S. Appl. No. 13/425,159, filed Mar. 20, 2012, 33 pages. |
Third Office Action received for Chinese Patent Application Serial No. 201080003206.X dated Nov. 26, 2014, 6 pages. |
Third Office Action received for Chinese Patent Application Serial No. 201710704712.5 dated Jan. 3, 2020, 8 pages. |
Vahedi, V., et al., “Verification of Frequency Scaling Laws for Capacitive Radio-Frequency Discharges Using Two-Dimensional Simulations”, Phys. Fluids B, , vol. 5, No. 7, Jul. 1993, pp. 2719-2729. |
Wakeham, S.J., et al . . . , “Low Temperature Remote Plasma Sputtering of Indium Tin Oxide for Flexible Display Applications”, Thin Solid Films, vol. 519, 2009, pp. 1355-1358. |
Wang, S.B., et al., “Control of Ion Energy Distribution at Substrates During Plasma Processing”, J. Applied Physics, vol. 88, No. 2, Jul. 15, 2000, pp. 643-646. |
Wendt “Thomson Innovation Patent Export”, Mar. 10, 2009, 10 pages. |
Xiubo, et al., “Charging of Dielectric Substrate Materials During Plasma Immersion lon Implantation”, Nuclear Instruments and Methods in Physics Research B, vol. 187, 2002, pp. 485-491. |
Yun, Y.B., et al., “Effects of Various Additive Gases on Chemical Dry Etching Rate Enhancement of Low-k SiOCH Layer in F2/Ar Remote Plasmas”, Thin Solid Films, vol. 516, 2008, pp. 3549-3553. |
Fiona Doherty, Patent Cooperation Treaty, International Preliminary On Patentability, Aug. 31, 2023, The International Bureau Of WIPO, Switzerland. |
Hockstrasser, European Search Report, Jul. 20, 2023, European Patent Office, Munich, Germany. |
Fiona Doherty, Patent Cooperation Treaty, International Preliminary On Patentability, Aug. 24, 2023, The International Bureau Of WIPO, Switzerland. |
TIPO, Taiwanese Office Action Patent Application No. 111150645, Dated Oct. 18, 2023. |
Takashi Maki, Notice of Reasons For Rejection, Patent Application No. 2020-545048, Nov. 14, 2023. |
Final Office Action received for U.S. Appl. No. 12/767,775 dated Dec. 15, 2014, 37 pages. |
Final Office Action received for U.S. Appl. No. 12/767,775 dated Sep. 10, 2013, 30 pages. |
Final Office Action received for U.S. Appl. No. 13/193,299 dated Dec. 4, 2015, 30 pages. |
Final Office Action received for U.S. Appl. No. 13/193,299 dated Sep. 26, 2014, 37 pages. |
Final Office Action received for U.S. Appl. No. 13/193,345 dated Jan. 15, 2016, 33 pages. |
Final Office Action received for U.S. Appl. No. 13/193,345 dated Jul. 7, 2014, 26 pages. |
Final Office Action received for U.S. Appl. No. 13/596,976 dated Apr. 5, 2017, 23 pages. |
Final Office Action received for U.S. Appl. No. 13/596,976 dated Jul. 1, 2016, 34 pages. |
Final Office Action received for U.S. Appl. No. 13/597,032 dated Apr. 9, 2015, 32 pages. |
Final Office Action received for U.S. Appl. No. 13/597,050 dated Mar. 10, 2016, 19 pages. |
Final Office Action received for U.S. Appl. No. 13/597,093 dated Jul. 8, 2016, 25 pages. |
First Office Action received for Chinese Patent Application Serial No. 201080003206.X dated Sep. 4, 2013, 15 pages. |
First Office Action received for Chinese Patent Application Serial No. 201180046783.1 dated Mar. 24, 2015, 18 pages. |
First Office Action received for Chinese Patent Application Serial No. 201280047162.X dated Sep. 6, 2015, 18 pages. |
First Office Action received for Chinese Patent Application Serial No. 20171074712.5 dated Feb. 22, 2019, 9 pages. |
First Office Action received for Chinese Patent Application Serial No. 201711336133.6 dated Mar. 4, 2019, 16 pages. |
Fourth Office Action received for Chinese Patent Application Serial No. 201080003206.X dated Jun. 10, 2015, 8 pages. |
Fourth Office Action received for Chinese Patent Application Serial No. 201710704712.5 dated Apr. 1, 2020, 7 pages. |
Gangoli, S.P., et al., “Production and transport chemistry of atomic fluorine in remote plasma source and cylindrical reaction chamber”, J. Phys. D: Appl. Phys., vol. 40, Aug. 16, 2007, pp. 5140-5154. |
George, M.A., et al., “Silicon Nitride Arc Thin Films by New Plasma Enhanced Chemical Vapor Deposition Source Technology”, Article downloaded from www.generalplasma.com, Jul. 7, 2011, pp. 1-5. |
Giangregorio, M.M., et al., “Role of Plasma Activation in Tailoring the Nanostructure of Multifunctional Oxides Thin3 Films”, Applied Surface Sci., vol. 255, Sep. 10, 2008, pp. 5396-5400. |
Heil, S.B.S., et al., “Deposition ofTiN and HfO2 in a Commercial 200mm Plasma Atomic Layer Deposition Reactor”, J. Vac. Sci. Technol. A, Sep./Oct. 2007, Jul. 31, 2007, vol. 25, No. 5, pp. 1357-1366. |
Honda, S., et al., “Hydrogenation of Polycrystalline Silicon Thin Films”, Thin Solid Films, vol. 501, Oct. 5, 2005, pp. 144-148. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2010/032582 dated Nov. 10, 2011, 8 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2011/047467 dated Mar. 14, 2013, 7 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2012/048504 dated Feb. 6, 2014, 11 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2013/056634 dated Mar. 12, 2015, 7 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2013/056647 dated Mar. 12, 2015, 7 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2013/056657 dated Mar. 12, 2015, 8 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2013/056659 dated Mar. 12, 2015, 8 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2013/056851 dated Mar. 12, 2015, 8 pages. |
International Preliminary Report On Patentability Received for International PCT Application Serial No. PCT/US2018/061653 dated May 28, 2020, 9 pages. |
International Preliminary Report on Patentability received for International PCT Application Serial No. PCT/US2018/061671 dated May 28, 2020, 14 pages. |
International Preliminary Report on Patentability received International Application Serial No. PCT/US2018/061575 dated May 28, 2020, 9 pages. |
International Search Report and Writen Opinion received for International PCT Application Serial No. PCT/US2012/048504 dated Sep. 17, 2012, 13 pages . . . . |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2010/032582 dated Feb. 21, 2011, 10 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2011/047467 dated Nov. 24, 2011, 9 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2012/022380 dated Mar. 14, 2012, 11 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2012/029953 dated May 28, 2012, 11 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2013/056634 dated Nov. 15, 2013, 10 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2013/056647 dated Oct. 30, 2013, 10 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2013/056657 dated Oct. 28, 2013, 11 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2013/056659 dated Nov. 8, 2013, 11 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2013/056851 dated Nov. 18, 2013, 11 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2018/061575 dated Mar. 6, 2019, 12 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2018/061653 dated Mar. 8, 2019, 10 pages. |
International Search Report and Written Opinion received for International PCT Application Serial No. PCT/US2018/061671 dated Mar. 13, 2019, 17 pages. |
Japanese Office Action re Application No. 2012-508593, Sep. 11, 2013, p. 7. |
Jeon, M., et al., “Hydrogenated Amorphous Silicon Film as Intrinsic Passivation Layer Deposited at Various Temperatures using RF remote-PECVD technique”, Current Applied Physics, vol. 10, No. 2010, Nov. 12, 2009, pp. S237-S240. |
Kim, J.Y., et al., “Remote Plasma Enhanced Atomic Layer Deposition ofTiN Thin Films Using Metalorganic Precursor”, J. Vac. Sci. Technol. A, vol. 22, No. 1, Jan./Feb. 2004, Nov. 13, 2003, pp. 8-12. |
CNIPA, “First Office Action Issued in Application No. 201880086817.1”, Dec. 9, 2022, p. 34, Published in: CN. |
Bruno, G., et al., “Real Time Ellipsometry for Monitoring Plasma-Assisted Epitaxial Growth of GaN”, Applied Surface Sci., vol. 253, 2006, pp. 219-223. |
Bryns, B., et al . . . , “A VHF Driven Coaxial Atmospheric Air Plasma: Electrical and Optical Characterization”, Dep't of Nuclear Engr., 2011, pp. 1-18. |
Buzzi, F.L., et al., “Energy Distribution of Bombarding lons in Plasma Etching of Dielectrics”, “AVS 54th International Symposium”, Oct. 15, 2007, 18 pages. |
Decision Of Rejection received for Chinese Patent Application Serial No. 201710704712.5 dated Aug. 10, 2020, 8 pages. |
Emsellem, G., “Electrodeless Plasma Thruster Design Characteristics”, 41st Joint Propulsion Conference, Jul. 11, 2005, 22 pages. |
European Search Report received for European Patent Application Serial No. EP11822326 dated Oct. 9, 2015, 3 pages. |
Extended European Search Report received for European Patent Application Serial No. 10770205.2 dated Jan. 30, 2013, 8 pages. |
Extended European Search Report received for European Patent Application Serial No. 18878531.5 dated Sep. 1, 2021, 126 pages. |
Final Office Action received for U.S. Appl. No. 17/150,633 dated Jul. 27, 2022, 48 pages. |
TIPO, “Office Action Regarding Taiwanese Patent Application No. 10714924”, Aug. 20, 2021, p. 7, Published in: TW. |
International Preliminary Report on Patentability Chapter I received for International PCT Application Serial No. PCT/US2020/041771 dated Jan. 27, 2022, 10 pages. |
Non-Final Office Action received for U.S. Appl. No. 16/278,822 dated Aug. 2, 2021, 11 pages. |
Non-Final Office Action received for U.S. Appl. No. 17/150,633 dated Nov. 24, 2021, 52 pages. |
Non-Final Office Action received for U.S. Appl. No. 17/171,164 dated Oct. 15, 2021, 60 pages. |
Notice of Reasons for Rejection, Japanese Official Office Action Translation, Apr. 7, 2023, Japanese Patent Office. |
CNIPA, “Notification of the 3rd Office Action Issued in Application No. 201711336133.6”, Oct. 10, 2020, p. 21, Published in: CN. |
Kudelka, Stephan, “Communication Pursuant to Article 94(3) EPC Issued in Application No. 10 770 205.2”, Oct. 23, 2020, p. 4, Published in: EP. |
Tran, Anh Q, “Office Action Regarding U.S. Appl. No. 14/740,955”, Feb. 22, 2016, p. 16, Published in: US. |
Uda, Sumio, “Office Action Regarding Japanese Patent Application No. 2017-091857”, Feb. 2, 2018, p. 10, Published in: JP. |
Tran, Anh Q, “Office Action Regarding U.S. Appl. No. 13/343,576”, Nov. 13, 2014, p. 24, Published in: US. |
The Korean Intellectual Property Office, “Korean Decision of Rejection re Application No. 1020137019332”, Jan. 20, 2016, p. 6, Published in: KR. |
Hayashi, Yasushi, “Japanese Office Action re Application No. 2013-547731”, Jul. 28, 2015, p. 13, Published in: JP. |
Hayashi, Yasushi, “Japanese Office Action re Application No. 2013-547731”, Sep. 30, 2014, p. 8, Published in: JP. |
Korean Intellectual Property Office, “Korean Office Action re Application No. 10-2013-7019332”, May 29, 2015, p. 16, Published in: KR. |
Mitrovic, Bayer, “International Search Report and Written Opinion re Application No. PCT/US12/20219”, Feb. 22, 2012, p. 10, Published in: AU. |
Becamel, Philippe, “International Preliminary Report on Patentability re Application No. PCT/US2012/020219”, Jul. 18, 2013, p. 7, Published in: CH. |
Park, Hye Lyun International Search Report and Written Opinion of the International Searching Authority PCT Application Serial No. PCT/US2022/016278 dated Feb. 14, 2022, 8 pages. Korea. |
Hochstrasser, M, European Search Report, Jul. 20, 2023, European Patent Office. |
Krolak, M, “Matthew Krolak's MyElectricEngine.Com Megnetoplasmadynamic (MPD) Thruster Design”, Webpage downloaded from http://myelectricengine.com/projects/mpdthruster/mpdthruster.html, Apr. 28, 2011, 7 pages. |
Kuo, M.S., et al., “Influence of C4F8/Ar-based etching and H2-based remote plasma ashing processes on ultralow ? Materials Modifications”, J. Vac. Sci. Technol. B, vol. 28, No. 2, Mar./Apr. 2010, Mar. 19, 2010, pp. 284-294. |
Non Final Office Action received for U.S. Appl. No. 12/767,775 dated Apr. 25, 2013, 28 pages. |
Non Final Office Action received for U.S. Appl. No. 12/767,775 dated Jul. 1, 2014, 48 pages. |
Non Final Office Action received for U.S. Appl. No. 12/767,775 dated Oct. 17, 2012, 33 pages. |
Non Final Office Action received for U.S. Appl. No. 12/870,837 dated Apr. 9, 2015, 40 pages. |
Non Final Office Action received for U.S. Appl. No. 12/870,837 dated Mar. 22, 2013, 46 pages. |
Non Final Office Action received for U.S. Appl. No. 13/193,299 dated Dec. 18, 2013, 43 pages. |
Non Final Office Action received for U.S. Appl. No. 13/193,299 dated May 21, 2015, 24 pages. |
Non Final Office Action received for U.S. Appl. No. 13/193,345 dated Apr. 16, 2015, 34 pages. |
Non Final Office Action received for U.S. Appl. No. 13/193,345 dated Nov. 7, 2013, 36 pages. |
Non Final Office Action received for U.S. Appl. No. 13/596,976 dated Nov. 6, 2015, 77 pages. |
Non Final Office Action received for U.S. Appl. No. 13/596,976 dated Nov. 25, 2016, 20 pages. |
Non Final Office Action received for U.S. Appl. No. 13/597,032 dated Jun. 20, 2014, 42 pages. |
Non Final Office Action received for U.S. Appl. No. 13/597,050 dated Jul. 17, 2015, 86 pages. |
Non Final Office Action received for U.S. Appl. No. 13/597,093 dated Nov. 5, 2015, 76 pages. |
Non Final Office Action received for U.S. Appl. No. 14/011,305 dated Dec. 4, 2014, 28 pages. |
Non Final Office Action received for U.S. Appl. No. 14/606,857 dated Apr. 8, 2015, 51 pages. |
Non Final Office Action received for U.S. Appl. No. 15/667,239 dated Jun. 24, 2020, 131 pages. |
Non Final Office Action received for U.S. Appl. No. 16/193,790 dated Sep. 4, 2019, 86 pages. |
Non Final Office Action received for U.S. Appl. No. 16/194,104 dated Aug. 1, 2019, 83 pages. |
Non Final Office Action received for U.S. Appl. No. 16/194,125 dated Dec. 12, 2019, 88 pages. |
Non Final Office Action received for U.S. Appl. No. 16/278,822 dated Aug. 2, 2021, 107 pages. |
Non-Final Office Action received for U.S. Appl. No. 15/495,513 dated Jul. 2, 2020, 87 pages. |
Non-Final Office Action received for U.S. Appl. No. 16/246,996 dated Dec. 12, 2019, 85 bages. |
Non-Final Office Action received for U.S. Appl. No. 16/270,391 dated Dec. 12, 2019, 78 pages. |
Non-Final Office Action received for U.S. Appl. No. 16/803,020 dated Apr. 22, 2020, 36 pages. |
Notice of Allowance received for U.S. Appl. No. 16/193,790 dated Jan. 23, 2020, 16 pages. |
Notice of Allowance received for U.S. Appl. No. 16/193,790 dated Nov. 20, 2019, 40 pages. |
Notice of Allowance received for U.S. Appl. No. 16/194,125 dated Jun. 18, 2020, 42 pages. |
Notice of Allowance received for U.S. Appl. No. 16/246,996 dated Jun. 18, 2020, 27 pages. |
Notice of Allowance received for U.S. Appl. No. 16/270,391 dated Jun. 16, 2020, 36 pages. |
Notice of Allowance received for U.S. Appl. No. 16/803,020 dated Sep. 14, 2020, 100 pages. |
Notice of Allowance received for U.S. Appl. No. 17/031,027 dated Feb. 3, 2022, 8 pages. |
Notice of Allowance received for U.S. Appl. No. 17/031,027 dated Oct. 20, 2021, 81 pages. |
Notice of Allowance received for U.S. Appl. No. 17/150,633 dated Nov. 15, 2022, 42 pages. |
Notice Of Grounds For Rejection received for Korean Patent Application Serial No. 1020157007771 dated May 31, 2018, 4 pages. |
Notice Of Grounds For Rejection received for Korean Patent Application Serial No. 1020187029468 dated Feb. 7, 2019, 6 pages. |
Notice of Reasons for Rejection received for Japanese Patent Application Serial No. 2020545048 dated Aug. 19, 2022, 12 pages. |
Office Action received for Chinese Patent Application Serial No. 201180046783.1 dated Dec. 7, 2016, 9 pages. |
Office Action received for Chinese Patent Application Serial No. 201180046783.1 dated Dec. 8, 2015, 9 pages. |
Office Action received for Chinese Patent Application Serial No. 201180046783.1 dated May 17, 2016, 8 pages. |
Office Action received for Chinese Patent Application Serial No. 201280047162.X dated Apr. 26, 2016, 7 pages. |
Office Action received for Chinese Patent Application Serial No. 201280047162.X dated Oct. 24, 2016, 31 pages. |
Office Action received for Chinese Patent Application Serial No. 201380056068.5 dated Jun. 12, 2017, 16 pages. |
Office Action received for Chinese Patent Application Serial No. 201380056068.5 dated Oct. 17, 2016, 15 pages. |
Office Action received for Chinese Patent Application Serial No. 201380056070.2 dated Aug. 15, 2016, 25 pages. |
Office Action received for European Patent Application Serial No. 10770205.2 dated Nov. 2, 2017, 30 pages. |
Office Action received for European Patent Application Serial No. 11822326.2 dated Apr. 3, 2017, 4 pages. |
Office Action received for European Patent Application Serial No. 11822326.2 dated Feb. 27, 2018, 5 pages. |
Ding Ruiping, Notification of the 2nd Office Action, National Intellectual Property Administration of The People's Republic of China, Aug. 31, 2023, Patent Examination Cooperation Center. |
EPO, Communication pursuant to Article 94(3) EPC regarding Application No. 18878531.5, Apr. 18, 2024, 6 pages, Published in EP. |
KIPO, Notice of Ground of Rejection issued in Application No. 10-2020-7017361, Mar. 27, 2024, 22 pages, Published in KR. |
Le, Tung X, Office Action issued in U.S. Appl. No. 18/450,652, Apr. 1, 2024, 39 pages, Published in US. |
Luque, Renan, Final Office Action issued in U.S. Appl. No. 17/902,987, Jun. 12, 2024, 40 pages, Published in US. |
Luque, Renan, Office Action issued in U.S. Appl. No. 18/450,635, Mar. 28, 2024, 58 pages, Published in US. |
EPO, Extended European Search Report issued in EP Application No. 24170540.9, Jul. 23, 2024. |
Number | Date | Country | |
---|---|---|---|
20210202209 A1 | Jul 2021 | US |
Number | Date | Country | |
---|---|---|---|
62588255 | Nov 2017 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 16194125 | Nov 2018 | US |
Child | 17031027 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 17031027 | Sep 2020 | US |
Child | 17181382 | US |